Production Planning And Control

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By S_mai_s
S
S_mai_s
Community Contributor
Quizzes Created: 1 | Total Attempts: 1,206
| Attempts: 1,206 | Questions: 175
Please wait...
Question 1 / 175
0 %
0/100
Score 0/100
1. There are five manufacturing systems. However, many manufacturers combines two or more systems to produce a final product.

Explanation

Manufacturers often combine two or more manufacturing systems to produce a final product. This means that the statement "There are five manufacturing systems" is not sufficient on its own, as manufacturers have the flexibility to use a combination of systems to meet their production needs. Therefore, the answer is true.

Submit
Please wait...
About This Quiz
Production Planning And Control - Quiz

Take this test May 2009 prepared for SCDL exam from previous assignments.

Personalize your quiz and earn a certificate with your name on it!
2. Mass & flow production and process production are categorized under :-

Explanation

Mass & flow production and process production are categorized under continuous production because they involve the continuous and uninterrupted production of goods or services. In mass & flow production, products are manufactured in large quantities using assembly line techniques, with a continuous flow of materials and components. Process production, on the other hand, involves the continuous production of goods through a series of interconnected processes, such as in chemical or food manufacturing. Both types of production focus on efficiency, standardization, and high volume output, which align with the characteristics of continuous production.

Submit
3. The make-or-buy decision becomes necessary when the current source of supply is not able to supply the material in accordance with buyer's quality requirements.

Explanation

The explanation for the given correct answer is that the make-or-buy decision is typically made when the current supplier is unable to meet the buyer's quality requirements. This means that the buyer may need to consider whether it is more cost-effective and efficient to produce the material themselves (make) or to outsource it to another supplier (buy). If the current supplier is not able to meet the required quality standards, it may be necessary to explore alternative options to ensure that the buyer's quality requirements are met.

Submit
4. Line staff can assist PPC by manufacturing some of their needs in their own shops rather than making PPC to tool room or purchase.

Explanation

Line staff refers to the employees who directly work on the production line or perform operational tasks. By manufacturing some of their needs in their own shops, line staff can assist the PPC (Production Planning and Control) department by reducing the workload on the tool room or the need to make purchases. This can help streamline the production process and improve efficiency. Therefore, the statement is true.

Submit
5. Purchase department must keep PPC informed regarding lead time of different items specially where lead times are extended.

Explanation

The purchase department needs to inform the production planning and control (PPC) department about the lead times of different items, especially when the lead times are extended. This is important because PPC relies on this information to schedule production and ensure that materials are available on time. If the purchase department does not communicate the lead times accurately, it can lead to delays in production and affect the overall efficiency of the manufacturing process. Therefore, it is crucial for the purchase department to keep PPC informed about lead times.

Submit
6. Moving average method lags behind the latest trend.

Explanation

The statement is true because the moving average method is a lagging indicator. It calculates the average of a set of data points over a specific period of time, which means it is based on past data. As a result, it tends to smooth out short-term fluctuations and may not reflect the latest trend accurately. Therefore, it can be said that the moving average method lags behind the latest trend.

Submit
7. Orders with ________ slack time remaining per operation are run first.

Explanation

Orders with the shortest slack time remaining per operation are run first because slack time represents the amount of time a task can be delayed without delaying the entire project. Therefore, by prioritizing orders with the shortest slack time, it ensures that tasks are completed quickly and efficiently, minimizing the risk of project delays.

Submit
8. Buying for C quantities should be made in ________ quantities .

Explanation

Buying for C quantities should be made in large quantities because it is more efficient and cost-effective to purchase larger quantities at once. This can help in achieving economies of scale, reducing transportation costs, and obtaining bulk discounts. Additionally, buying in large quantities ensures that there is an adequate supply of the product, reducing the risk of running out of stock.

Submit
9. Stores issue order for an item is prepared as soon as the route sheet is ready.

Explanation

The statement suggests that stores issue an order for an item as soon as the route sheet is ready. This implies that the stores are proactive in preparing the order and do not delay it. Therefore, the correct answer is True, indicating that the statement is accurate.

Submit
10. When shop floor scheduling problem larger than 3 machines arise the analytical solution procedures leading to optimality are complex and difficult.

Explanation

The explanation for the given correct answer is that when the shop floor scheduling problem involves more than 3 machines, the analytical solution procedures become complex and difficult. This implies that it becomes challenging to find an optimal solution for the scheduling problem in such cases.

Submit
11. Exponential smoothening is weighted average method.

Explanation

Exponential smoothing is a technique used for forecasting time series data. It involves calculating weighted averages of past observations, with more weight given to recent observations. This allows for the detection of trends and patterns in the data. Therefore, it can be concluded that exponential smoothing is indeed a weighted average method.

Submit
12. The make-or-buy decision is not taken only at starting of a factory but has to be reviewed continuously.

Explanation

The statement is true because the make-or-buy decision is not a one-time decision made at the beginning of a factory's operation. It is an ongoing process that needs to be reviewed continuously. Factors such as changes in market conditions, cost fluctuations, technological advancements, and shifts in the company's core competencies may require the decision to be reassessed periodically. By regularly evaluating the make-or-buy options, a company can ensure it is making the most cost-effective and strategic choices to optimize its operations.

Submit
13. Inspection operations is a part of process plan for a part.

Explanation

Inspection operations are indeed a part of the process plan for a part. During the manufacturing process, inspection operations are carried out to ensure that the part meets the required specifications and quality standards. These operations involve examining the part for any defects, measuring its dimensions, and conducting various tests to verify its functionality. By including inspection operations in the process plan, manufacturers can identify and rectify any issues early on, ensuring that only high-quality parts are produced.

Submit
14. A company where different personnel give conflicting delivery promises need to improve its scheduling and processing function.

Explanation

The given statement suggests that the company is facing issues with conflicting delivery promises made by different personnel. This indicates a lack of coordination and effective scheduling within the company's operations. By improving its scheduling and processing function, the company can address these conflicts and ensure more accurate and reliable delivery promises. Therefore, the statement is true.

Submit
15. Lead time is ________ for different items.

Explanation

Lead time refers to the amount of time it takes for an item to be produced, delivered, or made available for use. In this context, the statement "Lead time is different for different items" means that the time required for different items to be produced or delivered varies. Each item may have its own specific lead time based on factors such as production processes, availability of raw materials, and transportation logistics. Therefore, the lead time can vary for different items, indicating that it is not the same for all items.

Submit
16. Heuristics approach gave very good results when Wester and Kilbridge applied it to ________ assembly line.

Explanation

The explanation for the given correct answer is that the heuristics approach provided favorable outcomes when applied to the TV assembly line. This implies that the heuristics approach was effective in improving the efficiency and productivity of the TV assembly line, resulting in positive results.

Submit
17. The non-mathematical rationale of the assignment method is one of minimizing opportunity costs.

Explanation

The assignment method aims to minimize opportunity costs, which means it tries to allocate resources in a way that maximizes the overall benefit or value. By minimizing opportunity costs, the assignment method ensures that the chosen allocation is the most efficient and effective. Therefore, the statement that the non-mathematical rationale of the assignment method is one of minimizing opportunity costs is true.

Submit
18. Overlapping of operations helps in compressing manufacturing time.

Explanation

Overlapping of operations refers to the practice of starting a new operation before the previous one is completed. This can help in compressing manufacturing time because it reduces idle time and minimizes the overall time required to complete a product. By overlapping operations, the manufacturing process becomes more efficient and streamlined, allowing for faster production. Therefore, the statement is true.

Submit
19. PERT uses linear programming and probability concepts for planning and controlling activities.

Explanation

PERT (Program Evaluation and Review Technique) is a project management tool that uses linear programming and probability concepts for planning and controlling activities. Linear programming is used to optimize the allocation of resources and determine the most efficient schedule for completing a project. Probability concepts are used to estimate the time required for each activity and to calculate the overall project completion time. Therefore, the given statement is true.

Submit
20. LOB is a manual planning and scheduling technique similar in nature to MRP [Material Resource Planning].

Explanation

LOB (Line of Balance) is a manual planning and scheduling technique that is indeed similar to MRP (Material Resource Planning). Both techniques are used to effectively manage and allocate resources in a project or production process. They involve creating a timeline or schedule, identifying the necessary resources, and ensuring that they are allocated efficiently to meet the project's objectives. Therefore, the given answer "True" is correct.

Submit
21. Because of uncertainty of activity timings, PERT acquired a shape of ________ model.

Explanation

PERT (Program Evaluation and Review Technique) is a project management tool that is used to analyze and represent the uncertainty in activity timings. It takes into account the fact that activity durations are not fixed and can vary within a certain range. Therefore, PERT uses a probabilistic model to estimate the time required for each activity. This model incorporates the probabilities of different durations occurring for each activity, allowing for a more realistic representation of the project timeline. Thus, the correct answer is "Probabilistic."

Submit
22. The LOB technique is most appropriate for assembly operations involving number of distinct components.

Explanation

The LOB (Line of Balance) technique is a project management tool that is commonly used in assembly operations where there are multiple distinct components involved. This technique helps in planning and scheduling the assembly process by visualizing the sequence of tasks and their dependencies. By using the LOB technique, project managers can effectively allocate resources, identify bottlenecks, and ensure a smooth flow of work in assembly operations with various components. Therefore, the statement that the LOB technique is most appropriate for assembly operations involving a number of distinct components is true.

Submit
23. Keeping procurement cost and carrying cost constant, if annual usage of certain product becomes 4 times, the EOQ would be :-

Explanation

When the annual usage of a product becomes 4 times, it means that the demand for the product has increased significantly. The Economic Order Quantity (EOQ) is a formula used to calculate the optimal order quantity that minimizes the total cost of ordering and carrying inventory. Since the demand has increased, the EOQ would need to be doubled in order to meet the higher demand and ensure that the inventory is properly managed. This is because a larger quantity would need to be ordered to accommodate the increased usage, resulting in a higher EOQ.

Submit
24. The sourcing of vendors in case of 'B' type of items is :-

Explanation

The sourcing of vendors for 'B' type items is considered to be medium. This means that it requires a moderate level of effort and resources to identify and select suitable vendors for these items. It suggests that there may be a reasonable number of potential vendors available in the market for these items, but some level of evaluation and comparison is still necessary to ensure the best fit. This sourcing process may involve conducting research, requesting quotes or proposals, and assessing vendor capabilities and qualifications.

Submit
25. XYZ analysis helps to identify few items which account for large amount of money locked up in the stock and take steps for liquidation / reduction.

Explanation

The XYZ analysis is a method used to identify items in stock that contribute to a significant portion of the overall value. By identifying these items, a company can take steps to liquidate or reduce them, freeing up money that may be tied up in inventory. Therefore, the statement is true.

Submit
26. ________ is a production line made up of operations that form or change the physical or sometimes chemical characteristics of a product.

Explanation

A fabrication line is a production line that consists of operations that form or change the physical or sometimes chemical characteristics of a product. This suggests that the correct answer is "Fabrication line" because it accurately describes the type of production line that is being referred to in the question. An assembly line, on the other hand, typically involves the process of putting together various components to create a finished product, rather than forming or changing the characteristics of the product.

Submit
27. Forecasting is function of ________.

Explanation

Forecasting is a function of the marketing department because it involves analyzing market trends, customer behavior, and competitive landscape to predict future demand for products or services. The marketing department is responsible for conducting market research, gathering data, and using various forecasting techniques to estimate future sales, identify potential opportunities, and make informed decisions regarding pricing, promotions, and product development. The CEO, on the other hand, oversees the overall strategic direction of the company and may rely on the marketing department's forecasts to make high-level decisions, but they are not directly involved in the forecasting process.

Submit
28. As the quantity increases, the procurement cost :-

Explanation

As the quantity increases, the procurement cost reduces. This is because when larger quantities are purchased, suppliers often offer discounts or lower prices per unit. This is known as economies of scale, where the cost per unit decreases as the volume of production or procurement increases. Therefore, it is more cost-effective to procure larger quantities, resulting in a reduction in procurement cost.

Submit
29. Rational figure on utilization index can be obtained by carrying out ________ study.

Explanation

Work sampling is a study method used to determine the utilization index of a rational figure. It involves observing and recording the amount of time workers spend on different tasks or activities. By analyzing the data collected through work sampling, one can calculate the utilization index, which represents the proportion of time that workers are engaged in productive work. Therefore, work sampling is the appropriate study method to obtain a rational figure on the utilization index.

Submit
30. To solve "n jobs - 3 machines" sequencing problem, the largest of time of any job on the second machine must be smaller than or equal to the smallest time of any job on first machine or third machine.

Explanation

In a "n jobs - 3 machines" sequencing problem, it is necessary for the largest time of any job on the second machine to be smaller than or equal to the smallest time of any job on the first machine or the third machine. This condition ensures that the jobs can be scheduled efficiently without any conflicts or delays. If this condition is not met, it may lead to inefficiencies and difficulties in scheduling the jobs. Therefore, the statement is true.

Submit
31. As per a study on materials management practices, a typical firm spends almost half of its rupee sales on goods purchased from vendors.

Explanation

The given statement is true because the study on materials management practices found that a typical firm spends almost half of its rupee sales on goods purchased from vendors. This indicates that a significant portion of a firm's revenue is allocated towards purchasing goods from external suppliers.

Submit
32. Sequencing helps management to determine the most economical job sequence the one that consumes minimum :-

Explanation

Sequencing helps management to determine the most economical job sequence based on elapsed time. Elapsed time refers to the total time taken to complete a job from start to finish, including processing, waiting, and transportation times. By considering elapsed time, management can identify the job sequence that minimizes the overall time required for production, leading to increased efficiency and cost-effectiveness.

Submit
33. The assembly work content [ Wi ] of the i'th station having n work stations is given by :-
Correct Answer

Explanation

The correct answer is "a Wi from i=1 to n". This means that the assembly work content of the i'th station, out of n work stations, is the sum of the work content of each individual station. In other words, it is the sum of Wi for i=1 to n.

Submit
34. PERT is suitable in defense projects and R&D where activity times can not be really predicted.

Explanation

PERT (Program Evaluation and Review Technique) is a project management tool that is particularly useful in defense projects and research and development (R&D) projects. This is because in these types of projects, the activity times cannot be accurately predicted due to the complex and uncertain nature of the work involved. PERT allows for the incorporation of uncertainty and variability in activity times, making it a suitable method for managing projects where there is a high degree of uncertainty in the duration of activities. Therefore, the statement that PERT is suitable in defense projects and R&D where activity times cannot be really predicted is true.

Submit
35. The sourcing of vendors in case of 'B' type of items is :-

Explanation

The sourcing of vendors for 'B' type of items is considered medium. This implies that the process of finding and selecting vendors for these items is not as challenging or time-consuming as it would be for 'A' type items, but it still requires some effort and evaluation. It suggests that there may be a moderate number of potential vendors available for these items, and the sourcing process may involve comparing different options and negotiating terms.

Submit
36. What shall be the consequence of acceptance of frequent rush orders by sales department?

Explanation

Accepting frequent rush orders can lead to delivery failure because the sales department may not have enough time or resources to fulfill these orders within the required timeframe. This can result in delays or even complete failure to deliver the products to the customers on time. Additionally, accepting rush orders may disrupt the normal scheduling of production, leading to further delays and inefficiencies in the overall delivery process.

Submit
37. Ordering of raw material is based on :-

Explanation

The ordering of raw material is based on sales forecast because it provides an estimation of the quantity of products that will be sold in a given period. By analyzing past sales data and market trends, businesses can predict future demand and accordingly plan their raw material requirements. This helps in avoiding overstocking or understocking situations, optimizing inventory levels, and ensuring a smooth production process. Marketing forecast, on the other hand, focuses more on understanding consumer behavior and identifying potential market opportunities, which may not directly translate into actual sales figures.

Submit
38. To solve "n jobs - 2 machines" sequencing problem, it is assumed that each machine can perform only one type of operation and can undertake only one job at a time.

Explanation

The explanation for the given correct answer is that in the "n jobs - 2 machines" sequencing problem, it is assumed that each machine is capable of performing only one type of operation and can handle only one job at a time. This assumption helps in simplifying the problem and allows for easier scheduling and sequencing of the jobs on the available machines.

Submit
39. The 'G' group of GOLF analysis involves moderate delivery time and availability of credit usually in the range of 30 to 60 days.

Explanation

The 'G' group in GOLF analysis refers to the delivery time and availability of credit. It states that the delivery time is moderate and the credit is usually available within 30 to 60 days. Therefore, the statement is true.

Submit
40. If set up time for four operations involved is 2 ,1.5, 2 , 2.5 hours respectively, total set up time would be 10 hours.

Explanation

The given statement is false because the total set up time for the four operations would be 8 hours, not 10 hours. This can be calculated by adding up the set up times for each operation: 2 + 1.5 + 2 + 2.5 = 8. Therefore, the correct answer is false.

Submit
41. C type items would never be vital under VED analysis.

Explanation

The statement "C type items would never be vital under VED analysis" is false. VED analysis categorizes items based on their criticality and importance. C type items are those that are essential for the smooth functioning of an organization but have a lower impact on operations if they are unavailable. While not as critical as V (vital) or E (essential) items, C type items still play a significant role in the overall functioning of the organization and can have an impact if they are not available. Therefore, C type items can be vital under VED analysis.

Submit
42. In replenishment system, the type of ordering is either according to "stock level" or "pre-fixed time scale".

Explanation

In a replenishment system, the type of ordering can be determined based on either the stock level or a pre-fixed time scale. This means that orders can be placed when the stock level reaches a certain threshold or at specific intervals of time. Therefore, the statement "In replenishment system, the type of ordering is either according to stock level or pre-fixed time scale" is true.

Submit
43. Short term forecasts are for ________.

Explanation

Short term forecasts are for Material Planning. This means that short term forecasts are used to predict and plan the material requirements for a specific period of time. It helps in ensuring that there is an adequate supply of materials to meet the production demands and avoid any shortages or excess inventory. Sales forecasting, on the other hand, is a separate process that focuses on predicting future sales volumes and revenues.

Submit
44. One of the causes of inability to meet delivery date originally promised :-

Explanation

The lack of availability of material in time can cause an inability to meet the originally promised delivery date. If the necessary materials are not available when needed, it can delay the production or completion of a project, leading to a delay in delivery. This could be due to issues with the supply chain, procurement delays, or unexpected shortages. Without the required materials, it becomes difficult to proceed with the necessary tasks, resulting in a failure to meet the delivery deadline.

Submit
45. ________ inventories help to balance company's supply with market demand.

Explanation

Finished goods inventories help to balance a company's supply with market demand because they consist of products that are ready to be sold to customers. By having a sufficient amount of finished goods in inventory, a company can meet customer demands promptly and efficiently. This helps to prevent stockouts and delays in delivering products to customers, ultimately ensuring customer satisfaction. Additionally, maintaining a balanced level of finished goods inventory allows a company to optimize production and minimize costs by avoiding excessive inventory or production shortages.

Submit
46. Work sampling is ________

Explanation

Work sampling is done at random intervals. This means that observations of work activities are taken at various, unpredictable times throughout the workday. This method allows for a representative sample of work to be collected, as it captures the variability and randomness of work tasks. By sampling work at random intervals, a more accurate picture of the overall work patterns and productivity can be obtained.

Submit
47. Proper Production Planning and Control can reduce cost in :-

Explanation

Proper production planning and control can reduce overtime cost by ensuring that production processes are efficiently managed and resources are effectively utilized. By accurately forecasting demand, optimizing production schedules, and minimizing production disruptions, companies can avoid the need for excessive overtime work, which can be costly. Additionally, effective planning and control can help identify and address production bottlenecks or inefficiencies, further reducing the need for overtime. Overall, by implementing proper production planning and control measures, companies can optimize their operations and reduce overtime costs.

Submit
48. Activity R can not start unless activities P & Q are completed . And activity S can not start unless activity Q is over [ I.e. activity P may not be even over ]. Activity R is therefore succedding to activity P & Q while activity S is succeeding to activity :-

Explanation

Activity R can only start once activities P and Q are completed. This means that both P and Q must be finished before R can begin. On the other hand, activity S can only start once activity Q is over, meaning that Q must be completed before S can begin. Therefore, activity R is succeeding activity P and Q, while activity S is succeeding activity Q.

Submit
49. To keep facilities busy, waiting time due to non-availability of work should be kept at :-

Explanation

To keep facilities busy, it is ideal to minimize the waiting time due to non-availability of work. This means that the facilities should always have work to do, ensuring maximum productivity and efficiency. By minimizing waiting time, resources are effectively utilized, reducing idle time and maximizing output. This approach helps to optimize the use of facilities and maintain a smooth workflow, ultimately leading to improved performance and customer satisfaction.

Submit
50. Labour efficiency depends upon ________

Explanation

Labour efficiency depends upon training and experience. Both factors play a crucial role in enhancing the productivity and effectiveness of the workforce. Training equips employees with the necessary skills and knowledge to perform their tasks efficiently, while experience allows them to apply that knowledge effectively in real-world scenarios. By combining training and experience, organizations can ensure that their employees are well-prepared and capable of delivering high-quality work, resulting in improved labour efficiency.

Submit
51. ________ is the sum of set up time and run time.

Explanation

Manufacturing time refers to the total time required to complete a manufacturing process, including both the set up time and the run time. Set up time is the time taken to prepare the equipment, tools, and materials before the actual production starts, while run time is the time taken for the actual production process. Therefore, manufacturing time is the sum of these two components.

Submit
52. Installed capacity :-

Explanation

Installed capacity refers to the maximum amount of power that a power plant or facility can generate under normal operating conditions. On the other hand, licensed capacity refers to the maximum amount of power that a power plant or facility is legally authorized to generate by the relevant regulatory authority. Therefore, it is possible for the installed capacity to be equal to or less than the licensed capacity, as the facility may not always operate at its maximum potential due to various factors such as maintenance, technical limitations, or market demand.

Submit
53. Stock of finished goods are based on :-

Explanation

The stock of finished goods is based on sales forecast because it helps in estimating the future demand for products. Sales forecast takes into account various factors such as historical sales data, market trends, customer behavior, and competitor analysis to predict the expected sales volume. By using sales forecast, companies can determine the appropriate level of inventory to meet the anticipated demand and avoid stockouts or excess inventory. Therefore, sales forecast is crucial in planning and managing the stock of finished goods efficiently.

Submit
54. Being capable to adjust their production facilities shortly just after change in demand for products and without incurring heavy expenses, greater flexibility in production is provided by ________.

Explanation

Job & batch production provides greater flexibility in production by allowing companies to adjust their production facilities shortly after a change in demand for products without incurring heavy expenses. This is because job & batch production involves producing goods in small quantities or batches, which allows for easier customization and adaptation to changing market demands. In contrast, continuous production involves producing goods in large quantities without the ability to easily adjust production levels, making it less flexible in responding to changes in demand.

Submit
55. Responsibility of smooth flow of work through different work centers or departments of company rests with :-

Explanation

The production control department is responsible for ensuring the smooth flow of work through different work centers or departments of a company. They coordinate and schedule production activities, monitor inventory levels, and allocate resources effectively to meet production targets. By overseeing the entire production process, the production control department plays a crucial role in maintaining workflow efficiency and meeting customer demands.

Submit
56. Ordering of raw material is based on :-

Explanation

The ordering of raw material is based on sales forecast because it helps in predicting the demand for the final product. By analyzing the sales forecast, a company can estimate the quantity of raw materials required to meet the projected demand. This allows them to plan their production and inventory levels effectively, ensuring that they have enough raw materials on hand to fulfill customer orders without excess inventory or stockouts. Therefore, sales forecast plays a crucial role in determining the ordering of raw materials.

Submit
57. The cost involved in subcontracting some of the operations of item outside the home plant is called :-

Explanation

The cost involved in subcontracting some operations of an item outside the home plant is referred to as outside operations cost. This includes the expenses incurred in outsourcing certain tasks or processes to external parties or facilities. By subcontracting outside the home plant, a company can benefit from cost savings, specialized expertise, or additional capacity. This cost category helps track and analyze the expenses associated with these external operations.

Submit
58. As the quantity increases, the procurement cost :-

Explanation

The correct answer is "Reduces" because as the quantity increases, the procurement cost per unit tends to decrease due to economies of scale. When more units are produced or purchased, the fixed costs are spread over a larger quantity, resulting in a lower cost per unit. This is a common phenomenon in many industries where bulk purchasing or production leads to cost savings. Therefore, it can be concluded that the procurement cost reduces as the quantity increases.

Submit
59. The make-or-buy decision is not related with profit of the factory.

Explanation

The make-or-buy decision is actually related to the profit of the factory. This decision involves analyzing whether it is more cost-effective for a company to produce a product or service in-house (make) or to outsource it from external suppliers (buy). By carefully considering factors such as production costs, expertise, quality control, and market conditions, a company can determine the most profitable option. Therefore, the statement that the make-or-buy decision is not related to the profit of the factory is false.

Submit
60. The light engineering company has one special purpose facing & centering machine And one copying lathe. The foreman has five work orders for processing . The operation Sequence is fixed [ each job is first faced and centered and then copy turned ] . The standard Hours required for each machine to process each work order are shown in the following Table :- Work Order Processing Time [Hours ] Facing & centering machine Copying Lathe I 16 40 II 30 60 III 20 6 IV 15 16 V 25 12 find sequence to minimize requirements of machine hours.

Explanation

The given answer sequence, IV-I-II-V-III, minimizes the requirements of machine hours. This can be determined by calculating the total hours required for each sequence and comparing them. In this sequence, the total hours required for the facing & centering machine are 31 (15 + 16), for the copying lathe are 68 (40 + 16 + 12), and the total machine hours required are 99. Comparing this with the other given sequence, II-III-IV-I-V, the total machine hours required are 115. Therefore, the sequence IV-I-II-V-III minimizes the requirements of machine hours.

Submit
61. Of all the work measurement techniques the most widely used techniques is________.

Explanation

Time study is the most widely used work measurement technique because it involves observing and measuring the time taken by a worker to complete a specific task or activity. This technique helps in determining the standard time required for completing the task, identifying inefficiencies, and setting realistic production targets. Time study is widely used across industries to improve productivity, optimize resource allocation, and establish fair and accurate work standards. It provides a quantitative and objective method for measuring and analyzing work performance, making it a popular choice among organizations for evaluating and improving work processes.

Submit
62. If number of work stations is 8 and work content of all stations is 32 , the cycle time would be ________.

Explanation

The cycle time can be calculated by dividing the total work content by the number of work stations. In this case, the total work content is 32 and the number of work stations is 8. Therefore, the cycle time would be 32/8 = 4.

Submit
63. The data in respect of spindle nose pertains to :-

Explanation

The data in respect of spindle nose pertains to tooling. This means that the information or specifications related to the spindle nose, such as its size, type, or compatibility, are relevant and important for the selection and use of appropriate tools. It may include details about the tool holders, collets, or chucks that can be used with the specific spindle nose. This information helps in ensuring proper tooling setup and compatibility, thereby enhancing the efficiency and accuracy of machining operations.

Submit
64. A firm has 6 jobs to be processed on three machines A,B and C in the order ABC. The processing time of each job is given in the table below:- Find the idle time on different machines . Job Processing time [ hours ] Machine A Machine B Machine C J1 25 16 20 J2 26 20 19 J3 24 17 18 J4 22 20 21 J5 24 21 17 J6 28 18 13

Explanation

The idle time on different machines can be calculated by subtracting the total processing time for each machine from the total available time. In this case, the total available time is the sum of the processing times for all the jobs.

For machine A, the total processing time is 25 + 26 + 24 + 22 + 24 + 28 = 149 hours. The total available time is 149 + 31 (idle time on machine B) + 58 (idle time on machine C) = 238 hours. Therefore, the idle time on machine A is 238 - 149 = 89 hours.

Similarly, for machine B, the total processing time is 16 + 20 + 17 + 20 + 21 + 18 = 112 hours. The total available time is 112 + 74 (idle time on machine A) + 58 (idle time on machine C) = 244 hours. Therefore, the idle time on machine B is 244 - 112 = 132 hours.

For machine C, the total processing time is 20 + 19 + 18 + 21 + 17 + 13 = 108 hours. The total available time is 108 + 74 (idle time on machine A) + 31 (idle time on machine B) = 213 hours. Therefore, the idle time on machine C is 213 - 108 = 105 hours.

Therefore, the idle time on different machines is 74 hours for machine A, 31 hours for machine B, and 58 hours for machine C.

Submit
65. Production output in night shift is :-

Explanation

The production output in the night shift is lower than the production output in the day shift. This could be due to various reasons such as fewer workers available during the night shift, lower energy levels and productivity during nighttime, or reduced efficiency due to fatigue. Additionally, there may be certain limitations or constraints during the night shift that affect production output, such as reduced availability of resources or equipment.

Submit
66. Detachable ticket, after filling in required information is :-

Explanation

After filling in the required information, the detachable ticket is placed in a tray/box. This suggests that there is a designated location for collecting these tickets, which could be for further processing or storage. It ensures that the tickets are organized and easily accessible when needed. Placing the tickets in a tray/box also helps in preventing them from getting lost or misplaced.

Submit
67. Physical Count method of collecting information from manufacturing shops is applicable in following situation :-

Explanation

The Physical Count method is suitable for workshops employing few machines because it involves physically counting the inventory items in the shop. This method is practical when there are only a few machines to monitor and it is feasible to physically count the items. It may be more time-consuming and challenging to implement in workshops with a large number of machines or complex production processes. Therefore, for workshops employing few machines, the Physical Count method is a suitable approach to collect information about the inventory.

Submit
68. ________ analysis mainly helps to identify non-existing items for which store keeps bin cards, wastes computer memory or wastes computer stationary while preparing stores ledger.

Explanation

MNG analysis helps to identify non-existing items for which the store keeps bin cards, wastes computer memory, or wastes computer stationary while preparing the stores ledger. This analysis allows the store to identify and eliminate any unnecessary or redundant items, saving resources and improving efficiency.

Submit
69. If efficiency is more, the manufacturing time required for completion of job would be generally :-

Explanation

If efficiency is higher, it means that the manufacturing process is more effective and productive. This implies that the resources are being utilized more efficiently, resulting in a decrease in the time required to complete the job. Therefore, the correct answer is "Less".

Submit
70. In ABC analysis, the classification is based on :-

Explanation

In ABC analysis, the classification is based on cumulative cost. This means that items are categorized according to their total cost over a specific period of time. Cumulative cost takes into account both the carrying cost and any other costs associated with the item, such as ordering or storage costs. By classifying items based on cumulative cost, businesses can prioritize their inventory management and focus on the items that contribute the most to their overall costs.

Submit
71. ________ are grouped so that their total time is preferably equal to or little lesser than the time available each work station.

Explanation

Tasks are grouped so that their total time is preferably equal to or little lesser than the time available each work station. This ensures that the work stations are not overwhelmed with tasks and can be completed within the allocated time. By grouping tasks in this manner, the efficiency and productivity of the assembly line can be maximized, as each work station can focus on completing their assigned tasks without any delays or bottlenecks.

Submit
72. The administrative lead time e.g. time involved in processing the order, which may be in periodical review system including the period until next review is called ________ lead time.

Explanation

The administrative lead time refers to the time involved in processing an order, including the period until the next review. This lead time is internal to the organization and does not involve any external factors. Therefore, the correct answer is "Internal."

Submit
73. A type items are always vital under VED analysis.

Explanation

In VED analysis, items are classified into three categories: Vital, Essential, and Desirable. Vital items are those that are critical for the functioning of an organization and their unavailability can lead to severe consequences. However, the statement suggests that A type items are always vital under VED analysis, which is not true. The classification of items into VED categories is based on their criticality and not their type. Therefore, the statement is false.

Submit
74. Buying for C quantities should be made in ________ quantities .

Explanation

When buying for a large quantity (C), it is more efficient and cost-effective to purchase in large quantities as well. This allows for bulk discounts, reduces the number of transactions, and minimizes logistical complications. Therefore, the correct answer is "Large" quantities.

Submit
75. The LOB technique is made more accurate and fast by using ________.

Explanation

The LOB technique, which stands for Line of Balance, is a scheduling method used in project management. It involves dividing a project into separate activities and organizing them in a linear sequence. The use of computers enhances the accuracy and speed of this technique by automating calculations, enabling quick adjustments to the schedule, and providing real-time updates. Computers can handle complex calculations and store large amounts of data, making them an ideal tool for optimizing the LOB technique.

Submit
76. The ROI of the company can be increased by :-

Explanation

By increasing profit and decreasing inventory, the company can improve its return on investment (ROI). Increasing profit means that the company is generating more revenue and reducing expenses, resulting in higher profitability. Decreasing inventory means that the company is effectively managing its inventory levels, avoiding excess stock and associated holding costs. This allows the company to optimize its resources and improve its ROI by generating more profit with fewer inventory expenses.

Submit
77. Work measurement is not useful for choosing between two alternate methods of production.

Explanation

Work measurement is useful for choosing between two alternate methods of production. Work measurement involves analyzing and quantifying the time and effort required to complete a task or process. By accurately measuring the work involved in each method, one can compare the efficiency and productivity of the alternatives. This allows decision-makers to make informed choices based on objective data, ensuring the selection of the most effective and efficient method of production.

Submit
78. Production Planning and Control makes the supervisor ineffective.

Explanation

Production Planning and Control can make the supervisor ineffective because it involves the establishment of production targets, scheduling of work, and allocation of resources. When these processes are not properly managed or coordinated, it can lead to inefficiencies, delays, and a lack of productivity. This can ultimately make the supervisor's job more challenging and hinder their ability to effectively oversee and manage the production process.

Submit
79. Given the following data :- procurement cost per order = Rs 30 ; frequency of ordering per year =4 ; number of suppliers = 3 . Form the above data, total procurement cost would be Rs ________.

Explanation

To calculate the total procurement cost, we need to multiply the procurement cost per order by the frequency of ordering per year and the number of suppliers. In this case, the procurement cost per order is Rs 30, the frequency of ordering per year is 4, and the number of suppliers is 3. Therefore, the total procurement cost would be 30 x 4 x 3 = Rs 360.

Submit
80. In alternate routing, the delayed job may be routed to a ________ machine where rate of production is faster.

Explanation

In alternate routing, the delayed job may be routed to a costlier machine where the rate of production is faster. This means that by using a more expensive machine, the job can be completed at a faster pace, which can help in reducing the overall delay. The costlier machine is likely to have more advanced technology or higher capacity, allowing it to handle the job more efficiently and effectively.

Submit
81. Random fluctuation is considered for deciding ________.

Explanation

Random fluctuation is considered for deciding analytical estimate. This means that when making an analytical estimate, random fluctuations are taken into account. These fluctuations can introduce uncertainty and variability into the estimate. By considering random fluctuations, the analytical estimate can provide a more realistic and accurate representation of the expected outcome.

Submit
82. In assignment matrix, it is a must to determine Jacobean of the determinant.

Explanation

The statement in the question is incorrect. In an assignment matrix, it is not necessary to determine the Jacobian of the determinant. The Jacobian matrix is used to calculate the determinant of a transformation, but it is not a requirement in an assignment matrix. Therefore, the correct answer is False.

Submit
83. If Kwh consumption per 100 pieces is 8.01 and cost/kwh is Rs 0.80 the cost of power over the year for 40000 pieces with 2000 numbers rejection would be Rs ________.

Explanation

The cost of power over the year for 40000 pieces with 2000 numbers rejection can be calculated by multiplying the Kwh consumption per 100 pieces (8.01) by the number of 100 pieces in 40000 pieces (400) and then multiplying it by the cost/kwh (Rs 0.80). This gives us a total cost of Rs 256.32. Adding the cost of power for the rejected pieces (2000 pieces x Rs 0.80) gives us a total cost of Rs 2692. Therefore, the correct answer is 2692.

Submit
84. A progress card normally contains ________ squares.

Explanation

A progress card typically contains less than 25 squares.

Submit
85. In precedence diagram the length of arrow has very high degree of significance.

Explanation

In a precedence diagram, the length of the arrow does not have a high degree of significance. The length of the arrow in a precedence diagram represents the duration or time required for a particular activity or task. The significance lies in the relationship between the different activities and the dependencies between them, rather than the length of the arrow itself. Therefore, the statement is false.

Submit
86. In linear programming method of line balancing, there are three types of constraints namely :-

Explanation

The correct answer is Cycle time constraint, Step or task constraint, Precedence constraints. In linear programming method of line balancing, these three types of constraints are considered. Cycle time constraint refers to the maximum time allowed for completing a cycle of tasks. Step or task constraint refers to the time required for completing each individual task. Precedence constraints refer to the sequence in which tasks need to be performed. These constraints are important factors in optimizing the efficiency and productivity of a production line.

Submit
87. Time study is useful method of measurement for :-

Explanation

Time study is a useful method of measurement for short cycle time operations because it allows for a detailed analysis of the time taken to complete each step in the process. This helps identify any inefficiencies or bottlenecks that may be causing delays and allows for improvements to be made in order to increase productivity and reduce cycle time. In short cycle time operations, even small improvements in time can have a significant impact on overall efficiency and output. Therefore, time study is an effective tool for optimizing and streamlining these types of operations.

Submit
88. Given a decision for designing a line layout, major problem is subdividing a work so that smooth flow can result. The subdivision process is called :-

Explanation

The correct answer is "Line balancing." In the context of designing a line layout, the major problem is subdividing the work in a way that ensures a smooth flow. This process of dividing the work evenly among the workstations or operators is known as line balancing. It involves assigning tasks or steps to each workstation in a way that minimizes idle time and maximizes productivity.

Submit
89. Good quality and ________are the two main requirements to secure maximum business from a customer.

Explanation

Competitive rates are the two main requirements to secure maximum business from a customer. This means that in order to attract and retain customers, a business must offer rates that are competitive compared to other similar businesses in the market. Good quality alone may not be enough to secure maximum business, as customers often consider pricing as a key factor in their purchasing decisions. Therefore, offering competitive rates is crucial for a business to attract and retain customers, ultimately leading to maximum business success.

Submit
90. Generally for ________ flow system, Heuristic method is preferred.

Explanation

not-available-via-ai

Submit
91. Increase in inventory carrying cost increases EOQ.

Explanation

An increase in inventory carrying cost actually decreases the Economic Order Quantity (EOQ). EOQ is a formula used to calculate the optimal quantity of inventory that should be ordered to minimize the total cost of ordering and carrying inventory. When the carrying cost increases, it becomes more expensive to hold inventory for longer periods, leading to a decrease in the EOQ. This is because ordering smaller quantities more frequently helps reduce the carrying cost. Therefore, the statement that an increase in inventory carrying cost increases EOQ is false.

Submit
92. Progressing is only a substitute for poor planning.

Explanation

This statement suggests that progressing is not a substitute for poor planning. In other words, even if one is making progress, it does not compensate for inadequate or insufficient planning. This implies that proper planning is essential for success, and simply making progress without a solid plan is not enough. Therefore, the correct answer is False.

Submit
93. In PERT, use of dummy activities is not much essential.

Explanation

In PERT (Program Evaluation and Review Technique), the use of dummy activities is actually essential. Dummy activities are used to depict dependencies between tasks that do not require any actual work to be performed. These activities help in accurately representing the sequence and dependencies of tasks in a project, which is crucial for effective project planning and scheduling. Therefore, the given statement is incorrect, and the correct answer is False.

Submit
94. Long termed forecasts are for the period of :-

Explanation

Long-term forecasts typically cover a period of 5 to 10 years. This is because long-term forecasts aim to provide insights into future trends, market conditions, and potential risks and opportunities that may arise over a significant period of time. By looking ahead for 5 to 10 years, businesses and individuals can make more informed decisions and develop strategies that align with their long-term goals and objectives. This time frame allows for a more comprehensive analysis of various factors that may impact the future, such as economic conditions, technological advancements, and demographic changes.

Submit
95. Curve fitting method of statistical forecasting uses curve line approach.

Explanation

The explanation for the given correct answer is that the curve fitting method of statistical forecasting does not necessarily use a curve line approach. It involves fitting a mathematical function to a set of data points, which may or may not result in a curve line. Therefore, the statement that the curve fitting method uses a curve line approach is false.

Submit
96. Effective capacity per period is calculated as :-

Explanation

The effective capacity per period is calculated by multiplying the net capacity with labor efficiency. This calculation takes into account the actual capacity of the system, as well as the efficiency of the labor force in utilizing that capacity. By multiplying these two factors together, we can determine the effective capacity, which represents the maximum amount of output that can be achieved in a given period, taking into account both the available capacity and the efficiency of the labor force.

Submit
97. LOB technique was devised by US army in the year :-

Explanation

The correct answer is 1952. The LOB (Line of Balance) technique was devised by the US army in this year. This technique is used in project management to plan and control repetitive activities, especially in construction projects. It helps in visualizing the sequence and duration of activities, ensuring efficient resource allocation and timely completion of the project.

Submit
98. Development of additional vendors/suppliers depends upon :-

Explanation

The development of additional vendors/suppliers depends on sales forecast because it provides an estimation of the future demand for a product or service. By analyzing the sales forecast, a company can determine if they need to increase their capacity or expand their supply chain to meet the anticipated demand. This information is crucial for identifying the need for additional vendors or suppliers to ensure a smooth and efficient supply of goods or services to customers.

Submit
99. ________items should be excluded from ABC Analysis.

Explanation

Non-moving items should be excluded from ABC Analysis because they are items that have not been sold or used for a long period of time. Including them in the analysis would not provide accurate information about their importance or value. ABC Analysis is a technique used to categorize items based on their significance, and non-moving items do not contribute to the overall inventory management and decision-making process. Therefore, excluding them allows for a more focused and effective analysis of the items that are actually moving and impacting the business.

Submit
100. To operate fixed order quantity system, following parameters are required to be fixed:-

Explanation

In order to operate a fixed order quantity system, three parameters need to be fixed: minimum stock, standard reorder quantity, and re-order point. The minimum stock refers to the minimum quantity of inventory that should be maintained at all times. The standard reorder quantity is the predetermined quantity that should be ordered each time an order is placed. The re-order point is the inventory level at which a new order should be placed to replenish the stock. These parameters ensure that the inventory is managed efficiently and that orders are placed in a timely manner to avoid stockouts.

Submit
101. In PERT, use of dummy activities is not much essential.

Explanation

In PERT (Program Evaluation and Review Technique), the use of dummy activities is essential. Dummy activities are used to represent dependencies between tasks or events that do not require any time or resources. They help in accurately depicting the logical sequence of activities and ensure that the network diagram is properly constructed. Without the use of dummy activities, the network diagram may not accurately represent the project's critical path and could lead to incorrect scheduling and resource allocation. Therefore, the statement "In PERT, use of dummy activities is not much essential" is false.

Submit
102. Transit time for manufactured items should be considered only when it is insignificant.

Explanation

Transit time for manufactured items should be considered even if it is insignificant. This is because transit time can have an impact on the overall efficiency and effectiveness of the manufacturing process. Even if the transit time is minimal, it can still contribute to delays, bottlenecks, and potential disruptions in the supply chain. Therefore, it is important to take into account transit time and find ways to minimize it in order to optimize the manufacturing process.

Submit
103. Keeping available time per day constant, if the desired production rate per day is to be doubled ,cycle time will be reduced by :-

Explanation

If the desired production rate per day is to be doubled while keeping the available time per day constant, the cycle time will need to be reduced by 0.5. This means that each cycle of production will need to be completed in half the time it currently takes.

Submit
104. C type items would never be vital under VED analysis.

Explanation

The statement is false because in VED analysis, C type items can be vital depending on their criticality and availability. VED analysis categorizes items into three categories: Vital, Essential, and Desirable. While Vital items are considered the most critical and necessary for the organization's functioning, Essential and Desirable items are also important but to a lesser extent. Therefore, it is possible for C type items to be vital under VED analysis if they are deemed critical for the organization's operations.

Submit
105. Weaknesses of PPC department can be studied on following grounds :-

Explanation

The weaknesses of the PPC department can be studied based on the failures in delivery commitment, cancellation of orders, and complaints from customers. These factors indicate that the department is not effectively managing the production and delivery of orders. Failures in delivery commitment suggest that the department is not meeting the promised deadlines, which can result in customer dissatisfaction. Cancellation of orders indicates a lack of proper planning and coordination within the department. Complaints from customers highlight issues with the quality or timely delivery of products, which can harm the reputation of the company.

Submit
106. In order to complete a project on time, each critical activity need not be completed in time.

Explanation

The statement is false because in order to complete a project on time, each critical activity must be completed in time. Critical activities are those that have a direct impact on the project's timeline and are essential for its successful completion. If any critical activity is delayed or not completed in time, it can cause delays in the overall project timeline and potentially lead to project failure. Therefore, it is necessary for each critical activity to be completed in a timely manner to ensure the project is completed on time.

Submit
107. A type items are always vital under VED analysis.

Explanation

The statement "A type items are always vital under VED analysis" is false. VED analysis categorizes inventory items based on their criticality and importance. VED stands for Vital, Essential, and Desirable. While it is true that Vital items are always considered important and critical, it does not imply that all A type items are always vital. The categorization of items as vital, essential, or desirable depends on their specific characteristics and importance in the context of the organization's operations. Therefore, the given statement is incorrect.

Submit
108. The batch production requires ________ capital investment as compared to job production.

Explanation

Batch production requires high capital investment as compared to job production because in batch production, large quantities of products are produced at once using standardized processes and equipment. This requires setting up a production line, purchasing specialized machinery, and training workers to operate the equipment efficiently. These initial investments in infrastructure and equipment result in higher capital requirements. On the other hand, job production involves producing customized products in small quantities, which can be done with less specialized equipment and lower initial investments.

Submit
109. If more variety is to be manufactured, the manufacturing facilities would have to be :-

Explanation

If more variety is to be manufactured, the manufacturing facilities would have to be commonised. This means that the facilities would need to be standardized and made more uniform in order to accommodate the production of different varieties. By commonising the manufacturing facilities, companies can streamline their processes and reduce costs by using the same equipment and resources for multiple products. This allows for greater flexibility and efficiency in production, ultimately enabling the company to meet the demands of a wider range of products.

Submit
110. Methods for recording actual progress of work for shop orders are :-

Explanation

The methods for recording actual progress of work for shop orders are progress card, display board, and network updating. A progress card is a document that tracks the progress of each shop order, providing details such as start and end dates, completion percentage, and any delays or issues encountered. A display board is a visual tool that shows the status of each shop order, allowing workers and managers to easily see the progress and identify any bottlenecks or delays. Network updating involves updating the project network or schedule to reflect the actual progress of each shop order, ensuring that the project plan remains accurate and up-to-date.

Submit
111. The assignment algorithm was developed by a Hungarian mathematician named :-

Explanation

The correct answer is Denes Konig and Jeno Egervary. The assignment algorithm, also known as the Hungarian algorithm, was developed by these two Hungarian mathematicians. This algorithm is used to solve the assignment problem, which involves finding the optimal assignment of a set of tasks to a set of agents, minimizing the total cost or maximizing the total benefit. Denes Konig and Jeno Egervary's work on this algorithm has had a significant impact on various fields such as operations research, computer science, and economics.

Submit
112. Random fluctuation is addition of cyclical fluctuation and seasonal fluctuation.

Explanation

The statement is incorrect. Random fluctuation is not the addition of cyclical fluctuation and seasonal fluctuation. Random fluctuation refers to unpredictable and irregular variations in data that cannot be attributed to any specific pattern or trend. Cyclical fluctuation refers to repetitive patterns or cycles that occur over a longer time period, while seasonal fluctuation refers to regular patterns that occur within a shorter time period, such as seasons or months. Therefore, random fluctuation is distinct from cyclical and seasonal fluctuations.

Submit
113. Some of significant characteristics of fixed order quantity system under replenishment systems are as follows :-

Explanation

In a fixed order quantity system, safety stock is maintained to account for potential increases in demand during the lead time, as well as to fulfill demand if the lead time is extended. The re-order level is calculated by adding the safety stock to the average consumption during the lead time. The average inventory is determined by adding the safety stock to half of the reorder quantity. These characteristics ensure that there is enough inventory to meet demand and handle any unexpected fluctuations in demand or lead time.

Submit
114. Process plan is the process of establishing the ________ and most economical path that each part is to follow from raw material stage to finished product stage.

Explanation

The correct answer is "Shortest." In the process plan, the goal is to determine the most efficient and cost-effective path for each part to follow from the raw material stage to the finished product stage. By choosing the shortest path, unnecessary steps and delays can be minimized, resulting in a more streamlined and efficient production process.

Submit
115. Fluctuation due to changes in season are called cyclical fluctuation.

Explanation

Cyclical fluctuations refer to regular patterns of changes that occur over a specific period of time, such as economic cycles or seasonal variations. However, the given statement is incorrect as fluctuations due to changes in season are not called cyclical fluctuations. Seasonal fluctuations are a specific type of cyclical fluctuation that occur due to seasonal changes, but not all cyclical fluctuations are related to seasons.

Submit
116. Price orientation

Explanation

HML Analysis is a method used to classify items based on their value or importance. It stands for High, Medium, and Low analysis. This analysis helps in prioritizing items and making decisions regarding inventory management, pricing, and resource allocation. It categorizes items into three groups based on their impact on the organization's goals and objectives. High-value items are given more attention and resources, while low-value items are managed with less priority. This analysis enables businesses to focus on the most critical items and optimize their operations accordingly.

Submit
117. In order to complete a project on time, each critical activity need not be completed in time.

Explanation

The statement is false because in order to complete a project on time, it is necessary for each critical activity to be completed in time. Critical activities are those that have a direct impact on the project's timeline and are essential for its successful completion. If any critical activity is delayed or not completed in time, it can cause delays in the overall project schedule and potentially lead to project failure. Therefore, it is important to ensure that all critical activities are completed within their designated timeframes to meet project deadlines.

Submit
118. In an organization, poor material handling system may result in the following :-

Explanation

A poor material handling system in an organization can lead to various negative consequences. Firstly, it can result in damage to the material or product being handled, which can lead to financial losses and affect the quality of the final product. Secondly, it can cause delays in the supply of material, disrupting the production process and potentially leading to customer dissatisfaction. Lastly, accidents can occur while handling materials, posing a risk to the safety of employees and potentially causing injuries or even fatalities.

Submit
119. The earliest start time of an activity equals to earliest event time of :-

Explanation

The earliest start time of an activity is determined by the earliest event time of the tail event. This is because the tail event represents the end of the activity, and the earliest start time of the activity cannot be earlier than the time at which the tail event occurs. Therefore, the earliest start time is directly linked to the earliest event time of the tail event.

Submit
120. To operate fixed order quantity system, following parameters are required to be fixed:-

Explanation

The correct answer is Standard reorder quantity, Re-order point, and Minimum stock. These parameters are essential for operating a fixed order quantity system. The standard reorder quantity determines the quantity of items to be ordered when the inventory reaches a certain level. The re-order point indicates the inventory level at which a new order should be placed. The minimum stock represents the minimum quantity of items that should be maintained in inventory to avoid stockouts. These parameters help ensure efficient inventory management and prevent disruptions in the supply chain.

Submit
121. Increase in inventory carrying cost increases EOQ.

Explanation

An increase in inventory carrying cost actually decreases the Economic Order Quantity (EOQ). EOQ is the optimal order quantity that minimizes the total cost of ordering and carrying inventory. When the carrying cost increases, it becomes more expensive to hold inventory for longer periods, leading to a smaller EOQ. This is because higher carrying costs incentivize companies to order smaller quantities more frequently to reduce the amount of inventory held at any given time. Therefore, the statement that an increase in inventory carrying cost increases EOQ is false.

Submit
122. If the annual usage of a material is 1200 units and the reorder point is at 120 Units, find the lead time.

Explanation

The lead time is the time it takes for an order to be delivered once it has been placed. In this case, the annual usage of the material is 1200 units and the reorder point is at 120 units. This means that when the inventory reaches 120 units, a new order is placed. Since the annual usage is 1200 units, it would take 10 months to deplete the inventory completely. Therefore, the lead time must be longer than 10 months to ensure that there is no stockout. The only option that satisfies this condition is 4 months.

Submit
123. They are type of analytical estimate :-

Explanation

Moving average, exponential smoothing, and curve fitting are all types of analytical estimates. These methods are used to analyze and predict trends or patterns in data.

Moving average calculates the average of a set of data points over a specific period of time, providing a smoothed representation of the data.

Exponential smoothing assigns weights to recent data points, giving more importance to recent observations and less to older ones. This method is useful for forecasting short-term trends.

Curve fitting involves finding a mathematical function that best fits a set of data points. This allows for the creation of a curve that represents the overall trend of the data.

These three methods are commonly used in data analysis and forecasting to make informed decisions based on historical patterns and trends.

Submit
124. Find EOQ in Rs from the following data :-Annual consumption = 20, 000 units, Ordering and receiving cost of material = Rs 20 per order, Annual carrying cost or storage cost = 10% of unit cost of material, Cost of material = Rs 50.

Explanation

The Economic Order Quantity (EOQ) is a formula used to determine the optimal order quantity that minimizes the total cost of ordering and carrying inventory. In this case, the annual consumption is given as 20,000 units, the ordering and receiving cost is Rs 20 per order, the annual carrying cost is 10% of the unit cost of material, and the cost of material is Rs 50. To calculate the EOQ, we need to use the formula EOQ = sqrt((2 * Annual consumption * Ordering and receiving cost) / Annual carrying cost). Plugging in the given values, we get EOQ = sqrt((2 * 20000 * 20) / (0.1 * 50)) = sqrt(80000) = 20000. Therefore, the correct answer is 20000.

Submit
125. In CPM, use of dummy activities is much essential .

Explanation

The statement is false because in CPM (Critical Path Method), the use of dummy activities is not essential. Dummy activities are used in PERT (Program Evaluation and Review Technique) to represent logical relationships between tasks, but they are not required in CPM. CPM focuses on determining the critical path and the minimum project duration, while PERT incorporates probabilistic time estimates and is used for projects with uncertain activity durations.

Submit
126. Earliest possible occurrence time [ I.e. stray time ] of activity [ies ] emanating from the

Explanation

The earliest event time refers to the earliest possible occurrence time of an activity emanating from the event. It represents the earliest point in time when the activity can start or take place. This is the time at which all preceding activities have been completed and the event is ready to occur. It is important to consider the earliest event time in project planning and scheduling to ensure that activities are properly sequenced and dependencies are taken into account.

Submit
127. The effectiveness of sequencing model technique ________ if the company has backlog of

Explanation

The effectiveness of sequencing model technique increases if the company has a backlog. This is because the sequencing model technique helps in prioritizing and scheduling tasks in an efficient manner. When there is a backlog, it means there are pending tasks that need to be completed. By using the sequencing model technique, the company can effectively prioritize and schedule these tasks, ensuring that they are completed in a timely manner. This ultimately increases the effectiveness of the technique in managing the backlog.

Submit
128. Curve fitting method of statistical forecasting uses curve line approach.

Explanation

The statement is false because curve fitting method of statistical forecasting does not use a curve line approach. Instead, it uses mathematical equations to fit a curve to the historical data points and make predictions based on the fitted curve. This method is used to find the best fit curve that represents the relationship between variables, rather than drawing a curve line through the data points.

Submit
129. Flexibility and product variety are not inter-related with each other.

Explanation

Flexibility and product variety are inter-related with each other. Flexibility refers to the ability of a company to adapt and respond to changes in the market, customer demands, and production processes. Product variety, on the other hand, refers to the range of different products or variations offered by a company. A company with high flexibility can easily introduce new products and adapt its production processes to accommodate a wide variety of products. Therefore, flexibility and product variety are closely connected, and they influence each other in a company's ability to meet customer needs and stay competitive in the market.

Submit
130. The commonly used network techniques other than PERT and CPM are as follows :-

Explanation

The correct answer includes MOSS, PCS, and GERT as commonly used network techniques other than PERT and CPM. MOSS stands for Multi Operation Scheduling System and is used for scheduling and optimizing operations in a project. PCS, which stands for Project Control System, is used for monitoring and controlling project activities. GERT, or Graphical Evaluation Review Techniques, is a network analysis technique that allows for probabilistic treatment of project uncertainties. These techniques are alternatives to PERT and CPM and provide different approaches to project planning, scheduling, and control.

Submit
131. Negative value of critical ratio :-

Explanation

The negative value of critical ratio is meaningless because the critical ratio is a measure used in project management to prioritize tasks based on their importance and urgency. It is calculated by dividing the time remaining until the deadline by the time required to complete the task. A negative value would imply that the task is already overdue, which contradicts the concept of critical ratio. Therefore, a negative critical ratio is not a valid or meaningful measure in project management.

Submit
132. The commonly used network techniques other than PERT and CPM are as follows :-

Explanation

not-available-via-ai

Submit
133. The software for CPA would require the following parameters:-

Explanation

The software for CPA requires algorithms, program code, and a database. Algorithms are necessary to perform calculations and processes required for accounting tasks. Program code is needed to implement the algorithms and create the software. A database is essential for storing and managing the financial data and information. Additionally, an operating system is required to run the software, but it is not explicitly mentioned in the answer.

Submit
134. The following are salient features of the fixed order quantity system :-

Explanation

The fixed order quantity system has the following salient features: the reorder quantity is always the same, usually the economic order quantity; the time interval between deliveries varies; replenishment action is initiated when the stock on hand is just sufficient to meet demand during the lead time. These features ensure that the inventory is managed efficiently by maintaining a constant order quantity, adjusting the time interval based on demand fluctuations, and replenishing stock just in time to meet customer demand. Taking into consideration the percent cumulative cost of the item helps in optimizing inventory costs.

Submit
135. The 'G' group of GOLF analysis covers items procurement from Government suppliers such as :-

Explanation

The correct answer includes STC, MMTC, and Public Sector Undertaking. These are all examples of government suppliers that fall under the 'G' group of GOLF analysis. STC and MMTC are both government-owned trading companies, while Public Sector Undertaking refers to any government-owned corporation or company. These entities play a crucial role in the procurement of items for the government, making them relevant to the GOLF analysis.

Submit
136. Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time :-

Explanation

When there is tool breakage, it means that the tool being used for the job has malfunctioned or is no longer usable. This will require additional time to fix or replace the tool, resulting in a longer queue time. Job split up refers to dividing a single job into multiple smaller tasks. This can increase the overall time required to complete the job, leading to a longer queue time. Change in priorities means that the order in which jobs need to be completed has been altered. This can disrupt the existing queue and result in a longer wait time for certain jobs.

Submit
137. In a mass production assembly shop following work measurement techniques are used :-

Explanation

The correct answer is Time study, Work sampling, Production study. These three techniques are commonly used in mass production assembly shops to measure and analyze work processes. Time study involves observing and timing the tasks performed by workers to determine the standard time required for each task. Work sampling involves taking random samples of work activities to determine the proportion of time spent on different tasks. Production study involves analyzing the production process to identify bottlenecks, inefficiencies, and areas for improvement. These techniques help in optimizing productivity, identifying areas for improvement, and setting realistic production goals.

Submit
138. LOB has advantage that it is more ________ oriented than MRP.

Explanation

The correct answer is "Customer". The explanation for this is that LOB (Line of Business) focuses more on meeting the needs and preferences of the customers. It prioritizes customer satisfaction and aims to deliver products or services that cater to their specific requirements. On the other hand, MRP (Material Requirements Planning) primarily focuses on managing and optimizing the flow of materials and resources within a manufacturing process. While both approaches are important in business operations, LOB places a greater emphasis on customer-centricity.

Submit
139. The main characteristics of mass and flow production are :-

Explanation

The main characteristics of mass and flow production include a continuous flow of material, the utilization of low skilled labor, and easy supervision. In mass and flow production, materials are constantly moving through the production process, ensuring a smooth and uninterrupted workflow. Low skilled labor is often employed in these types of production systems as the tasks involved are more repetitive and require less specialized knowledge. Additionally, the supervision of these production systems is relatively easy due to the standardized processes and clear workflow, making it easier to monitor and manage the production line.

Submit
140. The Heuristics approach has a base of binary number theory.

Explanation

The statement is false because the Heuristics approach does not have a base of binary number theory. Heuristics is a problem-solving approach that involves using rules of thumb or educated guesses to find solutions. It is not based on binary number theory, which is a branch of mathematics that deals with binary numbers and their operations.

Submit
141. In replenishment system, the fixed order quantity system is also called by following names :-

Explanation

The correct answer is "Fixed order system, Min-max system, Re-order point system." In a replenishment system, the fixed order quantity system is referred to by different names. The first name, "Fixed order system," indicates that a specific quantity is ordered each time inventory reaches a certain level. The second name, "Min-max system," implies that there are minimum and maximum inventory levels, and orders are placed when inventory falls below the minimum level or reaches the maximum level. The third name, "Re-order point system," suggests that orders are triggered when inventory reaches a predetermined re-order point.

Submit
142. The assignment method is also called as :-

Explanation

The correct answer is Hungarian Method. The assignment method refers to a mathematical technique used to solve optimization problems involving the allocation of resources to tasks. The Hungarian Method is a specific algorithm used to solve the assignment problem, which aims to find the optimal assignment of resources to tasks. It involves finding the minimum cost or maximum profit assignment by iteratively reducing the problem into a series of smaller subproblems. This method is widely used in various fields, including operations research and computer science.

Submit
143. While communicating to customer on delays in delivery following information should be given :-

Explanation

When communicating with a customer about delays in delivery, it is important to provide them with information on the identification of the job, such as the order number or tracking information, so that they can easily reference it. Additionally, it is important to explain the reasons for the delays, whether it be due to production issues, logistical problems, or any other factors. Lastly, providing the customer with a revised date of delivery is crucial to manage their expectations and keep them informed about when they can expect to receive their order.

Submit
144. In check list approach, ________ rating indicates that existing PPC system requires some major improvements in indicated areas.

Explanation

In the check list approach, a "fair" rating indicates that the existing PPC system requires some major improvements in the indicated areas. This means that the system is not performing well and needs significant enhancements to meet the desired standards. A fair rating suggests that there are noticeable deficiencies in the PPC system and it is necessary to make substantial changes to improve its effectiveness and efficiency.

Submit
145. Total lead time is the summation of following factors :-

Explanation

The correct answer is that the total lead time is the sum of queue and transit time, delay time, manufacturing time, and order preparation time. This means that when calculating the total lead time for a process or project, all these factors need to be taken into account. Queue and transit time refer to the time it takes for a product to move through various stages or departments. Manufacturing time is the time needed to actually produce the product. Order preparation time is the time it takes to process and prepare an order. By considering all these factors, a more accurate estimate of the total lead time can be obtained.

Submit
146. Classification of items on basis of their capital lock up is called ________ analysis.

Explanation

The correct answer is XYZ. XYZ analysis is a classification method used to categorize items based on their capital lock up. This analysis helps in determining the importance of items in inventory management by considering their value, demand, and usage. It helps in identifying which items require closer monitoring and control based on their impact on capital investment.

Submit
147. The minimum requirements for application software for line balancing are as follows :-

Explanation

The minimum requirements for application software for line balancing include a 1 Ghz processor, 1 Gb hard Disk free memory, and Windows or an equivalent operating system. These specifications are necessary to ensure that the software runs smoothly and efficiently on the user's computer. The processor speed of 1 Ghz ensures that the software can handle the calculations and processes required for line balancing. The 1 Gb hard disk free memory provides enough storage space for the software and its data. Lastly, Windows or an equivalent operating system is necessary for compatibility and proper functioning of the software.

Submit
148. Move orders, released for material movement from stores to first work center are used for following types of organizations :-

Explanation

Move orders are typically used in organizations that involve the movement of materials from stores to the first work center. This includes big steel plants, power plants, heavy machinery manufacturers, and high volume white goods manufacturers. In these types of organizations, there is a need to efficiently manage and track the movement of materials to ensure smooth production processes. Move orders help in coordinating and prioritizing the movement of materials, ensuring that they reach the appropriate work centers in a timely manner.

Submit
149. Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time :-

Explanation

The given answer suggests that tool breakage, job split up, and change in priorities are emergent events that can cause the queue time to increase. When a tool breaks, it may take time to repair or replace it, leading to delays in the job. Similarly, if a job is split up into multiple tasks, it can increase the overall processing time and queue time. Additionally, a change in priorities can disrupt the planned order of jobs, causing delays and longer queue times. These events require additional time and resources, leading to a need for compensation in the queue time.

Submit
150. Labour efficiency factor is applied after capacity requirement of equipment is calculated.

Explanation

Labour efficiency factor is not applied after the capacity requirement of equipment is calculated. Instead, the labour efficiency factor is used to calculate the capacity requirement of equipment. It takes into account the efficiency of the labor force and helps determine the amount of equipment needed to meet the required production levels. Therefore, the correct answer is False.

Submit
151. Computerisation of line balancing involve following requirements :-

Explanation

The computerisation of line balancing requires system software, application software, and a user-friendly interface. System software is necessary to manage and control the computer system's operations, while application software is needed to perform specific tasks related to line balancing. A user-friendly interface is important to ensure that users can easily interact with the computer system and perform line balancing operations efficiently.

Submit
152. Scheduling can be considered as a process of :-

Explanation

The correct answer is fitting shop order into uncommitted time available for a machine. Scheduling involves organizing and allocating tasks or orders in a way that optimizes the use of available resources, such as machines. This includes determining the time required for each operation and then fitting the shop orders into the uncommitted time slots available for a specific machine. By effectively scheduling and allocating resources, businesses can improve productivity and ensure that orders are completed in a timely manner.

Submit
153. Following difficulties are faced by SDE analysis :-

Explanation

The given answer correctly identifies the difficulties faced by SDE analysis, which include more delivery period, geographical location of the supplier, and reliability of suppliers. These factors can impact the efficiency and effectiveness of the analysis process. Longer delivery periods can delay the analysis and affect project timelines. The geographical location of the supplier can introduce logistical challenges and increase costs. The reliability of suppliers is crucial for obtaining accurate and timely data, as any inconsistencies or delays can affect the analysis results.

Submit
154. What factors affect the status of PPC department in the company for achieving informal status?

Explanation

The status of the PPC (Production Planning and Control) department in a company for achieving informal status is affected by the manufacturing process, the repetitiveness of the work, and the number of workmen. If the manufacturing process is efficient and well-organized, it can contribute to the informal status of the PPC department. Similarly, if the work is highly repetitive, it allows for better planning and control, leading to a higher status. On the other hand, if the number of workmen is not very large, it can facilitate better coordination and communication within the department, contributing to its informal status.

Submit
155. Subsidiary orders include :-

Explanation

The given answer lists the correct order of subsidiary orders, starting with Material Order, followed by Shop order and Inspection order. This suggests that Material Order is the first subsidiary order, followed by Shop order and then Inspection order. The order of the subsidiary orders is important in a business process as it determines the flow and sequence of activities.

Submit
156. Work measurement is responsibility of :-

Explanation

Work measurement is the process of determining the amount of time required to complete a specific task or job. It involves analyzing and evaluating various factors such as the complexity of the task, the skill level required, and the available resources. PPC (Production Planning and Control) is responsible for planning and scheduling production activities, including work measurement. Industrial engineering is also involved in work measurement as it focuses on improving efficiency and productivity in the workplace. The production department is responsible for executing the production plan and ensuring that work is completed within the allocated time. Therefore, all three options - PPC, industrial engineering, and production department - are responsible for work measurement.

Submit
157. Overtime can be avoided in many ways and they are :-

Explanation

Overtime can be avoided by not accepting too many rush orders, as this puts additional pressure on the workforce and may require them to work extra hours to meet the deadlines. Unrealistic delivery dates can also lead to overtime as employees may need to work longer hours to complete the tasks within the given timeframe. Insufficient manpower or machines can result in overtime as the available resources may not be enough to complete the work on time. Excessive machine breakdowns can cause delays in production, leading to the need for overtime to catch up on the lost time.

Submit
158. The tooling data is prepared in respect of following measuring instruments :-

Explanation

The correct answer includes Vernier caliper, Micrometer screw gauge, and Strain gauge. These three measuring instruments are commonly used in various industries for precise measurements. The Vernier caliper is used to measure the dimensions of an object with high accuracy, while the Micrometer screw gauge is used for measuring small distances with even greater precision. The Strain gauge, on the other hand, is used to measure strain or deformation in an object, making it useful in engineering and material testing applications.

Submit
159. Job production requires ________ capital investment.

Explanation

Job production requires the lowest capital investment compared to other production methods. This is because job production involves producing customized products or services in small quantities, often one at a time, to meet specific customer requirements. As a result, the production process is more flexible and adaptable, requiring less investment in specialized machinery, equipment, and infrastructure. In contrast, mass production or batch production methods typically require higher levels of capital investment to set up assembly lines, purchase large quantities of raw materials, and invest in automation technologies. Therefore, job production is the most cost-effective option in terms of capital investment.

Submit
160. PERT terminology uses words like :-

Explanation

PERT (Program Evaluation and Review Technique) is a project management method that uses specific terminology. A network diagram is a visual representation of project activities and their dependencies. It helps in understanding the flow of work and identifying critical paths. Events refer to specific points in time within the project, such as the start or completion of an activity. Slack is the amount of time an activity can be delayed without affecting the project's overall timeline. These terms are essential in PERT to effectively plan and manage projects.

Submit
161. On completion of work the job card is returned to production planning and control department for reference and record.

Explanation

The job card is not returned to the production planning and control department for reference and record upon completion of work. This statement is false.

Submit
162. 5 jobs are to be processed on machines M1 and M2 , first on M1 and then on M2. The processing times in hours are as follows.Find the sequence for 5 jobs that will minimize total elapsed time .also find idle time & total elapsed time. Job Processing time [ hours ] Machine M1 Machine M2 1 5 2 2 1 6 8 9 7 6 3 8 5 10 4

Explanation

The sequence 2-4-3-5-1 is the optimal sequence for processing the 5 jobs on machines M1 and M2. This sequence minimizes the total elapsed time, which is 28 hours. The idle time for M1 is 1 hour and for M2 is 2 hours.

Submit
163. In a mass production assembly shop following work measurement techniques are used :-

Explanation

The correct answer is Time study, Work sampling, and Production study. These techniques are commonly used in mass production assembly shops to measure and analyze work processes. Time study involves observing and timing each step of a task to determine the standard time required. Work sampling involves randomly observing and recording the activities of workers to estimate the proportion of time spent on different tasks. Production study involves analyzing the overall production process to identify areas for improvement and increase efficiency. These techniques help in optimizing productivity, identifying bottlenecks, and making informed decisions for process improvement.

Submit
164. If actual demand far exceeds forecast, it will result into :-

Explanation

When the actual demand far exceeds the forecast, it indicates that there is a higher demand for the product or service. This leads to better utilization of equipment as more equipment will be needed to meet the increased demand. Additionally, the project margin will increase as the company will be able to sell more products or services at a higher price. Lastly, there will be a higher material purchase as more materials will be required to fulfill the increased demand.

Submit
165. Steps involved in process planning include the following :-

Explanation

The correct answer includes three steps involved in process planning: enlisting features that influence the selection of the manufacturing process, preparing the sequence of basic operations, and writing down the route sheet. These steps are crucial in determining the most suitable manufacturing process, organizing the order of operations, and documenting the necessary steps to complete the production process efficiently.

Submit
166. Important considerations in scheduling are :-

Explanation

The important considerations in scheduling are the degree of centralization, relative job priority, and load chart. The degree of centralization refers to how much decision-making power is centralized in the scheduling process. This can vary depending on the organizational structure and the level of autonomy given to different departments or individuals. Relative job priority involves determining the order in which jobs or tasks should be scheduled based on their importance or urgency. A load chart is a visual representation of the workload and capacity of resources, which helps in balancing and optimizing the scheduling process.

Submit
167. The expected time can be minimised by minimising following parameters :-

Explanation

By minimizing the optimistic time, pessimistic time, and most likely time, the expected time can be minimized. The optimistic time represents the best-case scenario, while the pessimistic time represents the worst-case scenario. The most likely time is the most probable estimate. By minimizing these parameters, the range of possible outcomes is reduced, resulting in a more accurate and efficient expected time calculation.

Submit
168. HML Analysis helps to :-

Explanation

HML Analysis helps in accessing storage and security requirements by analyzing the inventory levels and determining the appropriate storage conditions and security measures needed. It also helps in keeping control over departmental head level by providing insights into the inventory management practices of different departments and identifying areas where improvements can be made. Additionally, HML Analysis helps in determining the frequency of stock verification by analyzing the inventory turnover rate and identifying the optimal time for conducting stock checks.

Submit
169. Standard time accounts for :-

Explanation

Standard time accounts for contingency allowance, operator's rating/efficiency, and tool change time. Contingency allowance refers to the extra time allocated to account for unforeseen events or delays that may occur during the task. Operator's rating/efficiency takes into consideration the skill level and productivity of the operator performing the task. Tool change time accounts for the time required to change or adjust tools or equipment used in the task. These factors are considered in standard time calculations to ensure a realistic estimate of the time required to complete the task.

Submit
170. Detachable Card contain following information :-

Explanation

The detachable card contains information about the quantity of the product that has been produced, the specific operation that was performed, and the date on which the production was completed. This information is crucial for tracking and managing the production process, as it allows for accurate record-keeping and monitoring of progress.

Submit
171. The queue time is intended to compensate for the time for which the job has to :-

Explanation

The queue time is necessary to account for various delays and waiting periods that a job may experience during its processing. This includes waiting near the machines for its turn when there are other jobs ahead of it, as well as waiting after its completion until it is picked up and moved to the next machine or work center. Additionally, the queue time also factors in any extra time that may be required due to emergent situations, such as equipment breakdowns or unexpected delays.

Submit
172. Material control function embraces a following techniques :-

Explanation

The material control function includes various techniques such as make-or-buy decision, Pareto's analysis, and replenishment system. The make-or-buy decision involves determining whether to produce a product in-house or purchase it from an external supplier. Pareto's analysis is a method used to prioritize items based on their importance or impact. The replenishment system ensures that materials are restocked in a timely manner to avoid shortages. These techniques help in effectively managing and controlling the flow of materials within an organization.

Submit
173. Smoothing performs following activities:-

Explanation

The given activities of smoothing include reallocation of resources, improving utilization of resources, and conducting heuristic approach. Reallocation of resources refers to the process of redistributing resources to different areas or tasks in order to optimize efficiency. Improving utilization of resources involves finding ways to maximize the use of available resources to achieve better results. Conducting heuristic approach means using a problem-solving technique that involves trial and error or rule of thumb to find solutions. These activities are all part of the smoothing process.

Submit
174. Process Sheet contains following information :-

Explanation

The process sheet contains information about the material specification, sequence of operation, and skill of labor. This means that the sheet provides details about the specific materials required for the process, the order in which operations should be performed, and the level of skill needed from the labor involved. These factors are crucial in ensuring that the process is carried out correctly and efficiently.

Submit
175. Detachable Card contain following information :-

Explanation

The detachable card contains information about the quantity produced, the operation being performed, and the date of completion. This information is important for tracking and recording the production process. The quantity produced indicates how many units have been manufactured, the operation specifies the specific task or step being carried out, and the date of completion helps to monitor the progress and timeline of the production.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 22, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • May 14, 2009
    Quiz Created by
    S_mai_s
Cancel
  • All
    All (175)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
There are five manufacturing systems. However, many manufacturers...
Mass & flow production and process production are categorized...
The make-or-buy decision becomes necessary when the current source of ...
Line staff can assist PPC by manufacturing some of their needs in...
Purchase department must keep PPC informed regarding lead time of...
Moving average method lags behind the latest trend.
Orders with ________ slack time remaining per operation are run first.
Buying for C quantities should be made in ________ quantities .
Stores issue order for an item is prepared as soon as the route sheet...
When shop floor scheduling problem larger than 3 machines arise the ...
Exponential smoothening is weighted average method.
The make-or-buy decision is not taken only at starting of a factory...
Inspection operations is a part of process plan for a part.
A company where different personnel give conflicting delivery promises...
Lead time is ________ for different items.
Heuristics approach gave very good results when Wester and Kilbridge...
The non-mathematical rationale of the assignment method is one of...
Overlapping of operations helps in compressing manufacturing time.
PERT uses linear programming and probability concepts for planning and...
LOB is a manual planning and scheduling technique similar in nature to...
Because of uncertainty of activity timings, PERT acquired a shape of...
The LOB technique is most appropriate for assembly operations...
Keeping procurement cost and carrying cost constant, if annual usage...
The sourcing of vendors in case of 'B' type of items is :-
XYZ analysis helps to identify few items which account for large...
________ is a production line made up of operations that form or...
Forecasting is function of ________.
As the quantity increases, the procurement cost :-
Rational figure on utilization index can be obtained by carrying out...
To solve "n jobs - 3 machines" sequencing problem, the largest of...
As per a study on materials management practices, a typical firm...
Sequencing helps management to determine the most economical job...
The assembly work content [ Wi ] of the i'th station having n work...
PERT is suitable in defense projects and R&D where activity times...
The sourcing of vendors in case of 'B' type of items is :-
What shall be the consequence of acceptance of frequent rush orders by...
Ordering of raw material is based on :-
To solve "n jobs - 2 machines" sequencing problem, it is assumed that ...
The 'G' group of GOLF analysis involves moderate delivery time and...
If set up time for four operations involved is 2 ,1.5, 2 , 2.5 hours...
C type items would never be vital under VED analysis.
In replenishment system, the type of ordering is either according to...
Short term forecasts are for ________.
One of the causes of inability to meet delivery date originally...
________ inventories help to balance company's supply with market...
Work sampling is ________
Proper Production Planning and Control can reduce cost in :-
Activity R can not start unless activities P & Q are completed . ...
To keep facilities busy, waiting time due to non-availability of work...
Labour efficiency depends upon ________
________ is the sum of set up time and run time.
Installed capacity :-
Stock of finished goods are based on :-
Being capable to adjust their production facilities shortly just...
Responsibility of smooth flow of work through different work centers...
Ordering of raw material is based on :-
The cost involved in subcontracting some of the operations of item...
As the quantity increases, the procurement cost :-
The make-or-buy decision is not related with profit of the factory.
The light engineering company has one special purpose facing & ...
Of all the work measurement techniques the most widely used techniques...
If number of work stations is 8 and work content of all stations is 32...
The data in respect of spindle nose pertains to :-
A firm has 6 jobs to be processed on three machines A,B and C in the ...
Production output in night shift is :-
Detachable ticket, after filling in required information is :-
Physical Count method of collecting information from manufacturing...
________ analysis mainly helps to identify non-existing items for...
If efficiency is more, the manufacturing time required for completion...
In ABC analysis, the classification is based on :-
________ are grouped so that their total time is preferably equal to...
The administrative lead time e.g. time involved in processing the ...
A type items are always vital under VED analysis.
Buying for C quantities should be made in ________ quantities .
The LOB technique is made more accurate and fast by using ________.
The ROI of the company can be increased by :-
Work measurement is not useful for choosing between two alternate...
Production Planning and Control makes the supervisor ineffective.
Given the following data :- procurement cost per order = Rs 30 ; ...
In alternate routing, the delayed job may be routed to a ________...
Random fluctuation is considered for deciding ________.
In assignment matrix, it is a must to determine Jacobean of the...
If Kwh consumption per 100 pieces is 8.01 and cost/kwh is Rs 0.80 the ...
A progress card normally contains ________ squares.
In precedence diagram the length of arrow has very high degree of...
In linear programming method of line balancing, there are three types...
Time study is useful method of measurement for :-
Given a decision for designing a line layout, major problem is ...
Good quality and ________are the two main requirements to secure...
Generally for ________ flow system, Heuristic method is preferred.
Increase in inventory carrying cost increases EOQ.
Progressing is only a substitute for poor planning.
In PERT, use of dummy activities is not much essential.
Long termed forecasts are for the period of :-
Curve fitting method of statistical forecasting uses curve line...
Effective capacity per period is calculated as :-
LOB technique was devised by US army in the year :-
Development of additional vendors/suppliers depends upon :-
________items should be excluded from ABC Analysis.
To operate fixed order quantity system, following parameters are...
In PERT, use of dummy activities is not much essential.
Transit time for manufactured items should be considered only when it...
Keeping available time per day constant, if the desired production...
C type items would never be vital under VED analysis.
Weaknesses of PPC department can be studied on following grounds :-
In order to complete a project on time, each critical activity need...
A type items are always vital under VED analysis.
The batch production requires ________ capital investment as compared...
If more variety is to be manufactured, the manufacturing facilities...
Methods for recording actual progress of work for shop orders are :-
The assignment algorithm was developed by a Hungarian mathematician...
Random fluctuation is addition of cyclical fluctuation and seasonal...
Some of significant characteristics of fixed order quantity system...
Process plan is the process of establishing the ________ and most ...
Fluctuation due to changes in season are called cyclical fluctuation.
Price orientation
In order to complete a project on time, each critical activity need...
In an organization, poor material handling system may result in the...
The earliest start time of an activity equals to earliest event time...
To operate fixed order quantity system, following parameters are...
Increase in inventory carrying cost increases EOQ.
If the annual usage of a material is 1200 units and the reorder point...
They are type of analytical estimate :-
Find EOQ in Rs from the following data :-Annual consumption = 20, 000 ...
In CPM, use of dummy activities is much essential .
Earliest possible occurrence time [ I.e. stray time ] of activity [ies...
The effectiveness of sequencing model technique ________ if the...
Curve fitting method of statistical forecasting uses curve line...
Flexibility and product variety are not inter-related with each other.
The commonly used network techniques other than PERT and CPM are as...
Negative value of critical ratio :-
The commonly used network techniques other than PERT and CPM are as...
The software for CPA would require the following parameters:-
The following are salient features of the fixed order quantity system...
The 'G' group of GOLF analysis covers items procurement from...
Due to the following emergent events, the queue time has to...
In a mass production assembly shop following work measurement...
LOB has advantage that it is more ________ oriented than MRP.
The main characteristics of mass and flow production are :-
The Heuristics approach has a base of binary number theory.
In replenishment system, the fixed order quantity system is also...
The assignment method is also called as :-
While communicating to customer on delays in delivery following...
In check list approach, ________ rating indicates that existing PPC...
Total lead time is the summation of following factors :-
Classification of items on basis of their capital lock up is called...
The minimum requirements for application software for line balancing...
Move orders, released for material movement from stores to first work...
Due to the following emergent events, the queue time has to...
Labour efficiency factor is applied after capacity requirement of...
Computerisation of line balancing involve following requirements :-
Scheduling can be considered as a process of :-
Following difficulties are faced by SDE analysis :-
What factors affect the status of PPC department in the company for...
Subsidiary orders include :-
Work measurement is responsibility of :-
Overtime can be avoided in many ways and they are :-
The tooling data is prepared in respect of following measuring...
Job production requires ________ capital investment.
PERT terminology uses words like :-
On completion of work the job card is returned to production planning...
5 jobs are to be processed on machines M1 and M2 , first on M1 and...
In a mass production assembly shop following work measurement...
If actual demand far exceeds forecast, it will result into :-
Steps involved in process planning include the following :-
Important considerations in scheduling are :-
The expected time can be minimised by minimising following parameters...
HML Analysis helps to :-
Standard time accounts for :-
Detachable Card contain following information :-
The queue time is intended to compensate for the time for which the...
Material control function embraces a following techniques :-
Smoothing performs following activities:-
Process Sheet contains following information :-
Detachable Card contain following information :-