PMP Itto Project Integration Management

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Budhines
B
Budhines
Community Contributor
Quizzes Created: 1 | Total Attempts: 339
Questions: 18 | Attempts: 341

SettingsSettingsSettings
PMP Itto Project Integration Management - Quiz

PMP ITTO Questions for Project Integration Management


Questions and Answers
  • 1. 

    The following are all inputs to the Develop Project Charter process except:

    • A.

      Project Statement of Work

    • B.

      Business Case

    • C.

      Contract

    • D.

      EEF (Enterprise Environmental Factors)

    • E.

      OPA (Organizational Process Assets)

    • F.

      Preliminary Scope Statement

    Correct Answer
    F. Preliminary Scope Statement
    Explanation
    The Develop Project Charter process involves creating a document that formally authorizes the existence of a project. This document includes key information such as the project's objectives, stakeholders, and high-level requirements. The inputs to this process are typically the Project Statement of Work, Business Case, Contract, EEF (Enterprise Environmental Factors), and OPA (Organizational Process Assets). The Preliminary Scope Statement, on the other hand, is not an input to this process. It is a document that outlines the project's initial scope and is typically created during the Define Scope process.

    Rate this question:

  • 2. 

    Which of the following is an output of Develop Project Charter process?

    • A.

      Project Charter

    • B.

      Project Management Plan

    • C.

      Schedule

    • D.

      WBS and WBS Dictionary

    Correct Answer
    A. Project Charter
    Explanation
    The output of the Develop Project Charter process is the Project Charter. The Project Charter is a document that formally authorizes the existence of a project, provides the project manager with the authority to apply organizational resources to project activities, and defines the high-level project objectives and scope. It is a key document that outlines the project's purpose, objectives, stakeholders, and high-level requirements. The Project Charter is typically developed by the project sponsor or initiator and is used to gain approval and support for the project.

    Rate this question:

  • 3. 

    All of the following are inputs to the Develop Project Management Plan process except:

    • A.

      Project Charter

    • B.

      Outputs from planning process

    • C.

      EEF (Enterprise Environmental Factors)

    • D.

      OPA (Organizational Project Assets)

    • E.

      Define Stakeholders

    Correct Answer
    E. Define Stakeholders
    Explanation
    The Develop Project Management Plan process involves creating a comprehensive document that outlines how the project will be executed, monitored, and controlled. Inputs to this process typically include the project charter, which provides the project's high-level objectives and authorization. Outputs from the planning process, such as the scope statement and work breakdown structure, also serve as inputs as they provide detailed information about the project's deliverables and activities. Additionally, the enterprise environmental factors (EEF) and organizational project assets (OPA) are considered inputs as they provide external and internal influences and resources that can impact the project. However, defining stakeholders is not an input to this process as it is a separate process that identifies and analyzes individuals or groups who may have an interest in or be affected by the project.

    Rate this question:

  • 4. 

    What is an output of Develop Project Management Plan process?

    • A.

      Project Management Plan

    • B.

      Project Charter

    • C.

      Quality Audit

    • D.

      Contracts

    Correct Answer
    A. Project Management Plan
    Explanation
    The output of the Develop Project Management Plan process is the Project Management Plan. This plan is a comprehensive document that outlines the approach, processes, and procedures that will be used to manage the project. It includes information on project scope, schedule, budget, resources, communication, risk management, and other important aspects of the project. The Project Management Plan serves as a guide for the project team and stakeholders throughout the project lifecycle, ensuring that everyone is on the same page and working towards the same goals.

    Rate this question:

  • 5. 

    All are inputs to the Direct and Manage Project Execution process except:

    • A.

      Project Management Plan

    • B.

      Approved Change Requests

    • C.

      Enterprise Environmental Factors

    • D.

      Organizational Process Assets

    • E.

      Statement of Work

    Correct Answer
    E. Statement of Work
    Explanation
    The Direct and Manage Project Execution process involves executing the project activities and producing deliverables. The Project Management Plan is a key input as it provides guidance on how the project should be executed. Approved Change Requests are also important inputs as they may introduce changes to the project scope or objectives. Enterprise Environmental Factors and Organizational Process Assets provide contextual information and resources for project execution. However, the Statement of Work is not an input to this process. The Statement of Work is a document that describes the project's objectives, deliverables, and scope, and is typically used during the project initiation and planning phases.

    Rate this question:

  • 6. 

    Which are outputs of the Direct and Manage Project Execution process?

    • A.

      Deliverables

    • B.

      Work Performance Information

    • C.

      Change Requests

    • D.

      Project Management Plan Updates

    • E.

      Project Document Updates

    • F.

      Charter

    • G.

      Approved Change Requests

    • H.

      Performance Reports

    Correct Answer(s)
    A. Deliverables
    B. Work Performance Information
    C. Change Requests
    D. Project Management Plan Updates
    E. Project Document Updates
    Explanation
    The outputs of the Direct and Manage Project Execution process include deliverables, which are the tangible products or services that are produced as part of the project. Work Performance Information is also an output, which includes data on how the project is progressing and performing. Change Requests are outputs because they may arise during project execution and require formal documentation and evaluation. Project Management Plan Updates and Project Document Updates are outputs because they need to be revised and updated as the project progresses.

    Rate this question:

  • 7. 

    Which of the following are inputs to the Monitor and Control Project Work process?

    • A.

      Project Management Plan

    • B.

      Work Performance Information

    • C.

      Enterprise Environmental Factors

    • D.

      Organizational Process Assets

    • E.

      Scope Statement

    • F.

      Stakeholder Analysis

    • G.

      Change Requests

    Correct Answer(s)
    A. Project Management Plan
    B. Work Performance Information
    C. Enterprise Environmental Factors
    D. Organizational Process Assets
    G. Change Requests
    Explanation
    The inputs to the Monitor and Control Project Work process include the Project Management Plan, Work Performance Information, Enterprise Environmental Factors, Organizational Process Assets, and Change Requests. The Project Management Plan provides the overall direction and guidance for the project. Work Performance Information is necessary to assess the progress and performance of the project. Enterprise Environmental Factors refer to external factors that can influence the project. Organizational Process Assets are the internal resources and knowledge that can be used to manage the project. Change Requests are also considered as inputs to address any changes that may arise during the project execution. The Scope Statement and Stakeholder Analysis are not mentioned as inputs to this process.

    Rate this question:

  • 8. 

    Which of the following is not an output of the Monitor and Control Project Work process?

    • A.

      Change Requests

    • B.

      Deliverables

    • C.

      Project Management Plan Updates

    • D.

      Project Document Updates

    Correct Answer
    B. Deliverables
    Explanation
    The Monitor and Control Project Work process involves tracking, reviewing, and reporting the progress of the project. It focuses on ensuring that the project is on track and meeting its objectives. Deliverables are the tangible outputs or results of the project that are produced and delivered to the stakeholders. Therefore, deliverables are not an output of the Monitor and Control Project Work process.

    Rate this question:

  • 9. 

    The following are all inputs to the Perform Integrated Change Control Process.

    • A.

      Project Management Plan

    • B.

      Work Performance Information

    • C.

      Change Requests

    • D.

      EEFs

    • E.

      OPAs

    • F.

      Project Charter

    • G.

      Change Control Meetings

    • H.

      Lessons Learned

    Correct Answer(s)
    A. Project Management Plan
    B. Work Performance Information
    C. Change Requests
    D. EEFs
    E. OPAs
    Explanation
    The Perform Integrated Change Control Process involves reviewing and approving or rejecting change requests to ensure that only approved changes are implemented. The inputs to this process include the Project Management Plan, which contains the overall project scope, objectives, and plans; Work Performance Information, which provides data on how the project is progressing; Change Requests, which are formal proposals for changes to the project; EEFs (Enterprise Environmental Factors), which are external factors that can impact the project; OPAs (Organizational Process Assets), which are internal assets such as templates, guidelines, and lessons learned from previous projects; and finally, the Project Charter, which provides the high-level project description and objectives. Change Control Meetings and Lessons Learned are not mentioned as inputs in this question.

    Rate this question:

  • 10. 

    All are outputs of Perform Integrated Change Control process except:

    • A.

      Approved Change Requests

    • B.

      Project Management Plan Updates

    • C.

      Project Document Updates

    • D.

      Deliverables

    • E.

      Change log

    Correct Answer
    D. Deliverables
    Explanation
    The Perform Integrated Change Control process is used to review and approve or reject changes to the project. It involves evaluating the impact of proposed changes on the project objectives, constraints, and requirements. Approved Change Requests are the outputs of this process, as they represent the changes that have been approved for implementation. Project Management Plan Updates and Project Document Updates are also outputs, as they reflect any changes made to the project's plans and documents. The Change log is another output, which tracks all the changes made throughout the project. However, Deliverables are not outputs of this process, as they represent the tangible products or results of the project activities, rather than changes made to the project.

    Rate this question:

  • 11. 

    Which of the following are inputs to the Close Project or Phase process?

    • A.

      Project Management Plan

    • B.

      Accepted Deliverables

    • C.

      OPAs

    • D.

      EEFs

    • E.

      Change Requests

    • F.

      Lessons Learned

    Correct Answer(s)
    A. Project Management Plan
    B. Accepted Deliverables
    C. OPAs
    Explanation
    The Close Project or Phase process involves wrapping up a project or phase. Inputs to this process include the Project Management Plan, which provides guidance on how the project should be closed. Accepted Deliverables are also important inputs as they confirm that the project has met its objectives and can be closed. Organizational Process Assets (OPAs) are another input as they contain valuable lessons learned and historical information that can be used to improve future projects.

    Rate this question:

  • 12. 

    Which of the following are outputs to the Close Project or Phase process?

    • A.

      Final Product, Service, or Result Transition

    • B.

      OPA Updates

    • C.

      Charter

    • D.

      Change Requests

    • E.

      Approved Change Requests

    Correct Answer(s)
    A. Final Product, Service, or Result Transition
    B. OPA Updates
    Explanation
    The outputs to the Close Project or Phase process include Final Product, Service, or Result Transition and OPA Updates. Final Product, Service, or Result Transition refers to the deliverables or outcomes of the project that are handed over to the customer or end-users. OPA Updates refer to the updates made to the organizational process assets based on the lessons learned and experiences gained during the project. These outputs are important for ensuring the successful completion of the project and for improving future projects within the organization.

    Rate this question:

  • 13. 

    Which of the following are valid tools and techniques for Developing the Project Charter?

    • A.

      Expert Judgment

    • B.

      Interviews

    • C.

      Focus Groups

    • D.

      Alternative Generation

    • E.

      Facilitation techniques

    Correct Answer(s)
    A. Expert Judgment
    E. Facilitation techniques
    Explanation
    Expert judgment and facilitation techniques are valid tools and techniques for developing the project charter. Expert judgment involves seeking advice and input from individuals with specialized knowledge or experience in the relevant area. This can help ensure that the project charter is comprehensive and accurate. Facilitation techniques, on the other hand, are used to guide a group of stakeholders through the process of developing the project charter. These techniques help to encourage collaboration, gather input, and ensure that all relevant perspectives are considered. Both of these tools and techniques are valuable in the process of developing a project charter.

    Rate this question:

  • 14. 

    Which of the following are valid tools and techniques for Developing the Project Management Plan?

    • A.

      Expert Judgment

    • B.

      Interviews

    • C.

      Focus Groups

    • D.

      Alternative Generation

    • E.

      Facilitation techniques

    Correct Answer(s)
    A. Expert Judgment
    E. Facilitation techniques
    Explanation
    Expert judgment and facilitation techniques are valid tools and techniques for developing the Project Management Plan. Expert judgment refers to seeking advice and opinions from subject matter experts who have experience and knowledge in the relevant field. Their expertise helps in making informed decisions and ensuring the plan is comprehensive and effective. Facilitation techniques involve using various methods to encourage collaboration and participation among project stakeholders, such as brainstorming, conflict resolution, and decision-making techniques. These techniques help in gathering input and perspectives from different stakeholders, ensuring their buy-in and increasing the chances of project success.

    Rate this question:

  • 15. 

    Which of the following are valid tools and techniques for Direct and Manage Project Execution?

    • A.

      Expert Judgment

    • B.

      Interviews

    • C.

      Focus Groups

    • D.

      Alternative Generation

    • E.

      Facilitation techniques

    • F.

      Meetings

    • G.

      Change control system

    • H.

      Project management information system

    Correct Answer(s)
    A. Expert Judgment
    F. Meetings
    H. Project management information system
    Explanation
    Expert Judgment, Meetings, and Project Management Information System are valid tools and techniques for Direct and Manage Project Execution. Expert Judgment involves seeking advice and input from subject matter experts to make informed decisions. Meetings are essential for communication, collaboration, and decision-making within the project team. Project Management Information System is a software tool that provides a centralized platform for managing project data, documents, and communication. These tools and techniques help in executing the project effectively, ensuring that tasks are completed as planned and project objectives are achieved.

    Rate this question:

  • 16. 

    Which of the following are valid tools and techniques for Monitor and Control Project Work?

    • A.

      Expert Judgment

    • B.

      Interviews

    • C.

      Focus Groups

    • D.

      Alternative Generation

    • E.

      Facilitation techniques

    • F.

      Meetings

    • G.

      Change control system

    • H.

      Project management information system

    • I.

      Analytical techniques

    Correct Answer(s)
    A. Expert Judgment
    F. Meetings
    H. Project management information system
    I. Analytical techniques
    Explanation
    The tools and techniques listed in the answer are all valid for Monitor and Control Project Work. Expert Judgment is important for gathering insights and opinions from experienced professionals. Meetings are necessary for discussing project progress, addressing issues, and making decisions. Project management information system helps in collecting, organizing, and presenting project data for monitoring and controlling purposes. Analytical techniques are used to analyze project data and make informed decisions.

    Rate this question:

  • 17. 

    Which of the following are valid tools and techniques for perform integrated change control?

    • A.

      Expert Judgment

    • B.

      Interviews

    • C.

      Focus Groups

    • D.

      Alternative Generation

    • E.

      Facilitation techniques

    • F.

      Meetings

    • G.

      Change control software/tools

    • H.

      Project management information system

    • I.

      Analytical techniques

    Correct Answer(s)
    A. Expert Judgment
    F. Meetings
    G. Change control software/tools
    Explanation
    Expert Judgment, Meetings, and Change control software/tools are valid tools and techniques for performing integrated change control. Expert Judgment involves seeking advice and insights from subject matter experts to make informed decisions about change requests. Meetings provide a platform for stakeholders to discuss and evaluate change requests. Change control software/tools help in documenting, tracking, and managing changes throughout the project. These tools automate the change control process and ensure that all changes are properly reviewed, approved, and implemented.

    Rate this question:

  • 18. 

    Which of the following are valid tools and techniques for Close Project or Phase?

    • A.

      Expert Judgment

    • B.

      Interviews

    • C.

      Focus Groups

    • D.

      Alternative Generation

    • E.

      Facilitation techniques

    • F.

      Meetings

    • G.

      Change control software/tools

    • H.

      Project management information system

    • I.

      Analytical techniques

    Correct Answer(s)
    A. Expert Judgment
    F. Meetings
    I. Analytical techniques
    Explanation
    Expert Judgment, Meetings, and Analytical techniques are valid tools and techniques for the Close Project or Phase process. Expert Judgment involves seeking advice and guidance from individuals with specialized knowledge or expertise. Meetings are important for reviewing project performance, conducting lessons learned sessions, and obtaining final approvals. Analytical techniques, such as trend analysis, variance analysis, and root cause analysis, help in evaluating project performance and identifying areas for improvement. These tools and techniques contribute to the successful closure of a project or phase.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jan 31, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Dec 04, 2018
    Quiz Created by
    Budhines
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.