There are five manufacturing systems. However, many manufacturers...
Mass & flow production and process production are categorized...
The make-or-buy decision becomes necessary when the current source of
...
Line staff can assist PPC by manufacturing some of their needs in...
Purchase department must keep PPC informed regarding lead time of...
Moving average method lags behind the latest trend.
Orders with ________ slack time remaining per operation are run first.
Buying for C quantities should be made in ________ quantities .
Stores issue order for an item is prepared as soon as the route sheet...
When shop floor scheduling problem larger than 3 machines arise the
...
Exponential smoothening is weighted average method.
The make-or-buy decision is not taken only at starting of a factory...
Inspection operations is a part of process plan for a part.
A company where different personnel give conflicting delivery promises...
Lead time is ________ for different items.
Heuristics approach gave very good results when Wester and Kilbridge...
The non-mathematical rationale of the assignment method is one of...
Overlapping of operations helps in compressing manufacturing time.
PERT uses linear programming and probability concepts for planning and...
LOB is a manual planning and scheduling technique similar in nature to...
Because of uncertainty of activity timings, PERT acquired a shape of...
The LOB technique is most appropriate for assembly operations...
Keeping procurement cost and carrying cost constant, if annual usage...
The sourcing of vendors in case of 'B' type of items is :-
XYZ analysis helps to identify few items which account for large...
________ is a production line made up of operations that form or...
Forecasting is function of ________.
As the quantity increases, the procurement cost :-
Rational figure on utilization index can be obtained by carrying out...
To solve "n jobs - 3 machines" sequencing problem, the largest of...
As per a study on materials management practices, a typical firm...
Sequencing helps management to determine the most economical job...
The assembly work content [ Wi ] of the i'th station having n work...
PERT is suitable in defense projects and R&D where activity times...
The sourcing of vendors in case of 'B' type of items is :-
What shall be the consequence of acceptance of frequent rush orders by...
Ordering of raw material is based on :-
To solve "n jobs - 2 machines" sequencing problem, it is assumed that
...
The 'G' group of GOLF analysis involves moderate delivery time and...
If set up time for four operations involved is 2 ,1.5, 2 , 2.5 hours...
C type items would never be vital under VED analysis.
In replenishment system, the type of ordering is either according to...
Short term forecasts are for ________.
One of the causes of inability to meet delivery date originally...
________ inventories help to balance company's supply with market...
Work sampling is ________
Proper Production Planning and Control can reduce cost in :-
Activity R can not start unless activities P & Q are completed .
...
To keep facilities busy, waiting time due to non-availability of work...
Labour efficiency depends upon ________
________ is the sum of set up time and run time.
Installed capacity :-
Stock of finished goods are based on :-
Being capable to adjust their production facilities shortly just...
Responsibility of smooth flow of work through different work centers...
Ordering of raw material is based on :-
The cost involved in subcontracting some of the operations of item...
As the quantity increases, the procurement cost :-
The make-or-buy decision is not related with profit of the factory.
The light engineering company has one special purpose facing &
...
Of all the work measurement techniques the most widely used techniques...
If number of work stations is 8 and work content of all stations is 32...
The data in respect of spindle nose pertains to :-
A firm has 6 jobs to be processed on three machines A,B and C in the
...
Production output in night shift is :-
Detachable ticket, after filling in required information is :-
Physical Count method of collecting information from manufacturing...
________ analysis mainly helps to identify non-existing items for...
If efficiency is more, the manufacturing time required for completion...
In ABC analysis, the classification is based on :-
________ are grouped so that their total time is preferably equal to...
The administrative lead time e.g. time involved in processing the
...
A type items are always vital under VED analysis.
Buying for C quantities should be made in ________ quantities .
The LOB technique is made more accurate and fast by using ________.
The ROI of the company can be increased by :-
Work measurement is not useful for choosing between two alternate...
Production Planning and Control makes the supervisor ineffective.
Given the following data :- procurement cost per order = Rs 30 ;
...
In alternate routing, the delayed job may be routed to a ________...
Random fluctuation is considered for deciding ________.
In assignment matrix, it is a must to determine Jacobean of the...
If Kwh consumption per 100 pieces is 8.01 and cost/kwh is Rs 0.80 the
...
A progress card normally contains ________ squares.
In precedence diagram the length of arrow has very high degree of...
In linear programming method of line balancing, there are three types...
Time study is useful method of measurement for :-
Given a decision for designing a line layout, major problem is
...
Good quality and ________are the two main requirements to secure...
Generally for ________ flow system, Heuristic method is preferred.
Increase in inventory carrying cost increases EOQ.
Progressing is only a substitute for poor planning.
In PERT, use of dummy activities is not much essential.
Long termed forecasts are for the period of :-
Curve fitting method of statistical forecasting uses curve line...
Effective capacity per period is calculated as :-
LOB technique was devised by US army in the year :-
Development of additional vendors/suppliers depends upon :-
________items should be excluded from ABC Analysis.
To operate fixed order quantity system, following parameters are...
In PERT, use of dummy activities is not much essential.
Transit time for manufactured items should be considered only when it...
Keeping available time per day constant, if the desired production...
C type items would never be vital under VED analysis.
Weaknesses of PPC department can be studied on following grounds :-
In order to complete a project on time, each critical activity need...
A type items are always vital under VED analysis.
The batch production requires ________ capital investment as compared...
If more variety is to be manufactured, the manufacturing facilities...
Methods for recording actual progress of work for shop orders are :-
The assignment algorithm was developed by a Hungarian mathematician...
Random fluctuation is addition of cyclical fluctuation and seasonal...
Some of significant characteristics of fixed order quantity system...
Process plan is the process of establishing the ________ and most
...
Fluctuation due to changes in season are called cyclical fluctuation.
Price orientation
In order to complete a project on time, each critical activity need...
In an organization, poor material handling system may result in the...
The earliest start time of an activity equals to earliest event time...
To operate fixed order quantity system, following parameters are...
Increase in inventory carrying cost increases EOQ.
If the annual usage of a material is 1200 units and the reorder point...
They are type of analytical estimate :-
Find EOQ in Rs from the following data :-Annual consumption = 20, 000
...
In CPM, use of dummy activities is much essential .
Earliest possible occurrence time [ I.e. stray time ] of activity [ies...
The effectiveness of sequencing model technique ________ if the...
Curve fitting method of statistical forecasting uses curve line...
Flexibility and product variety are not inter-related with each other.
The commonly used network techniques other than PERT and CPM are as...
Negative value of critical ratio :-
The commonly used network techniques other than PERT and CPM are as...
The software for CPA would require the following parameters:-
The following are salient features of the fixed order quantity system...
The 'G' group of GOLF analysis covers items procurement from...
Due to the following emergent events, the queue time has to...
In a mass production assembly shop following work measurement...
LOB has advantage that it is more ________ oriented than MRP.
The main characteristics of mass and flow production are :-
The Heuristics approach has a base of binary number theory.
In replenishment system, the fixed order quantity system is also...
The assignment method is also called as :-
While communicating to customer on delays in delivery following...
In check list approach, ________ rating indicates that existing PPC...
Total lead time is the summation of following factors :-
Classification of items on basis of their capital lock up is called...
The minimum requirements for application software for line balancing...
Move orders, released for material movement from stores to first work...
Due to the following emergent events, the queue time has to...
Labour efficiency factor is applied after capacity requirement of...
Computerisation of line balancing involve following requirements :-
Scheduling can be considered as a process of :-
Following difficulties are faced by SDE analysis :-
What factors affect the status of PPC department in the company for...
Subsidiary orders include :-
Work measurement is responsibility of :-
Overtime can be avoided in many ways and they are :-
The tooling data is prepared in respect of following measuring...
Job production requires ________ capital investment.
PERT terminology uses words like :-
On completion of work the job card is returned to production planning...
5 jobs are to be processed on machines M1 and M2 , first on M1 and...
In a mass production assembly shop following work measurement...
If actual demand far exceeds forecast, it will result into :-
Steps involved in process planning include the following :-
Important considerations in scheduling are :-
The expected time can be minimised by minimising following parameters...
HML Analysis helps to :-
Standard time accounts for :-
Detachable Card contain following information :-
The queue time is intended to compensate for the time for which the...
Material control function embraces a following techniques :-
Smoothing performs following activities:-
Process Sheet contains following information :-
Detachable Card contain following information :-