Chapter 6 Trivia Quiz: Project Management

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Roadman19771
R
Roadman19771
Community Contributor
Quizzes Created: 37 | Total Attempts: 24,251
Questions: 10 | Attempts: 442

SettingsSettingsSettings
Chapter 6 Trivia Quiz: Project Management - Quiz

Have you completed chapter six of your project management course? How confident are you that you understood all that you were taught? The quiz below is designed to test exactly that and your preparedness to move on to the next chapter, so press start and get to refresh your memory or add on to what you already know. All the best!


Questions and Answers
  • 1. 

    What is the first process in planning a project schedule?

    • A.

      Defining milestones

    • B.

      Defining activities

    • C.

      Estimating activity resources

    • D.

      Sequencing activity sequencing

    Correct Answer
    B. Defining activities
    Explanation
    The first process in planning a project schedule is defining activities. This involves breaking down the project into smaller, manageable tasks or activities that need to be completed. By defining activities, the project manager can identify the specific work that needs to be done, determine the order in which the activities should be performed, and estimate the time and resources required for each activity. This initial step lays the foundation for creating a detailed project schedule and helps in effectively managing and tracking progress throughout the project.

    Rate this question:

  • 2. 

    Predecessors, successors, logical relationships, lead and lags, resource requirements, constraints, imposed dates, and assumptions are all examples of __________

    • A.

      Items in an activity list

    • B.

      Items on a Gnatt chart

    • C.

      Milestone attributes

    • D.

      Activity attributes

    Correct Answer
    D. Activity attributes
    Explanation
    Activity attributes refer to the various characteristics or properties associated with an activity in a project. These attributes include predecessors, successors, logical relationships, lead and lags, resource requirements, constraints, imposed dates, and assumptions. They provide detailed information about each activity and help in planning and managing the project effectively. Activity attributes are typically documented in the project schedule and are used to track progress, allocate resources, and ensure successful completion of the project.

    Rate this question:

  • 3. 

    As the project manager for a software development company, you are helping to develop the project schedule.  You decide that writing code for a system should not start until users sign off on the analysis work.  What type of dependency is this?

    • A.

      Technical

    • B.

      Mandatory

    • C.

      Discretionary

    • D.

      External

    Correct Answer
    C. Discretionary
    Explanation
    This type of dependency is discretionary. Discretionary dependencies are those that are established based on the judgment of the project team or stakeholders. In this case, the project manager has made the decision that the code writing should not start until users sign off on the analysis work, based on their judgment that it is necessary for the project's success.

    Rate this question:

  • 4. 

    You cannot start editing a technical report until someone else completes the first draft.  What type of dependency does this represent?

    • A.

      Finish-To-Start

    • B.

      Start-To-Start

    • C.

      Finish-To-Finish

    • D.

      Start-To-Finish

    Correct Answer
    A. Finish-To-Start
    Explanation
    This question represents a Finish-To-Start dependency, where the completion of one task (someone else completing the first draft) is required before another task (starting to edit the technical report) can begin.

    Rate this question:

  • 5. 

    Which of the following statements is false?

    • A.

      A resource structure is a hierarchical structure that identifies the project's resources by category and type

    • B.

      Duration and effort are synonymous terms

    • C.

      A three-point estimate is an estimate that includes an optimistic, most-likely, and pessimistic estimate

    • D.

      A Gnatt chart is a common tool for displaying project schedule information

    Correct Answer
    B. Duration and effort are synonymous terms
    Explanation
    The statement "Duration and effort are synonymous terms" is false because duration refers to the amount of time it takes to complete a task or project, while effort refers to the amount of work or labor required to complete the task or project. These terms are related but not interchangeable, as a task may require a high level of effort but a short duration, or vice versa.

    Rate this question:

  • 6. 

    What symbol on a Gnatt chart represents a slipped milestone?

    • A.

      Black arrow

    • B.

      White arrow

    • C.

      Black diamond

    • D.

      White diamond

    Correct Answer
    D. White diamond
    Explanation
    A white diamond symbol on a Gantt chart represents a slipped milestone. This means that the milestone was originally scheduled to be completed at a certain time but has been delayed or missed. The white diamond allows project managers and team members to easily identify and track any milestones that have been delayed, helping them to take necessary actions to get the project back on track.

    Rate this question:

  • 7. 

    What type of diagram show planned and actual project schedule information?

    • A.

      Network diagram

    • B.

      Gnatt Chart

    • C.

      Tracking Gnatt Chart

    • D.

      Milestone chart

    Correct Answer
    C. Tracking Gnatt Chart
    Explanation
    A tracking Gantt chart is a type of diagram that displays both the planned and actual project schedule information. It is used to track the progress of a project by comparing the planned schedule with the actual progress. This chart allows project managers to visually see any deviations or delays from the original plan and make necessary adjustments to keep the project on track. It provides a clear overview of the project's timeline and helps in identifying critical tasks and potential bottlenecks.

    Rate this question:

  • 8. 

    _____________ is a network diagramming technique used to predict total project duration.

    • A.

      PERT

    • B.

      Gnatt Chart

    • C.

      Critical path method

    • D.

      Crashing

    Correct Answer
    A. PERT
    Explanation
    PERT (Program Evaluation and Review Technique) is a network diagramming technique used to predict the total project duration. It involves breaking down the project into smaller tasks and estimating the time required for each task. PERT also considers the dependencies between tasks and incorporates probabilistic time estimates, taking into account optimistic, pessimistic, and most likely time durations. By analyzing the network diagram and considering the critical path, PERT helps in determining the expected duration of the entire project.

    Rate this question:

  • 9. 

    Which of the following statements is false?

    • A.

      "Growing grass" was on the critical path for a large theme park project

    • B.

      The critical path is the series of activities that determine the earliest time by which a project can be completed

    • C.

      A forward pass through a project network diagram determines the early start and early finish dates for each activity

    • D.

      Fast tracking is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost

    Correct Answer
    D. Fast tracking is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost
    Explanation
    Fast tracking is not a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost. Fast tracking is a technique that involves overlapping activities that would normally be done in sequence in order to expedite the project schedule. It may increase costs and risks, but it can help in compressing the project schedule.

    Rate this question:

  • 10. 

    ___________ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.

    • A.

      Parkinson's Law

    • B.

      Murphy's Law

    • C.

      Critical path analysis

    • D.

      Critical chain scheduling

    Correct Answer
    D. Critical chain scheduling
    Explanation
    Critical chain scheduling is a method of scheduling that takes into account the limited resources available for a project and incorporates buffers to safeguard the project completion date. This approach recognizes that resource constraints can impact the project timeline and aims to optimize the allocation of resources to ensure efficient project completion. By including buffers, such as project buffers and feeding buffers, critical chain scheduling helps to mitigate uncertainties and delays, allowing for better project management and timely delivery.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Oct 30, 2009
    Quiz Created by
    Roadman19771
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.