1.
The kick-off meeting for a project cannot be held before the business case and project charter are completed.
Correct Answer
A. True
Explanation
The kick-off meeting for a project cannot be held before the business case and project charter are completed because these documents provide important information about the project's objectives, scope, and deliverables. Without a completed business case and project charter, the team may not have a clear understanding of the project's goals and requirements, which can lead to confusion and inefficiency during the kick-off meeting. Therefore, it is essential to have these documents finalized before conducting the kick-off meeting.
2.
Substantial effort should go into initiating projects.
Correct Answer
A. True
Explanation
Initiating projects requires a significant amount of effort because it involves planning, organizing, and setting goals for the project. It also involves identifying the resources needed, creating a timeline, and obtaining the necessary approvals and support. Without putting in substantial effort at the beginning, the project may not be properly planned or executed, leading to potential issues and failure. Therefore, it is important to dedicate sufficient time and resources to initiate projects effectively.
3.
A stakeholder analysis should not be part of the official project plans, which are normally available for all stakeholders to review.
Correct Answer
B. False
Explanation
A stakeholder analysis should be part of the official project plans, which are normally available for all stakeholders to review. This analysis helps identify and prioritize the stakeholders who will be affected by the project and their level of influence or interest. By including this analysis in the project plans, it ensures that the project team is aware of the stakeholders and can effectively engage and communicate with them throughout the project lifecycle.
4.
The contents of a business case remain constant, despite the varying needs of individual projects.
Correct Answer
B. False
Explanation
The explanation for the answer "False" is that the contents of a business case can vary depending on the needs of individual projects. Each project may have different objectives, risks, costs, and benefits, which would require a tailored approach in developing the business case. Therefore, the contents of a business case are not constant but rather flexible and adaptable to specific project requirements.
5.
Management needs to create and distribute documentation to authorize project initiation.
Correct Answer
A. True
Explanation
The statement is true because in order to initiate a project, management needs to create and distribute documentation that authorizes the project. This documentation typically includes a project charter or a similar document that outlines the project's objectives, scope, deliverables, and stakeholders. This authorization is necessary to ensure that the project has the necessary support and resources to proceed.
6.
There are usually several versions of a scope statement, and each one becomes more detailed as the project progresses and more information becomes available.
Correct Answer
A. True
Explanation
As a project progresses and more information becomes available, the scope statement tends to evolve and become more detailed. This is because at the beginning of a project, there may be limited information and understanding of the project requirements. However, as the project moves forward and more information is gathered, the scope statement can be refined and expanded to include more specific details and requirements. Therefore, it is true that there are usually several versions of a scope statement, with each version becoming more detailed as the project progresses.
7.
The majority of project management processes occur as part of the executing process group.
Correct Answer
B. False
Explanation
The majority of project management processes do not occur as part of the executing process group. Project management processes are divided into five process groups: initiating, planning, executing, monitoring and controlling, and closing. While executing is an important process group, it does not encompass the majority of project management processes. The planning process group, for example, involves creating a detailed project plan, defining project objectives, and identifying project risks. The monitoring and controlling process group involves tracking project progress, managing changes, and ensuring project quality. Therefore, the correct answer is False.
8.
A crucial part of the project charter is the ____ section, where key project stakeholders sign the document to acknowledge their agreement on the need for the project.
Correct Answer
C. Sign-off
Explanation
The sign-off section of the project charter is important because it ensures that key project stakeholders have acknowledged and agreed on the need for the project. This section serves as a formal confirmation that these stakeholders are committed to the project and its objectives. It helps in establishing accountability and ensures that there is a shared understanding and agreement among all parties involved in the project.
9.
Which of the following information is typically included in a business case?
Correct Answer(s)
A. Competitor Opinions
B. Personal Background Checks
C. Business Objective
Explanation
A business case typically includes competitor opinions, personal background checks, and business objectives. Competitor opinions are important to assess the competitive landscape and understand the market dynamics. Personal background checks help evaluate the qualifications and credibility of individuals involved in the business. Business objectives outline the goals and targets that the organization aims to achieve. Including these elements in a business case provides a comprehensive understanding of the industry, the people involved, and the desired outcomes.
10.
Applying project management process groups in a consistent, structured fashion increases the chance of project success.
Correct Answer
A. True
Explanation
Applying project management process groups in a consistent, structured fashion increases the chance of project success. This is because following a standardized approach to project management ensures that all necessary steps and activities are properly planned, executed, monitored, and controlled. It helps in identifying and managing risks, allocating resources effectively, and ensuring clear communication and collaboration among team members. By following a consistent and structured process, project managers can minimize errors, improve efficiency, and increase the likelihood of achieving project objectives within the defined constraints.
11.
Companies that excel in project management know that every project manager should create unique document formats for project charters and business cases.
Correct Answer
B. False
Explanation
The statement is false because companies that excel in project management do not necessarily require project managers to create unique document formats for project charters and business cases. While it is important for project managers to create these documents, there is no requirement for them to be unique. Many companies have standardized templates or formats that project managers can use, which can help streamline the project management process and ensure consistency across projects.
12.
It is good practice to document kick-off meeting minutes, focusing on key decisions and ____ items.
Correct Answer
D. Action
Explanation
In a kick-off meeting, it is important to document the key decisions made and any action items that need to be taken. This helps ensure that everyone is on the same page and accountable for their tasks. By documenting the action items, it becomes easier to track progress and follow up on any unresolved issues. Therefore, the correct answer is "Action".
13.
Part of creating and following a project management methodology includes the creation and use of document ____.
Correct Answer
B. Templates
Explanation
A project management methodology involves creating and following a set of processes and procedures to ensure successful project completion. One important aspect of this methodology is the creation and use of document templates. Templates provide a standardized format for project documents such as project plans, status reports, and meeting agendas. They help save time and effort by providing a starting point and structure for creating these documents, ensuring consistency and efficiency throughout the project.
14.
Most experienced people will assert that it is easier to successfully complete a large project than a small one.
Correct Answer
B. False
Explanation
The given statement is "Most experienced people will assert that it is easier to successfully complete a large project than a small one." The correct answer is False. The statement suggests that it is easier to complete a large project than a small one, but the correct answer is False because it is generally believed that smaller projects are easier to manage and complete successfully compared to larger projects. This is because smaller projects usually have fewer complexities, require less coordination, and can be completed in a shorter time frame.
15.
Which of the following methods best helps a project manager identify and learn about key project stakeholders?
Correct Answer
A. Questioning acquaintances
Explanation
Questioning acquaintances is the best method to help a project manager identify and learn about key project stakeholders. This is because acquaintances may have knowledge or connections to individuals who are involved or have information about the project. By asking questions and seeking input from acquaintances, the project manager can gather valuable insights and potentially uncover important stakeholders who may have otherwise been overlooked. This method allows for direct communication and personal interactions, which can provide a deeper understanding of the project's stakeholders.
16.
For a large training project, there is often a(n) ____ project done first before investing in a larger project.
Correct Answer
D. Study
Explanation
Before investing in a larger project, it is often necessary to conduct a study. This study helps to gather information, analyze data, and assess the feasibility and potential success of the project. It allows for a thorough examination of the project's requirements, risks, and potential outcomes. By conducting a study beforehand, organizations can make informed decisions about whether or not to proceed with the larger project, saving time, resources, and potential setbacks.
17.
____ processes include devising and maintaining a workable scheme to ensure that the project meets its scope, time, and cost goals as well as organizational needs.
Correct Answer
B. Planning
Explanation
The given correct answer is "Planning". Planning is the process of creating a detailed plan or strategy to achieve the project's objectives and goals. It involves identifying the scope, defining the tasks and activities, estimating the resources and time required, and creating a schedule and budget. Planning ensures that the project is well-organized and that all necessary steps are taken to meet the project's scope, time, and cost goals, as well as the needs of the organization.
18.
It is helpful to create a ____, or initial, scope statement during project initiation so that the entire project team can start important discussions and work related to the project scope.
Correct Answer
C. . Preliminary
Explanation
During project initiation, it is important to create a preliminary scope statement. This statement helps the project team to start discussions and work related to the project scope. It provides an initial understanding of the project's objectives, deliverables, and boundaries. By having a preliminary scope statement, the team can begin to identify key stakeholders, define project requirements, and establish a foundation for further planning and execution.
19.
Typically included in the project charter, the ____ section describes how the project objectives will be met, provides a list of important assumptions, and often gives references to related documents.
Correct Answer
D. Approach
Explanation
The approach section is typically included in the project charter and it describes how the project objectives will be met. It provides a list of important assumptions and often gives references to related documents. This section outlines the specific strategies, methodologies, and techniques that will be used to achieve the project goals and deliverables. It helps to ensure that all stakeholders have a clear understanding of the planned approach for the project.
20.
4
One of the main tasks normally involved in project initiation is to identify and understand project ____.
Correct Answer
B. Stakeholders
Explanation
In project initiation, it is important to identify and understand project stakeholders. Stakeholders are individuals or groups who have an interest or can be affected by the project. They can include project sponsors, team members, clients, customers, suppliers, and the community. Understanding stakeholders is crucial for effective project management as it helps in identifying their needs, expectations, and potential impact on the project. This enables project managers to engage and communicate with stakeholders effectively, ensuring their involvement and support throughout the project lifecycle.