1.
You will use testable requirements during solution verification to determine if the solution receives a score of pass or fail. What type of criteria are you developing?
Correct Answer
B. Acceptance
Explanation
Acceptance criteria describe the minimal set of requirements that must be met in order for a particular solution to be worth implementing.
2.
Which input best provides you with an assessment of a solution’s ability to meet the business need at an acceptable level of quality?
Correct Answer
C. Solution validation assessment
Explanation
The solution validation assessment provides an assessment of the solution’s ability to meet the business need at an acceptable level of quality.
3.
What technique ensures that issues arising from an organizational readiness assessment are addressed and resolved?
Correct Answer
C. Problem-tracking
Explanation
The problem-tracking technique is used to ensure that issues identified by the organizational readiness assessment are resolved.
4.
Which statement is FALSE regarding your project’s transition requirements?
Correct Answer
C. Relevant after the existing solution is eliminated
Explanation
Transition requirements are not relevant after the new solution is implemented and should be discarded. All of the remaining statements are true.
5.
You are determining the most appropriate response to identified defects in a delivered solution. What activity are you performing?
Correct Answer
A. Validating the solution
Explanation
Solution validation ensures that a delivered solution meets the business needs on an ongoing basis and that any identified defects are reported and prioritized for resolution.
6.
What outputs are produced from ensuring that a delivered solution meets the business needs on an ongoing basis?
Correct Answer
A. Identified defects and mitigating actions
Explanation
Outputs from the validate solution task include identified defects, mitigating actions, and the solution validation assessment.
7.
You used prioritized solution requirements to assess several solution options. In order to make a decision, these prioritized requirements must also be:
Correct Answer
B. Approved
Explanation
Requirements must be prioritized and approved in order to allow a decision to be made about possible solution options during solution assessment.
8.
Which stakeholder approves the allocation of requirements to components and releases?
Correct Answer
B. Project sponsor
Explanation
The project sponsor is responsible for funding the project and required to approve the allocation of requirements to components and releases based on the recommendations of the business analyst and the project team.
9.
Requirements that are associated with the solution component that will implement them are called:
Correct Answer
D. Allocated requirements
Explanation
Allocated requirements are associated with a solution component that will implement them.
10.
You are making decisions about what solution requirements to include in your project iterations in order to cause minimal disruption of business activities during solution implementation. What activity are you performing?
Correct Answer
A. Release planning
Explanation
You are performing release planning, part of allocating your requirements. Release planning involves making decisions about which requirements are included in each phase or iteration of the project.
11.
What is another name for the existing solution?
Correct Answer
B. Deployed solution
Explanation
The deployed solution is the existing solution that will be replaced by a new solution.
12.
When should you begin to allocate requirements during a project?
Correct Answer
C. When the solution approach is determined
Explanation
Requirements allocation typically begins early in the project life cycle (as soon as the solution approach can be determined) and continues to be performed until all valid requirements are allocated, typically through design and construction of the solution.
13.
When should transition requirements be defined?
Correct Answer
B. After the solution has been designed
Explanation
Transition requirements are defined after the solution has been designed.
14.
What general technique would you select to discover if a solution defect is a symptom of a deeper, underlying problem?
Correct Answer
A. Root cause analysis
Explanation
During solution validation, the root cause analysis technique can be used to ensure that the underlying reason for a defect is identified, rather than simply correcting the output which may be a symptom of a deeper underlying problem.
15.
You are investigating how a solution is being used after it has been deployed. What Solution Assessment and Validation task are you performing?
Correct Answer
D. Evaluating solution performance
Explanation
Evaluating solution performance is where you investigate how a solution is actually used after it is deployed and assess its positive and negative effects.
16.
Solution validation can only be performed against a solution that is ________________.
Correct Answer
C. Constructed
Explanation
Solution validation can only be performed against a solution that exists. Although the solution may or may not be in actual use by the enterprise, it must be constructed.
17.
What type of requirements should address employee training, conversion of existing information, and user acceptance testing?
Correct Answer
B. Transition
Explanation
Transition requirements define capabilities needed to support the transition from the old system to the new solution, including employee training, conversion of existing information, and user acceptance testing.
18.
What source might assist you in defining transition requirements?
Correct Answer
A. Ongoing work using the old solution
Explanation
Sources of transition requirements include the actual data and metadata managed by the old system, the ongoing work in the old version of the solution, and the process for managing the organizational change resulting from the transition to the new system.
19.
Which task has solution performance metrics as an input?
Correct Answer
B. Evaluate Solution Performance
Explanation
Inputs for the Evaluate Solution Performance task include the solution performance metrics, the deployed solution, any identified defects, and the business requirements.
20.
What is the best reason for involving a business analyst in the Solution Assessment and Validation tasks?
Correct Answer
C. They are most knowledgeable about the business environment.
Explanation
The business analyst knows the business environment and can assess how each proposed solution would affect the environment. Business analysts are also responsible for ensuring that the stakeholders fully understand the solution requirements and that implementation decisions align with those requirements.