Project Integration Management

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Babjam
B
Babjam
Community Contributor
Quizzes Created: 14 | Total Attempts: 31,377
Questions: 20 | Attempts: 1,128

SettingsSettingsSettings
Project Integration Management - Quiz


Questions and Answers
  • 1. 

    A project charter does not authorize the project manager to use organizational resources to complete the project.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    A project charter is a document that formally authorizes the existence of a project and provides the project manager with the authority to allocate organizational resources to complete the project. Therefore, the statement that a project charter does not authorize the project manager to use organizational resources to complete the project is false.

    Rate this question:

  • 2. 

    A commonsense approach to improving the coordination between project plan development and execution is to follow this simple rule: Those who will do the work should not plan the work

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The statement suggests that those who will do the work should not be involved in planning the work, which is incorrect. In reality, involving the individuals who will be responsible for executing the project in the planning process can greatly improve coordination. This allows for better understanding of the requirements, potential challenges, and feasibility of the plan, leading to more effective execution. Therefore, the correct answer is False.

    Rate this question:

  • 3. 

    Project integration management does not include interface management.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Project integration management includes interface management. Interface management involves coordinating and integrating the activities of different stakeholders and systems to ensure smooth communication and collaboration throughout the project. It focuses on identifying, defining, and managing the interfaces between different components, processes, and organizations involved in the project. This helps to minimize conflicts, ensure compatibility, and promote effective integration of project elements. Therefore, the statement that project integration management does not include interface management is false.

    Rate this question:

  • 4. 

    The number of interfaces can increase exponentially as the number of people involved in a project increases.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    As the number of people involved in a project increases, the number of interfaces between them can also increase exponentially. This is because each person may need to communicate and interact with multiple other individuals, leading to a larger number of potential interfaces. This can result in more complexity and coordination challenges within the project. Therefore, the statement is true.

    Rate this question:

  • 5. 

    A(n) ____ is a document used to coordinate all project planning documents and help guide a project's execution and control.

    • A.

      Project management plan

    • B.

      Statement of work

    • C.

      Scope statement

    • D.

      Contact

    Correct Answer
    A. Project management plan
    Explanation
    A project management plan is a document that brings together all the project planning documents and serves as a guide for the execution and control of the project. It outlines the objectives, scope, deliverables, schedule, budget, resources, and risks associated with the project. It provides a comprehensive overview of how the project will be managed and ensures that all stakeholders are aligned and aware of the project's goals and requirements. The project management plan helps in coordinating and controlling the project activities, ensuring that they are executed according to the defined plan.

    Rate this question:

  • 6. 

    A(n) ____ is a document that describes the products or services to be created by the project team.

    • A.

      Contract

    • B.

      Statement of work

    • C.

      Project charter

    • D.

      Business case

    Correct Answer
    B. Statement of work
    Explanation
    A statement of work is a document that outlines the products or services that will be produced by the project team. It provides detailed information about the scope of the project, including deliverables, timelines, resources, and any specific requirements or expectations. This document serves as a formal agreement between the project team and the stakeholders, ensuring that everyone has a clear understanding of what will be delivered and what is expected from the project.

    Rate this question:

  • 7. 

    Project integration management must occur within the context of a particular project.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Project integration management does not occur within the context of a particular project. Instead, it is a knowledge area that encompasses the processes and activities required to coordinate and integrate all the various elements of a project. It involves ensuring that all project components work together effectively and that the project as a whole is aligned with the organization's objectives. Therefore, the correct answer is False.

    Rate this question:

  • 8. 

    ____ should result in improvements in project performance.

    • A.

      Corrective actions

    • B.

      Adjustments

    • C.

      Preventive actions

    • D.

      Proactive methods

    Correct Answer
    D. Proactive methods
    Explanation
    Proactive methods should result in improvements in project performance. Proactive methods involve taking preemptive actions to identify and address potential issues before they occur. By being proactive, project managers can anticipate challenges, mitigate risks, and implement strategies to enhance project outcomes. This approach helps to minimize disruptions, delays, and cost overruns, ultimately leading to improved project performance.

    Rate this question:

  • 9. 

    Directing and managing project execution involves overseeing project work to meet the performance objectives of the project.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Directing and managing project execution involves overseeing project work to meet the performance objectives of the project. This statement is true because the project manager is responsible for ensuring that the project is executed according to the plan and that the work is being done efficiently and effectively. They must monitor the progress of the project, make adjustments as necessary, and ensure that the project team is working together towards the desired outcomes.

    Rate this question:

  • 10. 

    _______ involves working with stakeholders to create the document that formally authorizes a project.

    • A.

      Developing the project charter

    • B.

      Developing the preliminary project scope statement

    • C.

      Developing the project management plan

    • D.

      Directing and managing project execution

    Correct Answer
    A. Developing the project charter
    Explanation
    Developing the project charter involves working with stakeholders to create the document that formally authorizes a project. This document outlines the project's objectives, scope, deliverables, and stakeholders. It also establishes the project manager's authority and provides the necessary resources and support for the project. The project charter is a crucial step in initiating a project as it ensures that all stakeholders are aligned and have a clear understanding of the project's purpose and goals.

    Rate this question:

  • 11. 

    Many people consider project integration management the key to overall project success.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Project integration management involves coordinating all aspects of a project to ensure that it is completed successfully. It includes activities such as developing a project charter, creating a project management plan, and monitoring and controlling project work. By effectively integrating all project components, project integration management helps to ensure that the project is aligned with its objectives and that all project activities are coordinated and executed smoothly. Therefore, it can be considered as the key to overall project success.

    Rate this question:

  • 12. 

    Some people might use a contract in place of a charter.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    This statement is true because some people may choose to use a contract instead of a charter. A contract is a legally binding agreement between two or more parties that outlines the terms and conditions of their relationship. Similarly, a charter is a document that establishes the rights, privileges, and responsibilities of an organization or group. While a charter is typically used for more formal and long-term arrangements, some people may opt to use a contract instead, depending on their specific needs and preferences.

    Rate this question:

  • 13. 

    A(n) ____ is a formal, documented process that describes when and how official project documents may be changed.

    • A.

      Integrated change control

    • B.

      Change request

    • C.

      Performance report

    • D.

      Change control system

    Correct Answer
    D. Change control system
    Explanation
    A change control system is a formal, documented process that describes when and how official project documents may be changed. It provides guidelines and procedures for requesting, reviewing, approving, and implementing changes to project documents. This system ensures that changes are properly evaluated, authorized, and managed to minimize risks and maintain project integrity. It helps maintain control over project scope, schedule, budget, and quality by ensuring that changes are carefully considered and implemented in a controlled and systematic manner.

    Rate this question:

  • 14. 

    As projects progress, the organization must reevaluate the need, funding, and will for each project to determine if the project should be continued, redefined, or terminated.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The statement is true because as projects progress, the organization needs to constantly assess the need, funding, and willingness to continue with each project. This evaluation is necessary to ensure that resources are allocated effectively and that projects align with the organization's goals and priorities. By regularly reevaluating projects, the organization can make informed decisions about whether to continue, redefine, or terminate them based on their current status and relevance.

    Rate this question:

  • 15. 

    Which of the following is an input to the integrated change control process?

    • A.

      Approved corrective and preventive actions

    • B.

      Work performance information

    • C.

      Approved and rejected change requests

    • D.

      Approved and validated defect repair

    Correct Answer
    B. Work performance information
    Explanation
    Work performance information is an input to the integrated change control process because it provides data on how the project is progressing and the current status of the work being performed. This information is crucial for evaluating the impact of any proposed changes and determining if they should be approved or rejected. By analyzing the work performance information, project managers can assess the potential effects of changes on the project's objectives, schedule, and budget, and make informed decisions about whether to incorporate them into the project or not.

    Rate this question:

  • 16. 

    The outputs of which process include approved and rejected change requests, approved corrective and preventive actions, approved and validated defect repair, deliverables, and updates to the project management plan and project scope statement?

    • A.

      Monitor and control the project work

    • B.

      Close the project

    • C.

      Develop the project management plan

    • D.

      Perform integrated change control

    Correct Answer
    D. Perform integrated change control
    Explanation
    Perform integrated change control is the correct answer because this process is responsible for reviewing all change requests, making decisions on whether to approve or reject them, and implementing approved changes. The outputs of this process include approved and rejected change requests, approved corrective and preventive actions, approved and validated defect repair, deliverables, and updates to the project management plan and project scope statement. This process ensures that changes are properly evaluated and implemented in a controlled manner to minimize risks and ensure project success.

    Rate this question:

  • 17. 

    Which section of the project plan should describe the major project functions and activities and identify those individuals who are responsible for them?

    • A.

      Organizational charts

    • B.

      Other organizational or process-related information

    • C.

      Project responsibilities

    • D.

      Management objectives

    Correct Answer
    C. Project responsibilities
    Explanation
    The section of the project plan that should describe the major project functions and activities and identify those individuals who are responsible for them is the "Project responsibilities" section. This section outlines the specific roles and responsibilities of each team member involved in the project, ensuring that everyone understands their tasks and accountabilities. It helps to establish a clear structure and ensures that the project functions and activities are properly assigned and executed by the responsible individuals.

    Rate this question:

  • 18. 

    The key deliverables section of the project management plan should describe the quality expectations for the product deliverables.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The key deliverables section of the project management plan is responsible for outlining the quality expectations for the product deliverables. This section ensures that the project team and stakeholders have a clear understanding of the expected level of quality for the final product. By including this information in the project management plan, it helps to establish a common understanding and sets the standard for the project's success. Therefore, the statement is true.

    Rate this question:

  • 19. 

    Which section of the project management plan describes specific methodologies a project might use and explains how to document information?

    • A.

      Management objectives

    • B.

      Project controls

    • C.

      Risk management

    • D.

      Technical processes

    Correct Answer
    D. Technical processes
    Explanation
    The section of the project management plan that describes specific methodologies a project might use and explains how to document information is the Technical processes section. This section outlines the specific techniques and tools that will be employed during the project, as well as how information will be recorded, stored, and communicated. It provides guidance on how to document project activities, processes, and deliverables, ensuring that information is properly documented and accessible to all stakeholders.

    Rate this question:

  • 20. 

    Project sponsors are usually most interested in ____.

    • A.

      Administrative closure procedures

    • B.

      Contract closure procedures

    • C.

      Final products, services, or results

    • D.

      Organizational process asset updates

    Correct Answer
    C. Final products, services, or results
    Explanation
    Project sponsors are usually most interested in the final products, services, or results of a project because these are the tangible outcomes that directly impact the organization's goals and objectives. The final products, services, or results are what the project sponsor has invested in and expects to receive as a return on their investment. They are interested in ensuring that these outcomes meet the desired quality standards and fulfill the project's objectives. The administrative closure procedures, contract closure procedures, and organizational process asset updates are important aspects of project management, but they are not the primary focus for project sponsors.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Sep 03, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Dec 07, 2010
    Quiz Created by
    Babjam
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.