Project Cycle And Organization

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By S.m.mumtaz
S
S.m.mumtaz
Community Contributor
Quizzes Created: 5 | Total Attempts: 60,350
Questions: 10 | Attempts: 698

SettingsSettingsSettings
Organization Quizzes & Trivia

This Quiz relates to Lecture 2 on Project Cycle and Organization . If you score less than 70%, you will be required to view the presentation again and re-read the relevant content of PMBOK 4th edition. Please spend about 50 seconds on each question. The time limit is 12 minutes. Those interested in viwing this presentation and other mutimedia Audio Visio Presentation on PMP Exam Prep Course may contact at 'pmp. Smmumtaz1@gmail. Com'


Questions and Answers
  • 1. 

      The collection of generally sequential and sometimes overlapping project phases whose name and number are determined by industry and control needs is known as:

    • A.

      Project phases

    • B.

      Project Life Cycle

    • C.

      Project Management Process Group

    • D.

      Product Life Cycle

    Correct Answer
    B. Project Life Cycle
    Explanation
    A project Life Cycle is a collection of generally sequential and sometimes overlapping project phases whose name and number are determined by the management and control needs of the organizations involved in the project, the nature of the project itself, and its area of application. (PMBOK Guide 4th Edition-p 15)

    Rate this question:

  • 2. 

      All of the following is true about Project Life Cycle except:

    • A.

      Cost and Staffing requirement are constant throughout the project Life Cycle.

    • B.

      The ability to influence the final characteristics of the project’s product, without significantly impacting cost is highest at the start of the project and decreases as the project progresses towards completion.

    • C.

      The cost of changes and correcting errors typically increases substantially as the project approaches completion.

    • D.

      Stakeholder influences, risk, and uncertainty are greatest at the start of the project. These factors decrease over the life cycle of he project.

    Correct Answer
    A. Cost and Staffing requirement are constant throughout the project Life Cycle.
    Explanation
    PMBOK says:

    Cost and staffing levels are low at the start, peak as the work is carried out, and drops rapidly as the project draws to a close.

    Rate this question:

  • 3. 

    All is true about Phase end review except:

    • A.

      It is marked by completion of one or more deliverables.

    • B.

      It is marked by Go-No go to next phase.

    • C.

      Includes a Quality Audit.

    • D.

      Also called phase-exit, stage gates or kill points.

    Correct Answer
    C. Includes a Quality Audit.
    Explanation
    Quality audits – they are not defined as part of a phase end review.

    Rate this question:

  • 4. 

      All of the following is true about Project Stakeholders except:

    • A.

      They are persons or organizations who are actively involved in the project.

    • B.

      They are persons or organizations whose interests may be positively or negatively affected by the performance or completion of the project.

    • C.

      They are persons or organizations that may exert influence over the project, its deliverables, and the project team members.

    • D.

      They are persons or organizations that are actively supportive of the project.

    Correct Answer
    D. They are persons or organizations that are actively supportive of the project.
    Explanation
    D- Stakeholders are not always supportive.

    Rate this question:

  • 5. 

    You are one of five Full time Project Managers in your organizations. You all share an administrative person. There are 10-12 projects every year that involve 25% of the organizations employees, however these employees do not report to you. Your organization can be best classified as :

    • A.

      Projectized.

    • B.

      Strong Matrix

    • C.

      Functional

    • D.

      Balance Matrix

    Correct Answer
    D. Balance Matrix
    Explanation
    Based on the given information, the organization can be best classified as a Balance Matrix. This is because there are five full-time project managers, indicating a level of project management structure within the organization. However, the fact that they share an administrative person suggests a functional component as well. Additionally, the presence of 10-12 projects each year involving 25% of the organization's employees indicates a balance between project-based work and functional work. Therefore, the organization can be considered a balance matrix.

    Rate this question:

  • 6. 

      The Project Manger has the greatest level of independence and authority in a ---------------- organization:

    • A.

      Projectized.

    • B.

      Strong matrix

    • C.

      Weak matrix

    • D.

      Functional

    Correct Answer
    A. Projectized.
    Explanation
    A- projectized

    Rate this question:

  • 7. 

      A project Manager is more likely to have full time role in a ----------------organization.

    • A.

      Weak matrix

    • B.

      Projectized

    • C.

      Functional

    • D.

      Small projects

    Correct Answer
    C. Functional
    Explanation
    Small projects

    Rate this question:

  • 8. 

    A phase-end review:

    • A.

      Includes a Quality Audit

    • B.

      Must be used to initiate the subsequent phase

    • C.

      Can have an explicit goal of obtaining authorization to continue

    • D.

      Can be delayed untill project closure

    Correct Answer
    C. Can have an explicit goal of obtaining authorization to continue
    Explanation
    Phase end reviews are performed during project life cycle, so choice D is out.It is not mandatory so choice B is eliminated.A quality Audit is not defined as part of Phase end review so choice A is out.

    Rate this question:

  • 9. 

    You have begun working on a subsequent phase of your project before approval of the current phase of deliverables because you felt the risk involved were acceptable. This practice of overlapping phases is often called:

    • A.

      Crashing

    • B.

      Reverse Resource allocation

    • C.

      Fast tracking

    • D.

      Leveling

    Correct Answer
    C. Fast tracking
    Explanation
    Fast tracking is the practice of overlapping project phases in order to expedite the project schedule. In this scenario, you have started working on the next phase of the project before the approval of the current phase because you deemed the risks involved to be acceptable. This approach allows for faster completion of the project by reducing the overall timeline.

    Rate this question:

  • 10. 

    You have been hired on an expansion work of a Highway running East-West. You are Incharge of Demolition work. Your job is on contract and you are required to report to the Project Mnager but also have liason with Highway maintenace Team.You will be released after completion of Demolition phase.What type of Organizational structure you are working in.

    • A.

      Weak Matrix

    • B.

      Functional

    • C.

      Projectized

    • D.

      Ongoing work

    Correct Answer
    C. Projectized
    Explanation
    In Projectised organization, ataff are released after completion of the work and they report to the Project manager

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Aug 18, 2009
    Quiz Created by
    S.m.mumtaz

Related Topics