Simple Information Technology Project Management Quiz

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Roadman19771
R
Roadman19771
Community Contributor
Quizzes Created: 37 | Total Attempts: 24,286
Questions: 22 | Attempts: 934

SettingsSettingsSettings
Simple Information Technology Project Management Quiz - Quiz

This is a simple information technology quiz that is designed to test out how well you understood the topic we just covered. Projects have a clear start and end, and this is actualized when people follow the laid down plans to meet a specified goal. Take up this quiz and see how well you would prosper in the field. All the best!


Questions and Answers
  • 1. 

    Have no duration and no resources but are occasionally needed on AOA network diagrams to show logical relationships between activities 

    • A.

      Three Point Estimate

    • B.

      Dummy Activities

    • C.

      Duration

    Correct Answer
    B. Dummy Activities
    Explanation
    Dummy activities are used in AOA network diagrams to represent logical relationships between activities. They have no duration or resources associated with them, but are necessary to accurately depict the sequence and dependencies between activities. Dummy activities are typically shown as dashed lines and are used when there is a need to show a relationship between two activities that cannot be directly connected. They help to clarify the logical flow and dependencies in the network diagram.

    Rate this question:

  • 2. 

    A hierarchical structure that identifies the project’s resources by category and type 

    • A.

      Resource Breakdown Structure

    • B.

      Dummy Activities

    • C.

      Three Point Estimate

    Correct Answer
    A. Resource Breakdown Structure
    Explanation
    A Resource Breakdown Structure is a hierarchical structure that categorizes and identifies the project's resources by their category and type. It provides a clear and organized view of the project's resources, allowing for better planning, allocation, and management of resources throughout the project lifecycle. By breaking down resources into categories and types, it becomes easier to understand the availability, skills, and requirements of each resource, enabling efficient resource utilization and optimization. This structure helps in ensuring that the right resources are assigned to the right tasks and that there is no shortage or overallocation of resources.

    Rate this question:

  • 3. 

    Includes that actual amount of time worked on an activity plus elapsed time

    • A.

      Effort

    • B.

      Consistency

    • C.

      Duration

    Correct Answer
    C. Duration
    Explanation
    Duration refers to the total amount of time spent on a particular activity, including both the actual time worked and any elapsed time. It takes into account the entire duration of the activity, from start to finish, and is an important factor in measuring the overall time commitment and efficiency of the task. Effort and consistency, on the other hand, are related to the level of energy and dedication put into the activity, but they do not necessarily capture the full duration of the task.

    Rate this question:

  • 4. 

    The number of workdays or work hours required to complete a task

    • A.

      Effort

    • B.

      Duration

    • C.

      Project timetable

    Correct Answer
    A. Effort
    Explanation
    Effort refers to the amount of work or energy required to complete a task. It is a measure of the resources, such as time and labor, needed to accomplish a specific goal. The number of workdays or work hours required to complete a task directly relates to the effort involved. Duration, on the other hand, refers to the total time taken to complete a task, including any breaks or delays. Project timetable is a schedule that outlines the planned start and end dates for various project activities. While both duration and project timetable are related to time, they do not specifically address the amount of work or resources required, making effort the correct answer.

    Rate this question:

  • 5. 

    An estimate that includes an optimistic, most-likely, and pessimistic estimate 

    • A.

      Tracking Gnatt Chart

    • B.

      Three Point Estimate

    • C.

      SMART Criteria

    Correct Answer
    B. Three Point Estimate
    Explanation
    A three-point estimate is an estimation technique that includes an optimistic, most-likely, and pessimistic estimate. This method is commonly used in project management to account for uncertainties and risks. The optimistic estimate represents the best-case scenario, the most-likely estimate represents the most probable outcome, and the pessimistic estimate represents the worst-case scenario. By considering these three estimates, project managers can better understand the range of possible outcomes and make informed decisions.

    Rate this question:

  • 6. 

    Guidelines used for developing milestones.  Stands for Specific Measurable, Assignable, Realistic, Time-framed 

    • A.

      Slack or Float

    • B.

      SMART Criteria

    • C.

      Three Point Estimate

    Correct Answer
    B. SMART Criteria
    Explanation
    The SMART criteria are guidelines used for developing milestones. SMART stands for Specific, Measurable, Assignable, Realistic, and Time-framed. This means that milestones should be clearly defined, quantifiable, assignable to a specific person or team, achievable within a given timeframe, and relevant to the overall project goals. Using the SMART criteria helps ensure that milestones are well-defined and can be effectively measured and tracked, leading to more successful project outcomes.

    Rate this question:

  • 7. 

    A Gnatt chart that compares planned and actual project schedule information 

    • A.

      Tracking Gnatt Chart

    • B.

      SMART Criteria

    • C.

      Critical Path Method or Critical Path Analysis

    Correct Answer
    A. Tracking Gnatt Chart
    Explanation
    A tracking Gantt chart is a visual representation that compares the planned schedule of a project with the actual progress made. It allows project managers to track and monitor the project's timeline, identify any delays or discrepancies, and make necessary adjustments to ensure that the project stays on track. By comparing the planned and actual schedule information, project managers can effectively manage resources, identify potential risks, and make informed decisions to keep the project on schedule.

    Rate this question:

  • 8. 

    The milestone activity was actually completed later than originally planned 

    • A.

      Slack or Float

    • B.

      Fast Tracking

    • C.

      Slipped Milestone

    Correct Answer
    C. Slipped Milestone
    Explanation
    The correct answer is "Slipped Milestone". This term refers to a situation where a milestone activity, which is a significant event or achievement in a project, is completed later than the initial planned date. It indicates a delay or setback in the project timeline. In this case, the milestone activity was completed later than originally planned, suggesting that there was a delay in achieving the targeted milestone.

    Rate this question:

  • 9. 

    A network diagramming technique used to predict total project duration 

    • A.

      Tracking Gnatt Chart

    • B.

      Theory of Constraints (TOC)

    • C.

      Critical Path Method or Critical Path Analysis

    Correct Answer
    C. Critical Path Method or Critical Path Analysis
    Explanation
    The correct answer is Critical Path Method or Critical Path Analysis. The Critical Path Method is a network diagramming technique used to predict the total project duration. It identifies the sequence of activities that must be completed on time in order to complete the project on schedule. By analyzing the critical path, project managers can determine which activities are most crucial to the project's timeline and allocate resources accordingly. This method helps in identifying the project's critical path, which is the longest path of dependent activities that determines the shortest possible project duration.

    Rate this question:

  • 10. 

    The amount of time an activity may be delayed without delaying a succeeding activity or the project finish date 

    • A.

      Slack or Float

    • B.

      Slipped Milestone

    • C.

      Backward Pass

    Correct Answer
    A. Slack or Float
    Explanation
    Slack or float refers to the amount of time that an activity can be delayed without delaying the project finish date or any succeeding activities. It represents the flexibility within the project schedule and allows for adjustments and delays without impacting the overall timeline. This concept is important in project management as it helps in identifying critical activities that have zero slack or float and need to be closely monitored to ensure timely completion of the project.

    Rate this question:

  • 11. 

    Determines he early start and early finish dates for each activity

    • A.

      Backward Pass

    • B.

      Fast Tracking

    • C.

      Forward Pass

    Correct Answer
    C. Forward Pass
    Explanation
    The forward pass is a scheduling technique used in project management that determines the early start and early finish dates for each activity in a project. It involves calculating the earliest possible start and finish dates for each activity based on the project's network diagram and the dependencies between activities. By performing the forward pass, project managers can identify the critical path and determine the earliest possible completion date for the project.

    Rate this question:

  • 12. 

    Determines the late start and late finish dates for each activity

    • A.

      Backward Pass

    • B.

      Forward Pass

    • C.

      Critical Chain Scheduling

    Correct Answer
    A. Backward Pass
    Explanation
    The backward pass is a scheduling technique that determines the late start and late finish dates for each activity in a project. It starts from the project's end date and works backwards, considering the dependencies and constraints of each activity. By calculating the late start and late finish dates, the project manager can identify the amount of flexibility or float available for each activity. This information is crucial for identifying the critical path, which consists of activities with zero float and determines the minimum project duration. Therefore, the backward pass is the correct answer as it specifically addresses the determination of late start and late finish dates.

    Rate this question:

  • 13. 

    A technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost 

    • A.

      Parkinson’s Law

    • B.

      Crashing

    • C.

      Multitasking

    Correct Answer
    B. Crashing
    Explanation
    Crashing is a technique used in project management to make cost and schedule trade-offs. It involves allocating additional resources to critical activities in order to compress the project schedule and meet tight deadlines. By doing so, the project can be completed earlier, but it may come at an incremental cost. Therefore, crashing allows for the greatest amount of schedule compression while considering the least incremental cost.

    Rate this question:

  • 14. 

    Doing activities in parallel that you would normally do in sequence

    • A.

      Forward Pass

    • B.

      Multitasking

    • C.

      Fast Tracking

    Correct Answer
    C. Fast Tracking
    Explanation
    Fast tracking refers to a project management technique where activities that are typically done sequentially are carried out in parallel to accelerate the project schedule. This involves overlapping activities to reduce the overall project duration. By fast tracking, project managers can save time and expedite the completion of a project. Therefore, the given answer, "Fast Tracking," accurately describes the concept of doing activities in parallel that are normally done in sequence.

    Rate this question:

  • 15. 

    Based on the fact that, like a chain with its weakest link, any complex system at any point in time often only has one or constraint that limits its ability to achieve more of its goal 

    • A.

      Theory of Constraints (TOC)

    • B.

      Critical Chain Scheduling

    • C.

      Program Evaluation and Review Technique (PERT)

    Correct Answer
    A. Theory of Constraints (TOC)
    Explanation
    Theory of Constraints (TOC) is the correct answer because it is a management philosophy that focuses on identifying and managing the constraints or bottlenecks in a system in order to improve overall performance. It suggests that a complex system usually has one or a few constraints that limit its ability to achieve its goals, and by identifying and addressing these constraints, the system can be optimized. TOC helps organizations prioritize and allocate resources effectively, and it provides a framework for continuous improvement and problem-solving. Critical Chain Scheduling and Program Evaluation and Review Technique (PERT) are project management techniques that can be used within the TOC framework to manage and optimize projects.

    Rate this question:

  • 16. 

    A method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date 

    • A.

      Project Buffer

    • B.

      Feeding Buffer

    • C.

      Critical Chain Scheduling

    Correct Answer
    C. Critical Chain Scheduling
    Explanation
    Critical Chain Scheduling is a method of scheduling that takes into account limited resources when creating a project schedule. It involves the use of buffers to protect the project completion date. These buffers are placed strategically throughout the project to account for uncertainties and delays, ensuring that the project stays on track and is completed on time. By considering resource constraints and implementing buffers, Critical Chain Scheduling helps to optimize project timelines and improve overall project performance.

    Rate this question:

  • 17. 

    Occurs when a resource works on more than one task at a time

    • A.

      Probabilistic Time Estimate

    • B.

      Fast Tracking

    • C.

      Multitasking

    Correct Answer
    C. Multitasking
    Explanation
    Multitasking refers to the situation where a resource, such as a person or a computer, works on more than one task simultaneously. This can lead to increased productivity and efficiency, as multiple tasks can be completed concurrently. However, it can also result in decreased focus and potential errors if the resource is not able to effectively manage and prioritize the different tasks. Multitasking is a common practice in many industries and is often used to optimize resource utilization and meet tight deadlines.

    Rate this question:

  • 18. 

    Additional time added before the project’s due date

    • A.

      Critical Chain Scheduling

    • B.

      Project Buffer

    • C.

      Feeding Buffers

    Correct Answer
    B. Project Buffer
    Explanation
    A project buffer is a time reserve added before the project's due date to account for any unexpected delays or issues that may arise during the project. It acts as a safety net and allows for flexibility in the project schedule. By adding extra time to the project buffer, the project manager can ensure that the project can still be completed on time even if there are unforeseen obstacles. This is a key concept in critical chain scheduling, which aims to optimize project schedules by focusing on the critical path and managing uncertainties effectively.

    Rate this question:

  • 19. 

    Additional time that is added before tasks on the critical chain that are preceded by non-critical path tasks 

    • A.

      Feeding Buffers

    • B.

      Project Buffer

    • C.

      Theory of Constraints (TOC)

    Correct Answer
    A. Feeding Buffers
    Explanation
    Feeding Buffers refer to additional time that is added before tasks on the critical chain that are preceded by non-critical path tasks. These buffers are used in the Theory of Constraints (TOC) methodology to protect the critical chain from delays caused by non-critical tasks. By adding extra time to the tasks that are dependent on non-critical tasks, any delays in the non-critical tasks will not impact the overall project schedule. This helps to ensure that the critical chain remains on track and the project is completed within the desired timeframe.

    Rate this question:

  • 20. 

    States that work expands to fill the time allowed

    • A.

      Parkinson’s Law

    • B.

      Probabilistic Time Estimate

    • C.

      Program Evaluation and Review Technique (PERT)

    Correct Answer
    A. Parkinson’s Law
    Explanation
    Parkinson's Law states that work expands to fill the time allowed. This means that if a certain amount of time is allocated for a task, people will tend to use up all of that time to complete the task, even if it could have been done more efficiently in a shorter amount of time. This concept highlights the tendency for work to stretch out and take longer than necessary, and emphasizes the importance of setting realistic deadlines and managing time effectively.

    Rate this question:

  • 21. 

    A network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates 

    • A.

      Theory of Constraints (TOC)

    • B.

      Feeding Buffers

    • C.

      Program Evaluation and Review Technique (PERT)

    Correct Answer
    C. Program Evaluation and Review Technique (PERT)
    Explanation
    Program Evaluation and Review Technique (PERT) is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates. PERT incorporates three estimates for each activity: optimistic, most likely, and pessimistic. By using these estimates, PERT calculates the expected duration for the project and identifies the critical path, which is the sequence of activities that determines the shortest possible project duration. PERT is particularly useful when there is a high level of uncertainty in project scheduling, as it allows for a more realistic estimation of project duration.

    Rate this question:

  • 22. 

    Duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations 

    • A.

      SMART Criteria

    • B.

      Probabilistic Time Estimate

    • C.

      Forward Pass

    Correct Answer
    B. Probabilistic Time Estimate
    Explanation
    This answer is correct because the term "Probabilistic Time Estimate" is mentioned in the given list of terms. The question is asking for an explanation of this term, which refers to the practice of estimating activity durations based on optimistic, most likely, and pessimistic estimates. This approach takes into account the uncertainty and variability in the time required for each activity, allowing for a more realistic and accurate estimation of the overall project duration.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Oct 31, 2009
    Quiz Created by
    Roadman19771
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.