1.
Which of the following breaks the project scope into smaller, more manageable pieces called work packages?
Correct Answer
A. Work Breakdown Structure (WBS)
Explanation
The correct answer is Work Breakdown Structure (WBS). A Work Breakdown Structure is a hierarchical decomposition of the project scope into smaller, more manageable pieces called work packages. It helps to organize and define the scope of the project by breaking it down into smaller deliverables, tasks, and sub-tasks. The WBS provides a visual representation of the project scope, allowing for better planning, scheduling, and resource allocation. It is an essential tool in project management for ensuring that all project components are identified, understood, and properly executed.
2.
The Requirements ________ Matrix is a tracking mechanism used to link requirements to their origin and trace them throughout the project life cycle.
Correct Answer
Traceability
Explanation
The Requirements Traceability Matrix is a tracking mechanism used to link requirements to their origin and trace them throughout the project life cycle. It helps in ensuring that all requirements are met and that any changes or updates to requirements can be easily traced back to their source. By maintaining traceability, project teams can effectively manage and track the progress of requirements, identify any gaps or inconsistencies, and ensure that all project deliverables align with the initial requirements.
3.
Which of the following is NOT done during the Planning phase?
Correct Answer
A. Verify Scope
Explanation
During the Planning phase, various activities are carried out to ensure a successful project. These activities include defining the scope of the project, creating a Work Breakdown Structure (WBS), and collecting requirements. However, the verification of the scope is not typically done during the Planning phase. Scope verification is usually performed during the Monitoring and Controlling phase to ensure that all the project deliverables meet the defined scope.
4.
Define Scope is the process of developing a detailed description of the project and product. True or false?
Correct Answer
A. True
Explanation
The statement is true because the Define Scope process involves creating a comprehensive and detailed description of both the project and the product. This includes defining the project's objectives, deliverables, requirements, constraints, and assumptions. It helps to establish a clear understanding of what needs to be accomplished and what is included within the project's boundaries. By developing a thorough scope definition, project stakeholders can effectively plan, execute, and control the project, ensuring that it stays on track and meets its intended goals and outcomes.
5.
________ is defined as compliance with the regulations, requirements, or specifications of a project.
Correct Answer
Validation
Explanation
Validation is the process of ensuring compliance with the regulations, requirements, or specifications of a project. It involves verifying that the project meets all the necessary criteria and standards set forth. This can include checking for accuracy, completeness, and adherence to guidelines. Validation is crucial to ensure that the project is on track and meets the desired objectives, ultimately leading to a successful outcome.
6.
Formal acceptance occurs at the ________ of a project or phase.
Correct Answer
end
Explanation
Formal acceptance occurs at the end of a project or phase. This means that the project or phase has been completed and all deliverables have been reviewed and approved. At this stage, stakeholders evaluate the final results and determine if they meet the predetermined objectives and requirements. Formal acceptance signifies the official sign-off and closure of the project or phase, allowing for the transition to the next stage or project.
7.
Which comes last in Project Scope Management?
Correct Answer
D. Control Scope
Explanation
Control Scope comes last in Project Scope Management because it involves monitoring and controlling changes to the project scope. Once the project scope has been defined, validated, and the scope management plan has been established, the next step is to control any changes that may occur during the project. This includes reviewing and approving or rejecting scope change requests, updating the project scope statement, and ensuring that the project remains within its defined scope. Control Scope is the final step in managing the project scope and ensuring that the project stays on track.
8.
True or False: "Decomposition is completion measured against the requirements"
Correct Answer
B. False
Explanation
Decomposition is not completion measured against the requirements. Decomposition is the process of breaking down a complex problem or system into smaller, more manageable parts. It involves dividing a problem into subproblems or breaking a system into smaller components. Completion measured against the requirements refers to the extent to which a solution meets the specified requirements. These two concepts are not the same, so the correct answer is False.