Welcome to the PERT and CPM Quiz! This quiz delves into two essential project management techniques: Program Evaluation and Review Technique and Critical Path Method. With 180 words, you'll embark on a journey to explore these methodologies crucial for effective project planning and scheduling.
Challenge yourself with questions covering topics such as activity sequencing, network diagrams, slack time, critical activities, and project variance. Gain insights into how these tools aid in resource allocation, risk management, and decision-making throughout project execution.
This quiz offers an engaging platform to assess your comprehension and refine your skills in PERT and CPM methodologies. Prepare Read moreto unravel the complexities of project scheduling and optimization, and see how well you fare in navigating the intricate paths of PERT and CPM!
Most likely time
Pessimistic time
Optimistic time
All of the above
Rate this question:
PERT is probabilistic in nature.
CPM is probabilistic in nature.
CPM and PERT use similar terminology but were developed independently.
All of these statements are correct.
Rate this question:
A project is a set of activities that can be performed in a certain logical sequence.
A network is a graphic portrayal of the independency relationship among the activities of a project.
An arrow representing an activity can have any length and shape.
An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Rate this question:
Each defined activity is represented by one and only one arrow.
A network should have only an initial and one terminal node.
Identical initial and final nodes can identify two activities.
Only as few dummy activities should be included as is warranted.
Rate this question:
Forward pass calculations yield the earliest and the latest start and finish times of various activities.
The difference between the latest and the earliest finish times is the total slack.
Backward pass determines the latest start and the latest finish.
Determination of the earliest and the latest start time of various activities of a project is useful for proper planning of their execution.
Rate this question:
All activities on a critical path are critical activities.
A project network may have none, one, or more critical paths.
A delay in critical activity surely delays the completion of the project.
Each critical activity has identical earliest and the latest start times.
Rate this question:
The expected time of an activity is a weighted average of three times estimates, a, m, and b, with respective weights of 1, 4, and 1.
The target time minus the expected time divided by standard deviation is the z value.
The completion of the project using the PERT method follows a normal distribution.
The sum total of variances of critical activity times gives the variance of the overall project completion time.
Rate this question:
0.6293
0.8413
0.1587
0.3707
Rate this question:
0.5000
0.6826
0.2586
0.3174
Rate this question:
An event that represents the initiation of more than one activity is called the burst event.
The longest path of a given project gives the maximum duration, while its shortest path indicates the shortest duration.
The resource allocation programs aim to allocate the given resources in a manner that the project completes in minimum time.
A non-critical activity may or may not have any free float.
Rate this question:
Quiz Review Timeline +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.