PMP Exam Prep - (Focus On Quality Management)

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By PMPprepper
P
PMPprepper
Community Contributor
Quizzes Created: 1 | Total Attempts: 1,846
Questions: 7 | Attempts: 1,846

SettingsSettingsSettings
PMP Quizzes & Trivia

Prepare for PMP Exam


Questions and Answers
  • 1. 

    As a project manager, you are tracking the project work using a network logic diagram. You would like to enter an actual finish date in order to calculate float for a finished activity. How will this affect your ability to calculate float for the finished activity?

    • A.

      Finished activities will prevent float from being calcuated correctly unless the actual finish date is equal to the scheduled finish date.

    • B.

      Calculating free float and total float is typically not done for finished activities.

    • C.

      Once the activity is finished, the amount of total float will be converted to free float.

    • D.

      Once the activity is finished, the amount of total float will be converted to slack.

    Correct Answer
    B. Calculating free float and total float is typically not done for finished activities.
    Explanation
    Calculating free float and total float is typically not done for finished activities because float is a measure of flexibility or slack in the schedule. Once an activity is finished, it no longer has any flexibility as it has been completed. Therefore, calculating float for a finished activity is not relevant or necessary.

    Rate this question:

  • 2. 

    You are interviewing a candidate for a position as a Quality Manager on a  project. Which of the following qualifications should count towards experience in performing Quality Assurance?

    • A.

      Any project experience spent collecting requirements during Scope Definition

    • B.

      Any project experience spent writing test scripts that are mapped to requirements collected during Scope Definition

    • C.

      Experience in determining Quality Metrics within the Planning process of a project

    • D.

      Exoerience in performing Quality Audits during the Monitoring and Controlling process

    Correct Answer
    D. Exoerience in performing Quality Audits during the Monitoring and Controlling process
    Explanation
    The experience in performing Quality Audits during the Monitoring and Controlling process should count towards experience in performing Quality Assurance because Quality Audits are a key component of Quality Assurance. During the Monitoring and Controlling process, Quality Audits are conducted to ensure that project activities are being performed according to the defined processes and standards. This helps to identify any non-compliance issues and allows for corrective actions to be taken. Therefore, having experience in performing Quality Audits demonstrates a candidate's ability to assess and ensure the quality of project deliverables.

    Rate this question:

  • 3. 

    The following are not inputs to Perform Quality Control EXCEPT: 

    • A.

      Risk Register

    • B.

      Quality Control Measurements

    • C.

      Enterprise Environment Factors

    • D.

      Approved Change Requests

    Correct Answer
    D. Approved Change Requests
    Explanation
    Approved Change Requests are not inputs to Perform Quality Control because this process focuses on reviewing the quality of deliverables and ensuring that they meet the required standards. Approved Change Requests, on the other hand, are the outputs of the Perform Integrated Change Control process, where changes to the project are evaluated and approved. Therefore, they are not considered inputs to the Perform Quality Control process.

    Rate this question:

  • 4. 

    Root Cause Analysis, a type of process Analysis that helps identify a problem and it's causes in order to develop actions that will prevent the problem, is a Tool and Technique for which of the following Processes?

    • A.

      Perform Quality Assurance

    • B.

      Plan Quality

    • C.

      Control Costs

    • D.

      Monitor and Control Project Work

    Correct Answer
    A. Perform Quality Assurance
    Explanation
    Root Cause Analysis is a tool and technique used in the Perform Quality Assurance process. This process involves auditing the quality requirements and the results from quality control measurements to ensure that project activities are being executed correctly. Root Cause Analysis helps to identify the underlying causes of any quality issues or problems that may arise during the project. By understanding the root causes, the project team can develop appropriate actions to prevent similar problems from occurring in the future.

    Rate this question:

  • 5. 

    Early in the Planning process, the Project Manager identifed several risks that would result if certain project requirements were not met.  The project is now in the closing and several requirements were not met as predicted.  This situation can best be described by the following phrase: 

    • A.

      Risks were identified at the Work Package level, but not the Project Level

    • B.

      Quality was not achieved

    • C.

      Risk Thresholds were not set high enough

    • D.

      Quality Metrics were not adequately defined

    Correct Answer
    B. Quality was not achieved
    Explanation
    The given situation can be best described by the phrase "Quality was not achieved". This is because the project manager identified risks that would result if certain project requirements were not met, and now that several requirements were not met as predicted, it implies that the desired level of quality was not achieved.

    Rate this question:

  • 6. 

    The project sponsor is continually directing the Project Manager to continually improve quality, seemingly without regard to cost. The Project Manager wishes to identify the point at which increasing the cost of achieving the quality stops producing additional benefits. The Project Manager is applying which of the following Quality activities?

    • A.

      Continuous Improvement (Kaizen)

    • B.

      Marginal Analysis

    • C.

      Total Quality Management

    • D.

      Inverse Quality Benchmarking

    Correct Answer
    B. Marginal Analysis
    Explanation
    The Project Manager is applying Marginal Analysis. Marginal Analysis is a decision-making tool that helps identify the point at which increasing the cost of achieving quality stops producing additional benefits. It involves analyzing the additional cost incurred for each unit of improvement in quality and determining whether the benefits gained are worth the cost. In this scenario, the Project Manager wants to determine the point at which increasing the cost of achieving quality no longer adds significant benefits, indicating the application of Marginal Analysis.

    Rate this question:

  • 7. 

    A project manager is attempting to to vary each part of a four-step manufacturing process alone, and in combination with the other parts, to see which adjustments will result in the product staying within the Upper and Lower Specification limits. This technique is commonly known as:

    • A.

      Regression Analysis

    • B.

      Statistical Regression Sampling

    • C.

      Quality Auditing

    • D.

      Design of Experiments

    Correct Answer
    D. Design of Experiments
    Explanation
    Design of Experiments is a technique used by project managers to systematically vary each part of a manufacturing process alone and in combination with other parts. This technique helps to identify which adjustments will result in the product staying within the Upper and Lower Specification limits. Regression Analysis is a statistical technique used to model the relationship between variables, while Statistical Regression Sampling is a method used to select a representative sample from a population. Quality Auditing is a process of evaluating the quality management system of an organization. Therefore, the correct answer is Design of Experiments.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • May 04, 2011
    Quiz Created by
    PMPprepper
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.