1.
Which of the following are characteristics of a Project
Correct Answer
B. Unique
Explanation
A project is characterized by being unique, meaning that it is a one-time endeavor with specific objectives and deliverables. Unlike repetitive tasks, projects have a defined start and end date, and they are undertaken to achieve a specific outcome or result. Projects also involve some degree of risk, as they often face uncertainties and challenges that need to be managed. Lastly, projects are not constant but rather temporary in nature, as they are completed once their objectives are achieved.
2.
Is there a difference between project management and operational management
Correct Answer
A. Yes
Explanation
There is a difference between project management and operational management. Project management involves planning, organizing, and executing specific projects to achieve specific goals within a defined timeframe. It is temporary in nature and focuses on delivering a unique product, service, or result. On the other hand, operational management involves the day-to-day activities of managing ongoing operations within an organization. It focuses on the efficient and effective delivery of products or services on a continuous basis.
3.
Which of the following is classed as business as usual
Correct Answer
A. Continuous Manufacturing
Explanation
Continuous manufacturing is classified as business as usual because it refers to a production method that involves the uninterrupted and ongoing production of goods or services. It is a standard practice that is regularly carried out in the normal course of business operations. In contrast, a plant upgrade, new process implementation, or product introduction are considered as changes or new initiatives that deviate from the regular operations and require additional resources and planning.
4.
Which of the following should a project manager primarily focus on
Correct Answer
B. Delivering Defined Benefits
Explanation
A project manager should primarily focus on delivering defined benefits. This means that their main goal should be to ensure that the project achieves the desired outcomes and delivers the expected benefits to the organization. This involves managing the project scope, timeline, resources, and risks to ensure that the project objectives are met and the expected benefits are realized. While managing environmental threats and organizational influences are important aspects of project management, the ultimate focus should be on delivering the defined benefits.
5.
Which of the following would you consider a characteristics of a project
Correct Answer
C. It has a defined scope
Explanation
A project is characterized by having a defined scope, meaning that it has clear objectives and boundaries. This allows for the project to be effectively planned, executed, and controlled. A defined scope ensures that the project team and stakeholders understand what is included and excluded from the project, preventing scope creep and ensuring that the project stays on track.
6.
What is a project stakeholder
Correct Answer
C. Anybody with a vested project interest
Explanation
A project stakeholder refers to anyone who has a vested interest in the project. This includes individuals or groups who may be affected by the project's outcomes or have the ability to influence its success. Stakeholders can include project team members, clients, customers, sponsors, suppliers, and even the general public. They play a crucial role in shaping the project's objectives, providing input and feedback, and ensuring that the project meets their needs and expectations.
7.
Which of the following is not in a Project Status Report
Correct Answer
D. Key responsibilities and roles
Explanation
The given options are all elements that are typically included in a Project Status Report. However, "Key responsibilities and roles" is not typically included in a Project Status Report. This report typically focuses on the progress of the project, the activities planned for the upcoming week, and the key milestones and deliverables. The roles and responsibilities of the team members are usually outlined in a separate document, such as a project plan or a team charter.
8.
What are the characteristics of a project milestone
Correct Answer
C. It is an event in the project
Explanation
A project milestone refers to a significant event or achievement within a project. It is a specific point in time that marks the completion of a major deliverable or the accomplishment of a key objective. Milestones are essential in project management as they help track progress, provide a sense of accomplishment, and act as checkpoints to ensure that the project is on track. They do not necessarily consume resources or make the project more efficient, but they serve as important markers in the project timeline.
9.
Brainstorming is a valid project management tool and technique. However, which of the following can brainstorming primarily support during project planning
Correct Answer
C. Understanding project deliverable
Explanation
Brainstorming is a technique that encourages open and creative thinking among team members. It allows them to generate ideas, explore different perspectives, and identify potential project deliverables. By engaging in brainstorming sessions, project teams can gain a deeper understanding of the desired outcomes and objectives of the project. This helps in clarifying the project deliverables and setting clear goals and expectations. Therefore, brainstorming primarily supports understanding project deliverables during project planning.
10.
Which of the following is a characteristic/focus of project change management
Correct Answer
B. Supporing the delivery of the project scope, schedule and cost plans
Explanation
The characteristic/focus of project change management is supporting the delivery of the project scope, schedule, and cost plans. This involves ensuring that the project objectives are met within the defined scope, schedule, and budget. It includes managing any changes that may arise during the project and making sure that they are properly integrated into the plans and communicated to all stakeholders. This focus helps to ensure that the project stays on track and achieves its intended outcomes.
11.
What is Risk
Correct Answer
D. It is an uncertain issue
Explanation
Risk is defined as an uncertain issue because it refers to the possibility of an undesirable event or outcome occurring. It involves uncertainty because the outcome of a risky situation cannot be predicted with complete certainty. Risks are typically associated with potential losses or negative consequences, and they require careful evaluation and management to minimize their impact. Therefore, the correct answer is "It is an uncertain issue."
12.
What is the function of a Communication Plan
Correct Answer
B. Clarify how stakeholders are to be connected/integrated into the project
Explanation
A communication plan in a project serves the purpose of clarifying how stakeholders are to be connected and integrated into the project. It outlines the strategies and methods to effectively communicate with the stakeholders, ensuring that they are informed about the project's progress, goals, and any changes. By clarifying the communication channels and methods, the plan ensures that stakeholders are engaged and their input is considered, leading to better collaboration and project success.
13.
What is the responsibility of the Project Steering Group
Correct Answer
D. They are the escalation point for all project-related decisions
Explanation
The responsibility of the Project Steering Group is to act as the escalation point for all project-related decisions. This means that they are the final authority in making decisions for the project and resolving any issues or conflicts that may arise. They play a crucial role in ensuring that the project progresses smoothly and that all decisions are made in the best interest of the project and aligned with organizational structures. They also provide guidance and support to the project team and act as a point of reference for project progress.
14.
Which of the following would you expect to see in a Project Plan
Correct Answer
A. Gantt Chart and Activity List
Explanation
A project plan typically includes a Gantt Chart and an Activity List. A Gantt Chart is a visual representation of the project schedule, showing the start and end dates of each task and their dependencies. It helps in tracking the progress of the project. An Activity List, on the other hand, provides a detailed breakdown of all the tasks and activities required to complete the project. It includes information such as task descriptions, responsible parties, and estimated durations. Together, these two elements help in effectively organizing and managing the project activities.
15.
Which of the following is a characteristic of Project Governance
Correct Answer
B. Clear responsibilities
Explanation
Clear responsibilities is a characteristic of Project Governance because it ensures that each individual involved in the project knows their role and responsibilities. This helps to avoid confusion and ensures that everyone is accountable for their tasks. Clear responsibilities also promote effective communication and coordination among team members, leading to better project outcomes.
16.
Are end-users part of the project
Correct Answer
A. Yes
Explanation
The end-users are indeed part of the project. This means that they play a role in the project's development, implementation, and evaluation. Their input and feedback are essential for ensuring that the project meets their needs and expectations. By involving end-users, the project team can gain valuable insights, improve user experience, and increase the chances of project success.
17.
What is the difference between a risk and an issue
Correct Answer
C. A risk is uncertain and an issue is a live event
Explanation
A risk refers to a potential uncertain event or situation that may have a negative impact on a project or organization. It is something that may or may not occur in the future. On the other hand, an issue is a current problem or concern that is already happening and requires immediate attention. It is a live event that needs to be addressed and resolved. Therefore, the difference between a risk and an issue is that a risk is uncertain and a future possibility, while an issue is a current and ongoing problem.
18.
What should be the objective of completing a Project Status Report
Correct Answer
A. Report Project Performance
Explanation
The objective of completing a Project Status Report is to report the project performance. This report provides an overview of the progress, achievements, and challenges faced during the project. It helps stakeholders and project managers to assess the project's current status, identify areas of improvement, and make informed decisions. By reporting project performance, it promotes transparency, accountability, and effective communication among team members and stakeholders.
19.
What are the major constraints of a project
Correct Answer
A. Time, Cost and Scope
Explanation
The major constraints of a project are time, cost, and scope. Time refers to the duration or deadline for completing the project. Cost refers to the budget or financial resources allocated for the project. Scope refers to the specific goals, deliverables, and requirements of the project. These three constraints are interconnected and must be carefully managed to ensure the successful completion of the project within the given time frame, budget, and scope. Failure to manage these constraints effectively can lead to project delays, budget overruns, or incomplete deliverables.
20.
What would be a characteristic of Business as Usual Acceptance
Correct Answer
C. It is about the project understanding what it takes to transition the project deliverables into the busness
Explanation
Business as Usual Acceptance refers to the project's understanding of what is required to smoothly transition the project deliverables into the business. This means that the project team recognizes the necessary steps, processes, and considerations needed to integrate the project outcomes into the regular operations of the business. It involves ensuring that the deliverables align with the existing business processes and can be effectively implemented without disrupting the normal functioning of the organization. This characteristic emphasizes the importance of a seamless transition and successful integration of the project outcomes into the business operations.