1.
Which project management plan guides the creation of the detailed projectscope statement?
Correct Answer
D. Project scope management plan
Explanation
The project scope management plan defines the creation of the detailed
project scope statement. A, the charter, does include the preliminary project
scope statement, but not the detailed one the project scope management
plan defines. B, the project management plan, is a parent of the project scope
management plan. C is not a valid plan, so this answer is incorrect.
2.
Which one of the following is not needed to define the project scope?
Correct Answer
C. Risk management plan
Explanation
At this point, you won’t need, or likely have, the risk management plan
to define the project scope. A, B, and D are incorrect statements, as you’ll
need the project charter, organizational process assets, and the requirements
documentation to define the project scope.
3.
You are the project manager of the BHY Project. Your project customer hasdemanded that the project be completed by December 1. December 1 is anexample of which one of the following?
Correct Answer
A. Constraint
Explanation
This is an example of a project constraint.
4.
The lowest-level item in a WBS is called what?
Correct Answer
B. Work package
Explanation
The smallest item in the WBS is called the work package.
5.
You are working with the project team to create the WBS. There are someelements in the WBS that can’t be broken down yet. You and the team elect tobreak down these items later in the project as more details become available.This approach to creating the WBS is also known as what?
Correct Answer
D. Rolling wave planning
Explanation
This is a clear example of rolling wave planning.
6.
Your WBS is numbered in a hierarchical fashion for easy identification and reference. This numbering scheme is called what?
Correct Answer
A. Code of accounts
Explanation
The WBS numbering scheme is called the code of accounts.
7.
Which two items are parts of the scope baseline for the project?
Correct Answer
C. WBS and WBS dictionary
Explanation
The WBS and the WBS dictionary are two of three components of the scope
baseline. The approved detailed project scope statement is the third portion
of the scope baseline. Choices A, B, and D are all incorrect, as they do not
accurately define the scope baseline.
8.
Scope verification leads to what?
Correct Answer
B. Formal acceptance of the complete project scope
Explanation
Scope verification leads to one thing: formal acceptance of the complete
project scope. A, C, and D are incorrect choices, as defect repair, rework, and
inspection are not outputs of scope verification.
9.
What is the only tool and technique used during scope verification?
Correct Answer
A. Inspection
Explanation
Inspection is the only tool and technique used during scope verification.
10.
David, one of your project team members, has been making changes to hiswork, which, as a result, changes the project scope. David’s changes are alsoknown as what?
Correct Answer
C. Scope creep
Explanation
Undocumented changes are examples of scope creep. A, gold plating, is
when the project team adds changes to consume the project budget. B and D,
scope control defect and improvised scope composition, are not valid change
management terms.
11.
Which system defines how the project scope and the product scope can bechanged?
Correct Answer
A. Project scope change control system
Explanation
A. The only system that defines how project and product scope can be changed
is the project scope change control system.
12.
A change has been approved in Marcy’s project. All of the following must beupdated to reflect the change, except for which one?
Correct Answer
D. Defect repair review
Explanation
Defect repair and its review do not require a change request
13.
A project team member has, on his own initiative, added extra vents to an atticto increase air circulation. The project plan did not call for these extra vents,but the team member decided they were needed based on the geographicallocation of the house. The project team’s experts concur with this decision.This is an example of:
Correct Answer
B. Ineffective change control
Explanation
Even though the change is agreed upon, this is an example of ineffective
change control. The team member should follow the change control process
as defined in the project scope management plan. Choices A, C, and D are
incorrect choices.
14.
Which of the following is an output of scope control?
Correct Answer
B. Recommended corrective action
Explanation
Corrective actions are an output of scope control
15.
You are the project manager for the JHG Project. Your project is to create a newproduct for your industry. You have recently learned that your competitor isalso working on a similar project, but their offering will include a computer-aided program and web-based tools, which your project does not offer. Youhave implemented a change request to update your project accordingly. This isan example of which of the following?
Correct Answer
B. A change due to an external event
Explanation
B. This is a change due to an external event, the event being the product your
competitor has in their project.
16.
You are the project manager of a large project. Your project sponsor andmanagement have approved you to outsource portions of the project plan.What must be considered if a change request affects the procured work?
Correct Answer
B. Contractual agreement
Explanation
B. If a change to the project scope affects the procured work, the project
manager must consider the contract. This is because the change may affect the
existing contract the project manager and the vendor have entered into.
17.
A project team member has asked you what a scope statement is. Which of thefollowing is a characteristic of a project scope statement?
Correct Answer
D. Defines the project deliverables and the work needed to creates the deliverables
Explanation
D. The project scope statement defines the project deliverables and the
associated work to create those deliverables.
18.
One of the stakeholders of the project you are managing asks why you considerthe project scope statement so important in your project managementmethodology. You answer her question with which of the following?
Correct Answer
C. The project scope helps the project manager determine if a change is
within or outside of scope.
Explanation
C. The project scope statement can help the project management team
determine if a proposed change is within or outside of the project boundaries
19.
You are the project manager for a large construction project. The architecthas provided your project team with blueprints detailing the exact layout ofthe building your team will be creating. He insists that the team follow theblueprints as he’s designed them. The blueprints are an example of whichone of the following?
Correct Answer
A. Project specifications
Explanation
Blueprints are an example of the project specifications.
20.
Complete this sentence: Project scope management is primarily concernedwith defining and controlling ________________________.
Correct Answer
A. What is and is not included in the project
Explanation
A. Project scope management is primarily concerned with defining and
controlling what is and is not included in the project.