1.
In the TML, A PERMIT ACCEPTOR is also known as:-
Correct Answer
B. Initiator
Explanation
In the TML, a PERMIT ACCEPTOR is also known as an Initiator. This term refers to the person or entity responsible for initiating or requesting a permit. They are the ones who start the process of obtaining a permit and are typically responsible for ensuring that all necessary requirements and documentation are met before the permit is issued.
2.
Which of the following is not a HAZARDOUS ENERGY SOURCES according to the TML LOTO Standard & Procedure.
Correct Answer
A. Sound Energy
Explanation
According to the TML LOTO Standard & Procedure, sound energy is not considered a hazardous energy source. This means that it does not pose a risk of injury or harm to workers when it comes to energy isolation and control procedures. The other options listed, such as thermal energy, pneumatic energy, and nuclear energy, are all recognized as hazardous energy sources and require specific precautions and procedures to ensure worker safety.
3.
The definition of excavation and the precautions to be taken during excavation is mentioned in which annexure:-.
Correct Answer
B. Annexure II
Explanation
The correct answer is Annexure II. Annexure II contains the definition of excavation and provides information about the precautions that need to be taken during excavation. It is likely that this annexure specifically addresses the topic of excavation and is the appropriate section to refer to for understanding the definition and precautions associated with it.
4.
Which is not the duty of the ISSUER?
Correct Answer
A. FIRE WATCH
Explanation
The duty of the issuer is not to perform the task of FIRE WATCH. The issuer is responsible for arranging for the authorized gas tester, ensuring all the permits and JSA are in place, and knowing and identifying all potential hazards. However, the task of FIRE WATCH, which involves monitoring and preventing fires, is not listed as one of the duties of the issuer.
5.
The Work Permit shall always operate on Custodian concept.
Correct Answer
A. True
Explanation
The statement means that the Work Permit will always function based on the Custodian concept. This implies that a person or entity will be responsible for overseeing and managing the work permit process. This Custodian will likely handle tasks such as issuing, renewing, and monitoring work permits, ensuring compliance with regulations and laws. The statement suggests that the Custodian concept is a fundamental aspect of the Work Permit system and will consistently be applied.
6.
Among these which is not a special case for the associated work permits?
Correct Answer
D. Cold Work
Explanation
Cold work is not a special case for the associated work permits because it refers to activities that are carried out in cold weather conditions, which are not considered to be high-risk or requiring specific permits. On the other hand, hot work involves activities that generate heat or sparks, work at height involves tasks performed above ground level, and evacuation work involves emergency procedures for evacuating a site. These three activities are considered high-risk and require special permits to ensure safety.
7.
What is the minimum % of Oxygen that should be available there for the worker survival in CONFINED SPACE ?
Correct Answer
C. 19.5
Explanation
The minimum % of Oxygen that should be available for worker survival in a confined space is 19.5%. This is because oxygen levels below this percentage can lead to oxygen deficiency, which can cause symptoms such as dizziness, confusion, and loss of consciousness. In extreme cases, it can even result in death. Therefore, it is crucial to ensure that the confined space has adequate oxygen levels to protect the workers' health and safety.
8.
For cancelling the permit which section of permit should be referred ?
Correct Answer
C. Saction I
Explanation
One possible explanation for the correct answer, "Saction I," is that it refers to the specific section in the permit documentation that outlines the process for canceling a permit. This section likely provides the necessary information and requirements for initiating the cancellation procedure, ensuring that the correct steps are followed and any necessary documentation is submitted.
9.
A Permit Holder can hold n number of permits? Here " n " is:-
Correct Answer
D. 1
Explanation
The answer is 1 because the statement says "A Permit Holder can hold n number of permits". This means that a Permit Holder can hold any number of permits, so the value of "n" can be any positive integer. Therefore, option 1 is the correct answer as it represents any number of permits.
10.
The maximum depth that is allowed in trench excavation(in metres):-
Correct Answer
A. 1.5
Explanation
The maximum depth allowed in trench excavation is 1.5 meters. This limit is set to ensure the safety of workers and prevent accidents such as cave-ins or collapses. Going deeper than 1.5 meters increases the risk of the trench walls becoming unstable and posing a danger to workers. Therefore, it is essential to adhere to this maximum depth to maintain a safe working environment.
11.
This annexure is used for the temporary removal of LOTO for 'Test & Trial':-
Correct Answer
D. Annexure VII
12.
Any deviation of the Hot Work Permit standard shall be approved by:-
Correct Answer
B. Plant Head
Explanation
The correct answer is Plant Head. The Plant Head is the highest authority in the plant and is responsible for making decisions regarding the operation and safety of the plant. Therefore, any deviation from the Hot Work Permit standard should be approved by the Plant Head to ensure that proper safety measures are in place.
13.
General Work Permit can be cancelled by Permit Issuer due to plant emergency:-
Correct Answer
A. True
Explanation
A general work permit is a document that allows an individual to work in a specific location. In the event of a plant emergency, the permit issuer may need to cancel the permit to ensure the safety of the workers and the plant. This could be due to various reasons such as a hazardous situation, equipment failure, or natural disaster. Therefore, it is true that a general work permit can be cancelled by the permit issuer in case of a plant emergency.
14.
No changes are allowed once a PTW is issued and the copies are distributed:-
Correct Answer
A. True
Explanation
Once a PTW (Permit to Work) is issued and the copies are distributed, no changes are allowed. This means that the conditions and restrictions specified in the PTW must be followed without any alterations. This is important for maintaining safety and ensuring that all necessary precautions are taken before carrying out any work. Any changes or modifications to the PTW after it has been issued can lead to confusion, potential hazards, and a breach in safety protocols. Therefore, it is crucial to adhere to the original PTW without making any changes.
15.
Fire Watch shall monitor the work site for " ……….." Minutes after the hot-work is over.
Correct Answer
B. 30 Min
Explanation
Fire Watch shall monitor the work site for 30 minutes after the hot-work is over. This duration allows for sufficient time to ensure that there are no remaining hot spots or potential fire hazards after the completion of the hot-work. It is important for the Fire Watch to remain vigilant during this period to promptly respond to any signs of fire or smoke. Monitoring for 30 minutes helps to minimize the risk of fire incidents and ensures the safety of the work site and personnel.
16.
Issuer is the one who is responsible for safe isolation of the electrical Equipments:-
Correct Answer
B. False
Explanation
The issuer is not responsible for the safe isolation of electrical equipment. The correct answer is false. It is the duty of the employer or the person in control of the equipment to ensure its safe isolation. The issuer may provide guidelines or instructions, but ultimately the responsibility lies with the employer or person in control.
17.
Apex Committee deploy required resources to ensure that the PTW system is functioning.
Correct Answer
A. True
Explanation
The statement is suggesting that the Apex Committee is responsible for deploying the necessary resources to ensure that the PTW (Permit to Work) system is functioning properly. This implies that the Apex Committee plays a crucial role in ensuring the effectiveness and efficiency of the PTW system within an organization or project. Therefore, the answer "True" indicates that the statement is accurate in describing the responsibilities of the Apex Committee in relation to the PTW system.
18.
Elaborate the " Take " word in Take 2 :-
Correct Answer
C. Talk Action Knowledge Equipment
Explanation
The word "Take" in "Take 2" refers to the action of talking, performing an action, having knowledge, and using equipment. It implies that in the second iteration or attempt, the individual or group will engage in a conversation or discussion, carry out a specific action or task, possess the necessary knowledge, and utilize the required equipment or tools.
19.
Upto how many day permit can be taken at once ?
Correct Answer
D. 7 Days
Explanation
Permits can be taken for a maximum of 7 days at once. This means that individuals can obtain permission to engage in a certain activity or access a particular area for a period of up to one week. It is important to note that this answer assumes that the question is referring to the maximum duration of a permit and not any specific context or regulation.
20.
Authorized Gas Tester shall be appointed by:-
Correct Answer
D. Custodian/ Issuer
Explanation
The Authorized Gas Tester is responsible for conducting gas tests in a specific area to ensure that it is safe for workers to enter. The Custodian/ Issuer, who is in charge of issuing permits for work in confined spaces, would be the appropriate person to appoint the Authorized Gas Tester. They would have the knowledge and authority to select a qualified individual for this role.
21.
When canceling General Work Permit, the Special Work Permit associated with the General Work Permit is automatically canceled.
Correct Answer
A. True
Explanation
When canceling a General Work Permit, the Special Work Permit that is linked to it is also canceled automatically. This means that if a General Work Permit is revoked or terminated, any Special Work Permit that was granted based on it will also be invalidated. Therefore, the statement "When canceling General Work Permit, the Special Work Permit associated with the General Work Permit is automatically canceled" is true.
22.
While a permit is due for renewal and/or the permit is under renewal process, Initiator shall not start working on the job.
Correct Answer
A. True
Explanation
During the renewal process of a permit, the initiator is not allowed to start working on the job. This implies that the permit must be fully renewed before any work can commence. Therefore, the statement is true.
23.
Acetylene gas shall not be used under any conditions at pressures in excess of :-
Correct Answer
C. 15 psig
Explanation
Acetylene gas is highly flammable and can become unstable at high pressures. It can decompose explosively if subjected to pressures above its safe limit. Therefore, it is important to not use acetylene gas at pressures exceeding 15 psig to prevent any potential accidents or explosions.
24.
PTW Standard refresher training required:-
Correct Answer
B. Once in 2 Year
Explanation
Employees are required to undergo PTW (Permit to Work) Standard refresher training once every two years. This training is necessary to ensure that employees are updated on the latest safety protocols and procedures related to permit to work systems. By refreshing their knowledge and skills every two years, employees can maintain a high level of safety awareness and competency in carrying out work activities that require a permit to work.
25.
As per Standard Internal Self Audit shall be carried out in every:-
Correct Answer
B. Three Month
Explanation
Standard internal self-audit should be carried out every three months. This ensures that regular checks are conducted to assess the effectiveness of internal controls, identify any potential risks or weaknesses, and make necessary improvements. By conducting audits every three months, organizations can maintain a proactive approach to risk management and ensure compliance with internal policies and procedures. This frequency allows for timely identification and resolution of issues, helping to maintain the integrity and efficiency of the organization's operations.