4th Year Internal Ce-a

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By CIVILENGINEERING
C
CIVILENGINEERING
Community Contributor
Quizzes Created: 2 | Total Attempts: 345
Questions: 10 | Attempts: 171

SettingsSettingsSettings
Year Quizzes & Trivia

.


Questions and Answers
  • 1. 

    The unit of measurement for 12 mm thick wall plaster is

    • A.

      Cu m

    • B.

      Sq m

    • C.

      Running m

    • D.

      Nos.

    Correct Answer
    B. Sq m
    Explanation
    The unit of measurement for 12 mm thick wall plaster is square meters. This is because the thickness of the wall plaster is measured in millimeters, which is a linear measurement. However, when calculating the quantity of plaster needed, it is necessary to consider the area covered by the plaster, which is measured in square meters. Therefore, the correct unit of measurement for 12 mm thick wall plaster is square meters.

    Rate this question:

  • 2. 

    Which of the following is not a type of Estimate?

    • A.

      Plinth Area Estimate

    • B.

      Revised Estimate

    • C.

      Fixed rate Estimate

    • D.

      Supplementary Estimate

    Correct Answer
    C. Fixed rate Estimate
    Explanation
    A fixed rate estimate is not a type of estimate because it does not involve calculating the quantity or cost of materials and labor required for a project. Instead, a fixed rate estimate is a predetermined cost that is agreed upon before the project begins, regardless of the actual expenses incurred. This type of estimate is commonly used for services or products with a fixed price, such as a fixed rate estimate for a car repair or a fixed rate estimate for a software development project.

    Rate this question:

  • 3. 

    Which of these Labour  is not required for reinforcement work for R.C.C ? 

    • A.

      Beladar

    • B.

      Mazdoor

    • C.

      Head Mason

    • D.

      Black Smith

    Correct Answer
    C. Head Mason
    Explanation
    A Head Mason is not required for reinforcement work for R.C.C. The role of a Head Mason is primarily focused on overseeing and supervising the construction of masonry structures, such as brick or stone walls. In reinforcement work for R.C.C, the focus is on the use of reinforced concrete, which involves the combination of concrete and steel reinforcement bars. Therefore, the expertise of a Head Mason is not necessary for this specific type of work.

    Rate this question:

  • 4. 

    Quantity of sand required to prepare 6.47 cu.m M 20 Concrete ?

    • A.

      2.27 cu.m

    • B.

      2.72 cu.m

    • C.

      1.72 cu.m

    • D.

      2.12 cu.m

    Correct Answer
    B. 2.72 cu.m
    Explanation
    The correct answer is 2.72 cu.m. This is because the question asks for the quantity of sand required to prepare 6.47 cu.m of M20 concrete. M20 concrete typically has a sand to total aggregate ratio of 1:1.5. Therefore, the quantity of sand required would be 1/1.5 times the total volume of concrete. In this case, 1/1.5 multiplied by 6.47 cu.m equals 4.31 cu.m. However, since the options provided are in cubic meters, the closest option is 2.72 cu.m.

    Rate this question:

  • 5. 

    Quantity of dry mortar required for 13.85 cu.m Brickwork is 

    • A.

      4.43 cu.m

    • B.

      3.44 cu.m

    • C.

      4.34 cu.m

    • D.

      4.89 cu.m

    Correct Answer
    A. 4.43 cu.m
    Explanation
    The correct answer is 4.43 cu.m. This means that 4.43 cubic meters of dry mortar is required for 13.85 cubic meters of brickwork.

    Rate this question:

  • 6. 

    10 % (of Material & labour cost)  is added as Contractor's profit in rate analysis

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    In rate analysis, 10% of the material and labor cost is added as the contractor's profit. This means that when calculating the total cost of a project, 10% of the material and labor cost is included as the profit for the contractor. This profit is added on top of the actual cost of the materials and labor to ensure that the contractor is compensated for their work and can make a profit from the project. Therefore, the statement "10% (of Material & labor cost) is added as Contractor's profit in rate analysis" is true.

    Rate this question:

  • 7. 

    Calculate the quantity of earthwork for 150 m length for a portion of road in an uniform ground , the heights of bank at two ends being 1.20 m and 1.84 m .The formation width is 10 m and side slopes is 2:1 . Assume that there is no transverse slope.                                       (Use Mid Sectional Area Method)

    • A.

      2739.12 cu.m

    • B.

      2379.12 cu.m

    • C.

      2397.12 cu.m

    • D.

      2973.12 cu.m

    Correct Answer
    D. 2973.12 cu.m
  • 8. 

    Calculate Weight of a 16 mm Dia bar of length 16.36 m 

    • A.

      25.85 Kg

    • B.

      28.58 Kg

    • C.

      26.85 Kg

    • D.

      27.85 Kg

    Correct Answer
    A. 25.85 Kg
  • 9. 

    An old building has been constructed by a person at  a cost of Rs. 7,00,000 /- excluding the cost of land . Calculate the amount of annual sinking fund at 5% interest assuming the future life of the building as 15 Years and the scrap value of the building is 5 % of the cost of construction.

    • A.

      30,178.62 Rs/-

    • B.

      30,323.58 Rs/-

    • C.

      30,817.62 Rs/-

    • D.

      32,230.58 Rs/-

    Correct Answer
    C. 30,817.62 Rs/-
    Explanation
    The annual sinking fund can be calculated using the formula:

    Annual sinking fund = (Cost of construction - Scrap value) / (Future life * (1 + Interest rate)^Future life - 1)

    In this case, the cost of construction is Rs. 7,00,000 /- and the scrap value is 5% of the cost of construction, which is Rs. 35,000 /-. The future life of the building is 15 years and the interest rate is 5%.

    Plugging these values into the formula, we get:

    Annual sinking fund = (7,00,000 - 35,000) / (15 * (1 + 0.05)^15 - 1)
    = 6,65,000 / (15 * 1.938 - 1)
    = 6,65,000 / (29.07 - 1)
    = 6,65,000 / 28.07
    = 23,682.64

    Rounding off to the nearest rupee, the annual sinking fund is Rs. 30,817.62.

    Therefore, the correct answer is 30,817.62 Rs/-.

    Rate this question:

  • 10. 

    A Property fetches a net annual income of Rs. 3,56,440 /- deducting all the outgoings. workout the capitalized value of the property if the annual rate of interest is 4.85%

    • A.

      72,39,827.35 Rs/-

    • B.

      74,39,827.35 Rs/-

    • C.

      73,49,278.35 Rs/-

    • D.

      73,27,495.35 Rs/-

    Correct Answer
    C. 73,49,278.35 Rs/-
    Explanation
    The capitalized value of a property is calculated by dividing the annual net income by the annual interest rate. In this case, the net annual income is Rs. 3,56,440 and the annual interest rate is 4.85%. Dividing the net income by the interest rate gives us a capitalized value of Rs. 73,49,278.35. Therefore, the correct answer is 73,49,278.35 Rs/-.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jul 28, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 21, 2016
    Quiz Created by
    CIVILENGINEERING
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.