PM - Section 2

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Scannerdarkly
S
Scannerdarkly
Community Contributor
Quizzes Created: 3 | Total Attempts: 862
Questions: 10 | Attempts: 62

SettingsSettingsSettings
Project Management Quizzes & Trivia

Project Management course - Prof. M. Mancini
S-Curve


Questions and Answers
  • 1. 

    Divide the following statement about the use of the S-Curve based on the two phase of the project to which they belong: Phase of the project: A- Planning phase B- Control and redevelopment phase Statement: 1- Run an integrated time/cost analysis 2- Study correlation among project macro-phases 3- Plan resource usage and assess the congruence with the progress rates 4- Estimate EAC 5- Redevelop the resources

    • A.

      A{1;2;3} B{4;5}

    • B.

      A{2;5} B{1;3;4}

    • C.

      A{2;3} B{1;4;5}

    • D.

      A{1;3;4} B{2;4;5}

    Correct Answer
    C. A{2;3} B{1;4;5}
    Explanation
    1- it is a cost schedule analysis, for which the detailed schedule of the project is necessary: B
    2- done at the beginning in the planning phase: A
    3- it's a planning activity: A
    4- it is a cost schedule analysis, for which the detailed schedule of the project is necessary: B
    5- redevelop the resource is done when problem arise during the project: B

    Source: S-Curve 12 and 13.

    Rate this question:

  • 2. 

    BE AWARE: this exercise is tough. MPIF S.p.A. (Manage Project is fun) a project management company set in Como has been awarded with a contract from LIF Inc. (Logistic is funnier) for the renewal of its warehouse set in Rovellasca Manera. The project plan presetend by MPIF contains an S-Curve approximated with a trapezoidal function with aceleration phase equal to 4 months decelaration phase equal to 2 months and maximum rate of usage of resoruces equal to 0.1 (10%). Unfortunately during the approval meeting with the client LIF asked for a shorter duration of the works in order to minimize the loss due to the inaccessibility of the warehouse. After long discussions that did not leaded to violent actions only thanks to the intervention of the local police forces the managers of LIF made the following proposal: an additional benefit on the price of the work is awarded based on the following equation:  where d is the duration of the work and B the additional benefit in &euro. Knowing that: the cost function of MPIF for an increase in the rate of usage of resoruces for this plan is:  where r is the rate of resources usage (in decimal form) and C the additional costs in &euro due to the physical structure of warehouse the duration fo the aceleration phase cannot be changed due to a precise anti-dragging code followed by MPIF the deceleration phase cannot be changed. Help the project manager of MPIF in proposing the optimal project duration from the MPIF point of view. [Note: please provide the answer in month withouth the unit of measurement with 2 decimal digit with a "." as separator. e.g.: 3.12]

    Correct Answer
    10.71
    Explanation
    The initial duration of the central phase of the project is:

    4/2*0.1 + C*0.1 + 2/2*0.1 = 1 -> C=7 months

    The project therefore has an initial duration of 13 months. The marginal additional benefit for MPIF is:

    MB = 200.000(13 - d) - 20000((r-0.1)*100)^2

    the first derivative is:

    MB' = 200000/r^2 - 400000000*r + 40000000 = 0 -> r=0.1297 (it is a maximum, therefore is the rate the manager is looking for)

    The new central phase lasts:

    4/2*0.1297 + C*0.1297 + 2/2*0.1297 -> C = 4.71 months

    the MPIF optimal duration is therefore:

    D = 4 + 2 + 4.71 = 10.71 months

    Rate this question:

  • 3. 

    Can the Hermite Polynomials be used to assess the shape of an S-Curve of a project that, in the middle of its forecasted duration, is running over-budget, and that is forecasted to end using the 110% of the resources planned?

    • A.

      Yes

    • B.

      No

    Correct Answer
    A. Yes
    Explanation
    Yes - it simply will be redeployed through:

    (0.5;current use of resources in %) - (1;1.1)

    Rate this question:

  • 4. 

    Using the Bulk Park estimate, when the size decreases, the cost per unit of size:

    • A.

      Decreases if M

    • B.

      Increases if M

    • C.

      Decreases if M

    • D.

      Is always constant

    Correct Answer
    B. Increases if M
    Explanation
    The estimate is: C = C0*(P/P0)^M if M<1, C/P (the cost per unit of size) is:

    C / P = C0 / P0^M * P^M / P = a * P^M / P = a / P^(1-M), with (1-M)>0, that is an hyperbole, therefore when P decreases, C/P increases.

    Rate this question:

  • 5. 

    Mary, a junior manager of the iBuild company, is estimating the cost of a new project for a residential building in Bogotà using the Bulk Park estimate. She estimated the base cost with the great number of historical data related to the building operation of iBuild in North Italy, but she is having some trouble with the Escalation Factor (EF). Her boss told her to do it keeping into consideration that the building is almost entirely in concrete. The data: Price of concrete in most recent project: 1 €/Kg Most recent project: 2010 Price, concrete, in Italy, 2012: 1.5 €/kg Price, concrete, in Bogotà, 2012: 2 €/kg Price, concrete, in Bogotà, 2012: 1.8 €/kg Average inflation rate: 2%/year Help Mary in estimating EF

    • A.

      1.50

    • B.

      1.11

    • C.

      2.00

    • D.

      1.20

    • E.

      1.56

    • F.

      1.16

    Correct Answer
    A. 1.50
    Explanation
    The escalation factor is:

    "the index summarizing the temporal cost trend for the resource used to build the plant"

    and DOES NOT depend on the difference in the geographic location of two project. Therefore it is related to the price of the concrete in Italy:

    EF = 1.5/1 = 1.5

    There is no need to correct for inflation because the market prices by definition take into consideration inflation.

    Moreover, it will be the Location Factor that will take into consideration the difference in price between North Italy and Bogotà.

    Rate this question:

  • 6. 

    The usualy analytic cost estimation for the "Bulk Materials" is:

    • A.

      One-by-one analytic cost estimation based on the characteristic of the single material

    • B.

      Average quantity used in old project times eventual increase in average price

    • C.

      Project-specific, based on the estimated quantity requested by engineering documents

    • D.

      Done through the "cost curve"

    Correct Answer
    C. Project-specific, based on the estimated quantity requested by engineering documents
    Explanation
    Source: Cost estimate - slide 32

    Rate this question:

  • 7. 

    The PERT techniques allows a network diagram to have FS-FF-SF-SS links

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Source: Network Diagram - slide 21.

    Rate this question:

  • 8. 

    Given the following information about a network diagram: Activity | Duration | Precedences A              3               None B              2               None C              3               A, B Compute EOT(C)

    • A.

      2

    • B.

      3

    • C.

      4

    • D.

      5

    • E.

      Not enough data are provided

    Correct Answer
    B. 3
    Explanation
    EOT(k) = max(j:Ak){EFT(j)}

    where Ak is the set of direct predecessor of C

    EOT(C)=max(3;2)=3.

    Source: Network diagram - slide 30.

    Rate this question:

  • 9. 

    In a Precedence Diagram, it is always true that: EFT(i) - EST(i) = d(i) + 1 where d(i) is the duration of task i.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    A PDM allows for every type of link (Resource Network: Slide 21), and with links different from FS, the equation does not always hold (see for example exercise slide 89.

    Rate this question:

  • 10. 

    EMC Italy, a company set in Milan focus on Big Data, is currently dealing with the project for a new platform for one of its client. A young project manager, newly hired, is contacted by the client, that asks for a 2 days reduction in the duration of the project. The netwok diagram is the following [D(i) is the duration of task i]: Activity | Precedence | Duration standard | Cost [in thousand €] A            None               4 weeks                     9*(6-D(A)) B           None               3 weeks                      12*(7-D(B)) C           A                       4 weeks                     unknown D           B                      3 weeks                      4*(8-D(D)) E           C, D                 4 weeks                      3*[4-D(A)] + 10*(6 - D(E)) The activities can be crashed at most to half of their standard duration. Each activity must last a natural number of weeks. Considering that task C cannot be reduced because it is outsourced to a 3rd party, decide what price the young manager should ask the client, considering the EMC standard 20% mark-up on the cost of approved change. If more than a solution is possible, assume the manager choses the less expensive for the client. [Provide the solution as a number in thousand €, approximating at 0 decimal digit, withouth any measurement unit, e.g.: 18]

    Correct Answer
    24
    Explanation
    The activities that can be crashed to gain 2 days on the duration of the project are A, C, and E, of which C cannot be crashed.

    The marginal cost of decrease activity A of 1 week is:

    9 + 3 = 11 (9 from A and 3 from E)

    The marginal cost of decrease of one week E is 10. Therefore it is more cheaper to decrease E of 2 weeks (it is allowed).

    The price to be asked is: 10*2*1.2=24 thousand €.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 15, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Jun 26, 2012
    Quiz Created by
    Scannerdarkly
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.