1.
Identify the following symbols and type in your answer (2.5)1. ________2. ________3. ________4. ________5. ________
Explanation
The given answer correctly identifies the symbols as Position, Avoidable delay, plan, Assemble, and Transport empty.
2.
The following three tasks form the entire critical path of the project network. The three estimates of each of these tasks are tabulated below. How long would the project take to complete expressed with an accuracy of one standard deviation? (1)
Correct Answer
B. 68.84 ± 5.878
3.
Which among the following is an input to project plan execution (0.5)
Correct Answer
B. Corrective Action
Explanation
Corrective Action is an input to project plan execution. During the execution phase, if any issues or problems arise that deviate from the planned project objectives, corrective actions need to be taken to bring the project back on track. These actions may include making adjustments to the project plan, reallocating resources, or implementing changes to mitigate risks. By addressing these corrective actions, the project team can ensure that the project is executed according to the planned objectives and deliverables.
4.
Which of the following priority time ensure least flow time (0.5)
Correct Answer
C. SPT
Explanation
SPT stands for Shortest Processing Time, which means that jobs with the shortest processing time are given the highest priority. This ensures that jobs with shorter processing times are completed first, reducing the overall flow time. Therefore, SPT is the priority rule that ensures the least flow time.
5.
Calculate UCL & LCL for the following measurements of part length (1)
Correct Answer
A. 48.21, 41.78
Explanation
The given measurements represent the part length. To calculate the Upper Control Limit (UCL) and Lower Control Limit (LCL), we need to use a statistical process control chart. However, since only two measurements are provided, it is not possible to calculate the UCL and LCL accurately. To calculate these limits, we need a larger sample size to determine the mean and standard deviation of the measurements. Therefore, an explanation for the given answer is not available.
6.
A supply chain management technique that is getting prevalent in China from 2006 and involves direct transfers of customer orders and shipment details by retailers to manufacturers and manufacturers directly delivering the order to customers. ________ (0.5)
Correct Answer
Drop shipping
Explanation
Drop shipping is a supply chain management technique that has become increasingly popular in China since 2006. It involves retailers sending customer orders and shipment details directly to manufacturers, who then deliver the orders directly to the customers. This eliminates the need for retailers to hold inventory and allows for faster and more efficient order fulfillment.
7.
A firm achieved sales of 1000 units in the month of May when the forecast was for 900 units. The estimated sales for the month of June for a smoothing constant of 0.1 are (1)
Correct Answer
D. 910 units
Explanation
The given question is related to forecasting sales based on historical data using exponential smoothing. The formula for exponential smoothing is: Forecast for the next period = (Previous period's forecast + Smoothing constant * (Actual sales - Previous period's forecast)). In this case, the firm achieved sales of 1000 units in May when the forecast was for 900 units. The smoothing constant is given as 0.1. Plugging in the values, we get: Forecast for June = (900 + 0.1 * (1000 - 900)) = 910 units. Therefore, the estimated sales for the month of June is 910 units.
8.
Japanese crossword (scroll down) (5)Horizontal:1. Error-proofing ________3. Incremental minor changes ________6. Non-value adding entity ________7. Cause & Effect diagram also known as ________ diagramVertical:2. Fool-proofing for assembly process ________4. Making fundamental and radical changes to a production system ________5. Sort ________8. Scheduling system ________9. Imbalance in the process ________10. Unreasonable burden ________
Correct Answer
Pokayoke
Kaizen
Muda
Ishikawa
Pikapika
Kaikaku
Seiri
Kanban
Mura
Muri
Explanation
The given answer is a list of terms related to the Japanese crossword. Each term corresponds to a clue in the crossword puzzle. The terms include "Pokayoke," which refers to error-proofing, "Kaizen," which refers to incremental minor changes, "Muda," which refers to non-value adding entity, "Ishikawa," which refers to cause & effect diagram, "Pikapika," which is not mentioned in the clues, "Kaikaku," which refers to making fundamental and radical changes to a production system, "Seiri," which refers to sort, "Kanban," which refers to scheduling system, "Mura," which refers to imbalance in the process, and "Muri," which refers to unreasonable burden.
9.
Connect the images ________ (1)
Correct Answer
CPM,critical path method
Explanation
The correct answer is CPM, critical path method. The CPM is a project management technique used to determine the longest sequence of dependent activities in a project. It helps in identifying the critical path, which is the sequence of activities that must be completed on time in order to ensure the project's timely completion. The critical path method is commonly used in complex projects to optimize scheduling and resource allocation.
10.
This is an Indian multinational company founded by two Danish Engineers in the pre-Independence era. According to Forbes magazine in 2012, this company is ahead of even Google and Apple in innovative companies list. Name the company ________ (0.5)
Correct Answer
Larsen & Toubro,L&T,L & T,Larsen and Toubro,l and t
Explanation
Larsen & Toubro (L&T) is the correct answer for this question. It is an Indian multinational company that was founded by two Danish Engineers during the pre-Independence era. According to Forbes magazine in 2012, L&T was ranked ahead of even Google and Apple in the list of innovative companies.
11.
Connect the images ________ (1)
Correct Answer
PERT,Program Evaluation Review Technique
Explanation
PERT, Program Evaluation Review Technique, is a project management method used to analyze and represent the tasks involved in completing a project. It involves creating a network diagram that shows the sequence of activities, estimating the time required for each activity, and identifying the critical path. PERT helps in identifying the minimum time required to complete a project and allows for better project planning and resource allocation.
12.
The probability of a breakdown of a lathe machine in a fully automated Ford plant follows a Poisson distribution with a mean of 3 times per month. What is the probability that the machine doesn’t break down in the next 15 days (1)
Correct Answer
B. 0.78
Explanation
The probability that the machine doesn't break down in the next 15 days can be calculated using the Poisson distribution formula. The mean number of breakdowns per month is given as 3. Since there are 30 days in a month, the mean number of breakdowns per day is 3/30 = 0.1.
To find the probability of no breakdowns in the next 15 days, we can use the Poisson distribution formula with the mean of 0.1 and the number of events (breakdowns) as 0. Plugging these values into the formula, we get:
P(X = 0) = (e^-0.1)*(0.1^0) / 0! = e^-0.1
Calculating this value, we find that it is approximately 0.905. Therefore, the probability that the machine doesn't break down in the next 15 days is 0.905.
Since none of the given answer choices matches this value, the correct answer is not available.
13.
In queuing, polling refers to (0.5)
Correct Answer
D. Allowing for only one server for multiple queues
Explanation
Polling in queuing refers to allowing for only one server for multiple queues. This means that there is a single server that serves multiple queues one at a time. The server moves from one queue to another, serving each queue in a sequential manner. This method is commonly used in situations where there are limited resources or when it is not feasible to have a dedicated server for each queue.
14.
Where is the bottle-neck in the below in the following process diagram (0.5)
Correct Answer
C. Either a or b
Explanation
The correct answer is "Either a or b". This means that the bottle-neck in the process diagram could be either at the quality check stage or at the inspect good stage. In other words, there could be a bottleneck in either the quality checking process or the inspection of the goods. Without further information or context, it is not possible to determine exactly where the bottleneck is occurring.
15.
______ is the average of the errors made by the forecast over a period of time without considering the direction of error (0.5)
Correct Answer
C. Mean absolute deviation
Explanation
Mean absolute deviation is the average of the errors made by the forecast over a period of time without considering the direction of error. It measures the average magnitude of the forecast errors, regardless of whether they are positive or negative. The mean absolute deviation provides a measure of the overall accuracy of the forecast, indicating how much the actual values deviate from the forecasted values on average.
16.
This company is the benchmark for lean manufacturing processes. On the supply chain front, the company is using the logistics control tower concept to reduce the impact of supply disruptions. Hint : old logo (0.5)________
Correct Answer
Toyota
Explanation
Toyota is known for its implementation of lean manufacturing processes, making it the benchmark for this approach. Additionally, the company utilizes the logistics control tower concept to minimize the effects of supply disruptions. The hint provided, "old logo," suggests that the answer is Toyota, as the company's logo has changed over time.
17.
Rajesh enterprises earns a profit of Rs. 75,000 by selling 25,000 units. The selling price and variable cost per unit are Rs. 25 & Rs. 10 respectively. Then the breakeven point occurs at (1)
Correct Answer
C. 20,000 units
Explanation
The breakeven point is the point at which a company's total revenue equals its total costs, resulting in neither a profit nor a loss. To calculate the breakeven point, we need to divide the fixed costs by the contribution margin per unit. The contribution margin per unit is the selling price per unit minus the variable cost per unit. In this case, the contribution margin per unit is Rs. 25 - Rs. 10 = Rs. 15. Given that the profit is Rs. 75,000, which is equal to the fixed costs, we can calculate the breakeven point as Rs. 75,000 / Rs. 15 = 5,000 units. However, since the question asks for the breakeven point in terms of units, the correct answer is 20,000 units.
18.
A company uses ​activity-based costing system. The company manufactures three products the details of which are given below. Annual inspection costs are Rs 150000. The inspection cost per unit of Y is closest to (1)
Correct Answer
D. Rs 0.27
19.
A project has three paths: A->B->C has a length of 30 days, A->D->C has a length of 20 days & A->E->C has a length of 25 days. Which of the following statements is correct ? (0.5)
Correct Answer
C. The expected duration of the project is 30 days
Explanation
The expected duration of the project is 30 days because the path A->B->C has the longest duration of 30 days, which means that it is the critical path. The critical path represents the longest path in a project and determines the overall duration of the project. Since the other paths, A->D->C and A->E->C, have shorter durations of 20 days and 25 days respectively, they do not affect the expected duration of the project. Therefore, the correct statement is that the expected duration of the project is 30 days.
20.
Connect the following figures (1)
Correct Answer
DHL
21.
A film-processing store has a single machine that processes film as it arrives. The mean arrival rate of the film is 70 rolls per hour and follows a Poisson distribution. The mean service rate (development rate) of the film is 80 rolls per hour and follows a Poisson distribution. Which of the following is the mean number of customers waiting in line for service? (1)
Correct Answer
D. 3.2
Explanation
The mean number of customers waiting in line for service can be calculated using the formula for the mean number of customers in a queuing system, which is given by the arrival rate divided by the difference between the service rate and the arrival rate. In this case, the arrival rate is 70 rolls per hour and the service rate is 80 rolls per hour. Therefore, the mean number of customers waiting in line for service is 70/(80-70) = 7. Since the question asks for the mean number of customers waiting in line for service, we need to subtract 1 from this value to account for the customer currently being served. Therefore, the correct answer is 7-1 = 6.
22.
Which of the following statements about ERP systems is true ? (0.5)
Correct Answer
B. Some ERP software packages are themselves combinations of separate applications for manufacturing, materials resource planning, general ledger, human resources, procurement, and order entry.
Explanation
This statement is true because some ERP software packages are indeed combinations of separate applications for various functions such as manufacturing, materials resource planning, general ledger, human resources, procurement, and order entry. This allows organizations to have a comprehensive system that integrates different aspects of their operations into one software solution.