Attempt all 200 questions in 4 hours.
Performing activities in accordance with the project management plan.
Managing changes to the deliverables.
Completing the work in accordance with the defined quality framework and specification.
Coordinating people and resources.
Rate this question:
AC + (BAC – EV)
(BAC - EV)/(BAC - AC)
BAC/CPIcum
(BAC - EV)/(EAC - AC)
Rate this question:
The 80% of the work that is important.
The qualitative improvement trend demonstrated by implementing a Six Sigma initiative.
A histogram ordered by frequency of occurrence.
The 20% of the work that is causing the most issues.
Rate this question:
Project plan updates.
Expert judgement.
Change control meetings.
A change control board to approve or reject changes.
Rate this question:
Decision tree analysis is more effective using net present values (NPV) in its calculations rather than EMV.
The EMV of an opportunity is generally a positive value.
EMV is a statistical concept that calculates the average value of a future scenario that may, or may not happen by multiplying the value of each possible outcome by the probability of it occurring and summing the products.
The EMV of a threat is generally a negative value.
Rate this question:
Ensure effective control over the work of the project team.
Develop the project team.
Define the organisation structure.
Acquire the project team.
Rate this question:
Balanced matrix.
Strong matrix.
Functional.
Weak matrix.
Rate this question:
The focusing of the efforts of a group of people on achieving a common objective.
High levels of respect and trust.
The ability to get things done through others.
A primary focus on external senior managers and other key stakeholders to ensure the project is a success through managing upwards.
Rate this question:
Collect Requirements, Plan Communications, Distribute Information, Manage Expectations and Report Performance.
Identify Stakeholders, Collect Requirements, Plan Communications, Distribute Information, Manage Stakeholder Expectations and Report Performance.
Identify Stakeholders, Plan Communications, Distribute Information, Manage Stakeholder Expectations and Report Performance.
Collect Requirements, Plan Communications, Distribute Information, Update Project Documentation and Report Performance.
Rate this question:
The PMI WBS and PRINCE2 product breakdown structure (PBS) are effectively the same thing.
The WBS is the same as the organisational breakdown structure (OBS).
The WBS is a deliverable oriented, hierarchical decomposition of the work to be executed by the project team.
The WBS is the bill of materials (BoM) needed to accomplish the work of the project.
Rate this question:
The seller is reimbursed for all allowable costs incurred performing the contract work.
The seller receives a fixed fee calculated as a percentage of the initial estimated project cost.
The fee does not change based on the performance of the seller.
The seller receives a fee calculated as a fixed percentage of the actual project cost.
Rate this question:
Tell the stakeholders the work cannot be added.
Evaluate the cost and time impacts of adding the work.
Add the work if it can be accommodated within the existing budget.
Talk to the sponsor and let her know of the request.
Rate this question:
Based on expert judgement and is consequently more accurate than standard critical path estimating.
Used when there is a limited amount of detailed information available.
A calculation based on a three point estimate using a modified BETA distribution.
The same as ‘bottom up’ estimating.
Rate this question:
Is the system used to keep track of purchases and contracts.
Is any numbering system used to uniquely identify each component of the work breakdown structure.
Links the work breakdown structure to the schedule task identifier.
Is the alpha-numeric reference used in the organisations accounts system to identify cost centres.
Rate this question:
The changes in market conditions between the contract date and the current time.
Any successes or failures in the process that warrant recognition.
The complete procurement process from initial planning through to the administration of the procurement.
Any lessons learned that can be applied to future procurement processes.
Rate this question:
It is a technique to reduce bias and prevent any one person from exerting undue influence.
It is a way to reach a consensus of experts.
It is an Oracle® database application used to optimise future outcomes.
Individual experts are unaware of who else is participating in the process.
Rate this question:
The formal contract documents are signed by your senior management.
When your legal department advises the contract is acceptable.
The formal contract documents are signed by official representatives of both parties.
There is an offer, acceptance, performance and consideration.
Rate this question:
Coin flip (random).
Command.
Consultation.
Rational choice theory
Rate this question:
Fixed Price Incentive Fee
Firm Price Incentive Free
Fixed Price Indicator Factor
Fast Performance Incentive Fee
Rate this question:
Informing appropriate stakeholders of all approved changes and associated costs.
Influencing factors that create changes in the authorised cost baseline.
Developing the cost performance baseline.
Acting to bring expected cost overruns within acceptable limits.
Rate this question:
Generally a product lifecycle is contained within a project lifecycle.
A project life cycle is determined by the organisation and generally consists of phases that may be sequential or overlapping.
A product lifecycle is determined by the organisation and generally consists of sequential phases.
Generally a project lifecycle is contained within a product lifecycle.
Rate this question:
Making sure the information is clear and complete, understood and acknowledged.
Making sure the information is received in its entirety, understood correctly and acknowledged.
Making sure the information is clear and complete, understood and agreed with.
Listening actively to ensure all of the information is received.
Rate this question:
Maslow.
McGregor.
Hertzberg.
Deming.
Rate this question:
Its primary use is to authorise the start of a project or phase.
It provides the project manager with authority to apply resources and expend money on project activities.
Its primary use is to request bids or proposals for the work it defines.
The project charter can be created by the person external to the project, responsible for the authorisation of the work, or that person can delegate the creation of the project charter to the project manager.
Rate this question:
EEF do not include the organisations purchasing guidelines because this type of function is managed by the Accounts Department.
EEF include the tools, systems and software that comprise the project management information system (PMIS).
EEF incorporates the organisation’s culture, structure and processes.
EEF include all relevant laws, regulations and standards imposed by all levels of government, industry bodies and society.
Rate this question:
It is an output of the Verify Scope process.
It describes the project’s deliverables and the work needed to create them.
It may contain explicit scope exclusions that can assist in managing stakeholder expectations.
It provides a common understanding of the project’s scope among the project’s stakeholders.
Rate this question:
Buying professional indemnity insurance.
The cost of defects and rework caused by failing to achieve requirements.
The cost of inspecting and appraising conforming products produced by the project.
Preventing non-conformance to requirements.
Rate this question:
The connections between activities and project team members.
The delegation of responsibility through the hierarchically organised management structure.
Accountabilities to assist in team performance appraisals.
The sequence of activities a named resource is responsible for accomplishing.
Rate this question:
All of the process groups are needed on all projects and all of their interactions apply to each phase of a project as well as the overall project.
The process groups are seldom one time, discrete events; they are overlapping activities that occur throughout the project.
Where a project is divided into phases, the process groups are invoked as appropriate.
The process groups are linked by the outputs they produce.
Rate this question:
Not starting design until all of the approvals have been received.
Waiting the specified 72 hours before stripping formwork from a newly poured concrete slab.
Applying a start-to-start link between two tasks in a PDM network.
Applying a lag of 4 days between two tasks.
Rate this question:
An Organizational Breakdown Structure (OBS)
A Department Breakdown Structure (DBS)
A Resource Breakdown Structure (RBS)
A Hierarchical Breakdown Structure (HBS)
Rate this question:
Cost-Plus-Fixed-Fee contract
A Time and material contract
Lump sum contract
Cost-Plus-Fee contract
Rate this question:
Mandatory dependency
Discretionary dependency
Soft logic
External dependency
Rate this question:
Sequence Activities phase
Define Scope phase
Estimate Activity Durations
Define Activities phase
Rate this question:
Ask the project team member to go ahead with the changes.
The changes are documented and they follow the change management process to become an Approved Change request.
Summarize the changes and archive your discussion with the team member as a future record.
Ask the team member to ignore the changes.
Rate this question:
Report the accurate status to your manager and send a separate report stating that each team member was busy for 40 hours
Report this accurately on the status report and ensure that activities are re-planned as necessary, to keep the team completely occupied.
Report on the status report that each team member was busy for 40 hours, and use the time saved for other activities not related to the project.
Avoid mentioning these kinds of savings on status reports.
Rate this question:
Contingent Response Strategy
Active acceptance
Passive acceptance
Avoidance
Rate this question:
Disbursement reconciliation
Expenditure Reconciliation
Budget Reconciliation
Funding Limit Reconciliation
Rate this question:
Forecast future performance based on past performance
Calculate the number of days left in the project
Calculate the value provided to the customer
Calculate the profitability of the project
Rate this question:
Talk to the customer about the impact of the change
Change the risk management plan
Include the expected monetary value of the risk in the new cost estimate
Analyze the impacts of the change with the team
Rate this question:
List of schedule milestones
Resource assigned
Contract Information
Code of Account Identifier
Rate this question:
Performance Report
Record Management System
Deliverables Checklist
Inspections and Audits
Rate this question:
Monitoring and controlling
Planning
Executing
Initiating
Rate this question:
Soft logic
Unilateral dependency
Fixed logic
Hard logic
Rate this question:
Time and Material contract
Cost-Plus-Fixed-Fee contract
Cost-Plus-Incentive-Fee contract
Fixed-price contract
Rate this question:
Foreign cause
Assignable cause
Atypical cause
Normal cause
Rate this question:
Many of the work packages have been completed and he wants to change the dates on subsequent ones.
His manager has requested him to change the milestone dates.
To allow time for a project status presentation.
To regulate expenditure of funds so that they can be reconciled against the disbursement of funds for the project.
Rate this question:
Inspection is work done by the Quality Control (QC) team whereas Prevention is work done by the Quality Assurance (QA) team
Inspection refers to keeping errors out of the process whereas prevention refers to keeping errors out of the hands of the customer.
Prevention refers to keeping errors out of the process whereas inspection refers to keeping errors out of the hands of the customer.
Inspection and Prevention refer to the same activity depending on what stage of the project the activity is done.
Rate this question:
The cost of correcting mistakes through an inspection is much lesser than the cost of preventing them.
The cost of preventing mistakes is generally much lesser than the cost of correcting them as revealed by inspection.
It does not matter where a defect is captured as long as the finished work product does not have a defect.
The cost of correcting mistakes through an inspection is more or less that same as the cost of preventing them since the same effort goes into both activities.
Rate this question:
Iterative planning
Balanced planning
Deferred planning
Rolling wave planning
Rate this question:
Quiz Review Timeline +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.