1.
Precautions for cold weather concrete should be followed when the mean daily temperature falls to ______degrees Fahrenheit.
Correct Answer
B. 40
Explanation
ICC Concrete Manual pg 254
2.
A Swiss Hammer operates on the principle that the rebound of a spring-loaded steel plunger striking the surface of concrete is proportional to the ______ of that concrete.
Correct Answer
C. Strength
Explanation
ICC Concrete Manual section 3.9
3.
A Swiss Hammer is a quick _______ test that can be used for determination of the approximate _______ strength of concrete in place, but it cannot be used to replace properly conducted cylinder or core tests.
Correct Answer
A. Nondestructive, compressive
Explanation
ICC Concrete Manual section 3.9
4.
Which of the following is not important for hot weather concrete precautions?
Correct Answer
D. Break truck arrival time
Explanation
ICC Concrete Manual Table 19.1
5.
The approximate percent of 28 day compressive strength loss between concrete that is cured at 73 and 42 degrees F is:
Correct Answer
B. 25
Explanation
ICC Concrete Manual Figure 19-5
6.
For concrete with Type III cement the time period for curing is ____ than for concrete with Type I cement.
Correct Answer
A. Shorter
Explanation
ICC Concrete Manual section 17.7
7.
After the contractor has been notified of discrepancies and they are not corrected, the discrepancies shall be brought to the attention of the _______ and to the registered design professional in responsible charge prior to the completion of that phase of work.
Correct Answer
B. Building official
Explanation
IBC Ch 17, 1704.1.2
8.
________ verification and inspection is required for shape of formwork, location and dimensions of the concrete member being formed.
Correct Answer
B. Periodic
Explanation
IBC Ch 17, Table 1704.4
9.
Special inspections shall not be required for isolated spread footings of buildings ____ stories or less in height that are fully supported on earth or rock.
Correct Answer
A. 3
Explanation
IBC Ch 17, 1704.4 exception 1
10.
If a concrete foundation wall is constructed in accordance with table 1805.5(5), special inspection is not required.
Correct Answer
A. True
Explanation
IBC Ch 17, 1704.4 exception 4
11.
Special inspectors shall inspect all work according to the Statement of Special Inspections for which they are responsible for conformance with the _______ approved (stamped) plans and specifications and applicable provisions of IBC Section 1704.
Correct Answer
B. Building department
Explanation
Model Program page 5
12.
Refer to the Model Program for special inspection. All of the following are duties and responsibilities of the special inspector except:
Correct Answer
A. Instruct workers on how to do their job
Explanation
Model Program page 5
13.
In reference to seismic design: A hook on a stirrup, hoop, or crosstie having a bend not less than 135 degrees, except that ______ hoops shall have a bend not less than 90 degrees.
Correct Answer
D. Circular
Explanation
ACI 318 page 306 21.1 definitions
14.
In reference to seismic designed hooks shall have a six-diameter (but not less than ____ inches) extension that engages the longitudinal reinforcement and projects into the interior of the stirrup or hoop.
Correct Answer
B. 3
Explanation
ACI 318 page 306 21.1 definitions
15.
In reference to seismic designed hoops being provided for frame members, the first hoop shall be located not more than ____ in. form the face of a supporting member.
Correct Answer
C. 2
Explanation
ACI 318 21.3.3.2
16.
The top mark on an ASTM standard reinforcing bar indicates _______.
Correct Answer
B. Producing mill
Explanation
ICC Concrete Manual pg 227
17.
A separation between adjoining parts of a concrete structure, usually a vertical plane at a designed location to allow relative movement in three directions and avoid formation of cracks elsewhere in the concrete and through which all or part of the bonded reinforcement is interrupted is a ________ joint.
Correct Answer
C. Isolation
Explanation
ACI 318 page 31
18.
Concrete that has been retempered can only be used when approved by the _______.
Correct Answer
D. Engineer
Explanation
ACI 318 page 70, 5.10.4
19.
Which type of steel can be identified with two grade lines?
Correct Answer
A. Grade 75
Explanation
ICC Concrete Manual pg 227
20.
Construction joints in floor slabs should be ________.
Correct Answer
C. Within the middle third of the slab span
Explanation
ACI 318 page 77, 6.4.4
21.
The tolerance for d for an eight inch continuous footing section is ______.
Correct Answer
C. +/- 3/8 inch
Explanation
ACI 318 page 81, 7.5.2.1
22.
A conduit line embedded in exterior concrete must have a minimum cover of ______.
Correct Answer
B. 1 ½ inch
Explanation
ACI 318 page 76, 6.3.10
23.
_____ is the minimum bend diameter for an ASTM standard #7 reinforcing bar.
Correct Answer
C. 6 db
Explanation
ACI 318 page 80, table 2
24.
There are six longitudinal #4 bars in the bottom mat of a grade beam. What is the required minimum clear spacing between these bars?
Correct Answer
B. 1 inch
Explanation
ACI 318 page 82, 7.6.1
25.
A pipe that is embedded in an interior concrete slab can not be larger than _____ in diameter and must be spaced a minimum of _____ apart.
Correct Answer
D. 2 inches, 3 diameters on center
Explanation
ACI 318 page 76, 6.3.6.3