1.
What year was Microsoft project released?
Correct Answer
A. 1984
Explanation
Microsoft Project was released in 1984.
2.
Is it included among the office suite?
Correct Answer
B. No
Explanation
The given answer "No" suggests that the item in question is not included among the office suite.
3.
How can you recognise the timeframe of a new project?
Correct Answer
D. Choosing the project information in the properties group in the project tab
Explanation
To recognize the timeframe of a new project, one should choose the project information in the properties group in the project tab. This implies that there is a specific feature or option available in the properties group that allows users to input or select the timeframe for the project. This suggests that the timeframe can be identified and set within the project properties, indicating that it is possible to recognize the timeframe of a new project.
4.
What is the default view of a new project?
Correct Answer
A. Gantt view
Explanation
The default view of a new project is the Gantt view. This view displays the project tasks and their corresponding timelines in the form of a Gantt chart. It allows users to visualize the project schedule, dependencies, and progress easily. The Gantt view is commonly used in project management to track and manage tasks efficiently.
5.
Which one do you like?
Correct Answer
C. Assigning a duration of zero days to the milestone task
Explanation
Assigning a duration of zero days to the milestone task is the correct answer because a milestone task is a significant event or achievement in a project that marks progress. It does not require any specific duration as it represents a point in time rather than a task that requires time to complete. Therefore, assigning a duration of zero days accurately represents the nature of a milestone task.
6.
Project lets you customize the calender for?
Correct Answer
D. All of the above
Explanation
The project calendar can be customized to cater to the needs of the people working on the project. It can be adjusted to reflect the project duration accurately, ensuring that all the important milestones and deadlines are included. Additionally, the calendar can be used to schedule and track the tasks that are part of the project, allowing for better organization and coordination. Therefore, all of the given options are valid reasons for customizing the project calendar.
7.
When you create a task, you can apply a subtask or set subtasks?
Correct Answer
B. To any task entered in the task list entry table for the
Explanation
You can apply a subtask or set subtasks to any task entered in the task list entry table. This means that when creating a task, you have the option to break it down into smaller subtasks or assign subtasks to existing tasks in the list. This flexibility allows for better organization and management of tasks, ensuring that each task can be further divided and tracked if necessary.
8.
Can all tasks be set as recurring?
Correct Answer
A. Yes
Explanation
All tasks can be set as recurring because the option to set a task as recurring is available in most task management systems. This allows users to automatically repeat tasks at specified intervals, such as daily, weekly, monthly, or annually. Recurring tasks are useful for activities that need to be performed regularly, such as paying bills, attending meetings, or completing routine chores. By setting tasks as recurring, users can save time and effort by avoiding the need to manually create the same task repeatedly.
9.
What year was the Macintosh version released?
Correct Answer
B. 1991
Explanation
The correct answer is 1991. This is the year when the Macintosh version was released.
10.
What is the latest version of the Microsoft project?
Correct Answer
C. Project 2016
Explanation
The latest version of Microsoft Project is Project 2016.