Cost Estimation In Project Management Quiz

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Jzc0811
J
Jzc0811
Community Contributor
Quizzes Created: 2 | Total Attempts: 3,515
Questions: 50 | Attempts: 1,618

SettingsSettingsSettings
Cost Estimation In Project Management Quiz - Quiz

How well do you understand cost estimation in project management? There are a lot of things that are needed to ensure that a project is carried out smoothly, and as it is common with every resource, there is an expense that needs to be incurred. Take this quiz and understand how to estimate your cost for each activity you undertake on the project.


Questions and Answers
  • 1. 

    Which of the following best describes analogous estimating?

    • A.

      Regression analysis

    • B.

      Bottom-up estimating

    • C.

      Less accurate

    • D.

      More accurate

    Correct Answer
    C. Less accurate
    Explanation
    Analogous estimating is less accurate than other estimating methods.

    Rate this question:

  • 2. 

    You are the project manager for the GHG Project. You are about to create the cost estimates for the project. Which input to this process will help you the most?

    • A.

      Parametric modeling

    • B.

      WBS

    • C.

      Project scope

    • D.

      Requirements document

    Correct Answer
    B. WBS
    Explanation
    The WBS is the input that can help you the most with the cost estimates.

    Rate this question:

  • 3. 

    You are the project manager for the JKH Project. You have elected to use parametric estimating in your cost estimating for the project. Which of the following is an example of parametric estimating?

    • A.

      $750 per ton

    • B.

      Historical information from a similar project

    • C.

      Estimates built bottom-up based on the WBS

    • D.

      Estimates based on top-down budgeting

    Correct Answer
    A. $750 per ton
    Explanation
    $750 per ton is an example of parametric estimating.

    Rate this question:

  • 4. 

    You are the project manager for a new technology implementation project. Management has requested that your estimates be as exact as possible. Which one of the following methods of estimating will provide the most accurate estimate?

    • A.

      Top-down estimating

    • B.

      Top-down budgeting

    • C.

      Bottom-up estimating

    • D.

      Parametric estimating

    Correct Answer
    C. Bottom-up estimating
    Explanation
    Bottom-up estimating provides the most accurate estimates. The project manager starts at zero, the bottom, and accounts for each cost within the project.

    Rate this question:

  • 5. 

    Your company has been hired to install the tile in 1,000 hotel rooms. All rooms will be identical in nature and will require the same amount of materials. You calculate the time to install the tile in each hotel room at six hours. The cost of labor for each room is calculated at $700. Your project sponsor disagrees with your labor estimate. Why?

    • A.

      You haven't completed one hotel room yet, so you don't know how long the work will actually take.

    • B.

      You have not factored in all of the effort applied to the work.

    • C.

      You have not considered the law of diminishing returns.

    • D.

      You have not considered the learning curve.

    Correct Answer
    D. You have not considered the learning curve.
    Explanation
    As the project team completes more and more units, the time to complete a hotel room should take less and less time

    Rate this question:

  • 6. 

    You are the project manager for a construction project to build 17 cabins. All of the cabins will be identical in nature. The contract for the project is set at a fixed cost, the incentive being that the faster the project work is completed, the more profitable the job. Management has requested that you study the work method to determine a faster, less costly, and better method of completing the project. This is an example of which one of the following?

    • A.

      Time constraint

    • B.

      Schedule constraint

    • C.

      Value engineering

    • D.

      Learning curve

    Correct Answer
    C. Value engineering
    Explanation
    Value engineering is a systematic approach to finding less costly ways to complete the same work.

    Rate this question:

  • 7. 

    You are the project manager for a technical implementation project. The customer has requested that you factor in the after-the-project costs, such as maintenance and service. This is an example of which one of the following?

    • A.

      Life-cycle costs

    • B.

      Scope creep

    • C.

      Project spin-off

    • D.

      Operations

    Correct Answer
    A. Life-cycle costs
    Explanation
    The after-project costs are known as the life-cycle costs.

    Rate this question:

  • 8. 

    Which one of the following provides the least accuracy in estimating?

    • A.

      Rough order of magnitude

    • B.

      Budget estimate

    • C.

      Definitive estimate

    • D.

      WBS estimate

    Correct Answer
    A. Rough order of magnitude
    Explanation
    The rough order of magnitude is the least accurate approach, since it may vary from -25 percent to +75 percent.

    Rate this question:

  • 9. 

    Which one of the following is true?

    • A.

      The cost management plan controls how change management affects the BAC.

    • B.

      The cost management plan controls how cost variances will be managed.

    • C.

      The cost management plan controls how the project manager may update the cost estimates.

    • D.

      The cost management plan controls how the BAC may be adjusted.

    Correct Answer
    B. The cost management plan controls how cost variances will be managed.
    Explanation
    The cost management plan controls how cost variances will be managed.

    Rate this question:

  • 10. 

    You have just started a project for a manufacturer. Project team members report they are 30 percent complete with the project. You have spent $25,000 out of the project's $250,000 budget. What is the earned value for this project?

    • A.

      10 percent

    • B.

      $75,000

    • C.

      $25,000

    • D.

      Not enough information to know

    Correct Answer
    B. $75,000
    Explanation
    The earned value is 30 percent of the project's budget.

    Rate this question:

  • 11. 

    You and your project team are about to enter a meeting to determine project costs. You have elected to use bottom-up estimating and will base your estimates on the WBS. Which one of the following is not an attribute of bottom-up estimating?

    • A.

      People doing the work create the estimates.

    • B.

      It creates a more accurate estimate.

    • C.

      It's more expensive to do than other methods.

    • D.

      It's less expensive to do than other methods.

    Correct Answer
    D. It's less expensive to do than other methods.
    Explanation
    Using bottom-up estimating is not less expensive to do.

    Rate this question:

  • 12. 

    What is the present value if an organization expects to make $100,000 four years from now and the annual interest rate is 6 percent?

    • A.

      $100,000

    • B.

      $79,000

    • C.

      $25,000

    • D.

      Zero

    Correct Answer
    B. $79,000
    Explanation
    The present value of $100,000 four years from now can be calculated by using this formula: present value = FV / (1 + i)n. FV is the future value, i is the interest rate, and n is the number of time periods.

    Rate this question:

  • 13. 

    You are the project manager for the construction of a new hotel. Before you begin the cost budgeting process, what is needed?

    • A.

      Cost estimates and project schedule

    • B.

      Cost estimates and supporting detail

    • C.

      EAC and BAC

    • D.

      A parametric model to arrive at the costs submitted

    Correct Answer
    A. Cost estimates and project schedule
    Explanation
    Cost estimates and the project schedule are inputs to the cost budgeting process.

    Rate this question:

  • 14. 

    You are the project manager of the MNJ Project. Your project is falling behind schedule, and you have already spent $130,000 of your $150,000 budget. What do you call the $130,000?

    • A.

      Planned value

    • B.

      Present value

    • C.

      Sunk costs

    • D.

      Capital expenditure

    Correct Answer
    C. Sunk costs
    Explanation
    Sunk costs are monies that have been spent.

    Rate this question:

  • 15. 

    You are the project manager of the JHD Project. Your project will cost your organization $250,000 to complete over the next eight months. Once the project is completed, the deliverables will begin earning the company $3,500 per month. Which of the following represents the time to recover the costs of the project?

    • A.

      Not enough information to know

    • B.

      8 months

    • C.

      72 months

    • D.

      5 years

    Correct Answer
    C. 72 months
    Explanation
    The time to recoup the monies from the project is 72 months. This is calculated by dividing the ROI of $3,500 per month into the project cost.

    Rate this question:

  • 16. 

    You are the project manager for a consulting company. Your company has two possible projects to manage, but they can only choose one. Project KJH is worth $17,000, while Project ADS is worth $22,000. Management elects to choose Project ADS. The opportunity cost of this choice is which one of the following?

    • A.

      $5,000

    • B.

      $17,000

    • C.

      $22,000

    • D.

      Zero, as project ADS is worth more than Project KJH

    Correct Answer
    B. $17,000
    Explanation
    The opportunity cost is the amount of the project that was not chosen.

    Rate this question:

  • 17. 

    You are the project manager for the CSR Training Project, and 21,000 customer service reps are invited to attend the training session. Attendance is optional. You have calculated the costs of the training facility, but the workbook expense depends on how many students register for the class. For every 5,000 workbooks created, the cost is reduced by a percentage of the original printing cost. The workbook expense is an example of which one of the following?

    • A.

      Fixed costs

    • B.

      Parametric costs

    • C.

      Variable costs

    • D.

      Indirect costs

    Correct Answer
    C. Variable costs
    Explanation
    This is an example of variable costs. The more students that register to take the class, the more the cost of the books will be.

    Rate this question:

  • 18. 

    You are the project manager of a construction project scheduled to last 24 months. You have elected to rent a piece of equipment for the duration of a project, even though you will need the equipment only periodically throughout the project. The costs of the equipment rental per month are $890. This is an example of which of the following?

    • A.

      Fixed costs

    • B.

      Parametric costs

    • C.

      Variable costs

    • D.

      Indirect costs

    Correct Answer
    A. Fixed costs
    Explanation
    This is a fixed-cost expense of $890 per month—regardless of how often the piece of equipment is used.

    Rate this question:

  • 19. 

    You are the project manager for the Hardware Inventory Project. You have a piece of equipment that was purchased recently for $10,000 and is expected to last five years in production. At the end of the five years, the expected worth of the equipment will be $1,000. Using straight-line depreciation, what is the amount that can be written off each year?

    • A.

      Zero

    • B.

      $1,000

    • C.

      $1,800

    • D.

      $2,000

    Correct Answer
    C. $1,800
    Explanation
    The straight-line depreciation takes the purchase value of the item, minus the salvage price of the item, divided by the number of time periods. In this instance, it would be $10,000 minus $1,000, or $9,000. The $9,000 is divided by five years and equates to $1,800 per year.

    Rate this question:

  • 20. 

    You are the project manager of the LKG Project. The project has a budget of $290,000 and is expected to last three years. The project is now 10 percent complete and is on schedule. What is the BAC?

    • A.

      $29,000

    • B.

      $290,000

    • C.

      $96,666

    • D.

      $9,666

    Correct Answer
    B. $290,000
    Explanation
    The BAC is the budget at completion, which is $290,000.

    Rate this question:

  • 21. 

    Your project has a budget of $130,000 and is expected to last ten months, with the work and budget spread evenly across all months. The project is now in month three, the work is on schedule, but you have spent $65,000 of the project budget. What is your variance?

    • A.

      $65,000

    • B.

      $39,000

    • C.

      $26,000

    • D.

      $64,999

    Correct Answer
    C. $26,000
    Explanation
    $26,000 is the variance. This is calculated by subtracting the actual costs of $65,000 from the earned value of $39,000. EV is calculated by taking the 30 percent completion of the project against the BAC. The project is considered to be 30 percent complete because it's slated for 10 months, is currently in month three, and is on schedule.

    Rate this question:

  • 22. 

    You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You are now 40 percent complete with the project, though your plan called for you to be 45 percent complete with the work by this time. What is your earned value?

    • A.

      $240,000

    • B.

      $270,000

    • C.

      $30,000

    • D.

      -$30,000

    Correct Answer
    A. $240,000
    Explanation
    The earned value is calculated by multiplying the percentage of completion, 40 percent, by the BAC, which is $600,000, for a value of $240,000.

    Rate this question:

  • 23. 

    You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You have spent $270,000 of your budget. You are now 40 percent done with the project, though your plan called for you to be 45 percent done with the work by this time. What is your CPI?

    • A.

      100

    • B.

      89

    • C.

      0.89

    • D.

      0.79

    Correct Answer
    C. 0.89
    Explanation
    The EV of $240,000 is divided by the AC of $270,000 for a value of 0.89.

    Rate this question:

  • 24. 

    You are the project manager for the Facility Installation Project. The project calls for 1,500 units to be installed in a new baseball stadium. Your team wants to know why you have not assigned the same amount of time for the last 800 units as you had for the first 500 units. You tell them it is because of the learning curve. Which one of the following best describes this theory?

    • A.

      Production increases as workers become more efficient with the installation procedure.

    • B.

      Efficiency increases as workers become more familiar with the installation procedure.

    • C.

      Costs decrease as workers complete more of the installation procedure.

    • D.

      Time decreases as workers complete more of the installation procedure in the final phases of a project.

    Correct Answer
    B. Efficiency increases as workers become more familiar with the installation procedure.
    Explanation
    The learning curve allows the cost to decrease as a result of decreased installation time because workers will complete more of the installation procedure.

    Rate this question:

  • 25. 

    Of the following, which one is the most reliable source of information for estimating project costs?

    • A.

      Historical information from a recently completed project

    • B.

      An SME's opinion

    • C.

      Recollections of team members that have worked on similar projects

    • D.

      Vendors' whitepapers

    Correct Answer
    A. Historical information from a recently completed project
    Explanation
    Of the choices presented, historical information from a recently completed project is the most reliable source of information.

    Rate this question:

  • 26. 

    Which of the following best describes analogous estimating?

    • A.

      Regression analysis

    • B.

      Bottom-up estimating

    • C.

      Less accurate

    • D.

      More accurate

    Correct Answer
    C. Less accurate
    Explanation
    Analogous estimating is less accurate than other estimating methods.

    Rate this question:

  • 27. 

    You are the project manager for the GHG Project. You are about to create the cost estimates for the project. Which input to this process will help you the most?

    • A.

      Parametric modeling

    • B.

      WBS

    • C.

      Project scope

    • D.

      Requirements document

    Correct Answer
    B. WBS
    Explanation
    The WBS is the input that can help you the most with the cost estimates.

    Rate this question:

  • 28. 

    You are the project manager for the JKH Project. You have elected to use parametric estimating in your cost estimating for the project. Which of the following is an example of parametric estimating?

    • A.

      $750 per ton

    • B.

      Historical information from a similar project

    • C.

      Estimates built bottom-up based on the WBS

    • D.

      Estimates based on top-down budgeting

    Correct Answer
    A. $750 per ton
    Explanation
    $750 per ton is an example of parametric estimating.

    Rate this question:

  • 29. 

    You are the project manager for a new technology implementation project. Management has requested that your estimates be as exact as possible. Which one of the following methods of estimating will provide the most accurate estimate?

    • A.

      Top-down estimating

    • B.

      Top-down budgeting

    • C.

      Bottom-up estimating

    • D.

      Parametric estimating

    Correct Answer
    C. Bottom-up estimating
    Explanation
    Bottom-up estimating provides the most accurate estimates. The project manager starts at zero, the bottom, and accounts for each cost within the project.

    Rate this question:

  • 30. 

    Your company has been hired to install the tile in 1,000 hotel rooms. All rooms will be identical in nature and will require the same amount of materials. You calculate the time to install the tile in each hotel room at six hours. The cost of labor for each room is calculated at $700. Your project sponsor disagrees with your labor estimate. Why?

    • A.

      You haven't completed one hotel room yet, so you don't know how long the work will actually take.

    • B.

      You have not factored in all of the effort applied to the work.

    • C.

      You have not considered the law of diminishing returns.

    • D.

      You have not considered the learning curve.

    Correct Answer
    D. You have not considered the learning curve.
    Explanation
    As the project team completes more and more units, the time to complete a hotel room should take less and less time

    Rate this question:

  • 31. 

    You are the project manager for a construction project to build 17 cabins. All of the cabins will be identical in nature. The contract for the project is set at a fixed cost, the incentive being that the faster the project work is completed, the more profitable the job. Management has requested that you study the work method to determine a faster, less costly, and better method of completing the project. This is an example of which one of the following?

    • A.

      Time constraint

    • B.

      Schedule constraint

    • C.

      Value engineering

    • D.

      Learning curve

    Correct Answer
    C. Value engineering
    Explanation
    Value engineering is a systematic approach to finding less costly ways to complete the same work.

    Rate this question:

  • 32. 

    You are the project manager for a technical implementation project. The customer has requested that you factor in the after-the-project costs, such as maintenance and service. This is an example of which one of the following?

    • A.

      Life-cycle costs

    • B.

      Scope creep

    • C.

      Project spin-off

    • D.

      Operations

    Correct Answer
    A. Life-cycle costs
    Explanation
    The after-project costs are known as the life-cycle costs.

    Rate this question:

  • 33. 

    Which one of the following provides the least accuracy in estimating?

    • A.

      Rough order of magnitude

    • B.

      Budget estimate

    • C.

      Definitive estimate

    • D.

      WBS estimate

    Correct Answer
    A. Rough order of magnitude
    Explanation
    The rough order of magnitude is the least accurate approach, since it may vary from -25 percent to +75 percent.

    Rate this question:

  • 34. 

    Which one of the following is true?

    • A.

      The cost management plan controls how change management affects the BAC.

    • B.

      The cost management plan controls how cost variances will be managed.

    • C.

      The cost management plan controls how the project manager may update the cost estimates.

    • D.

      The cost management plan controls how the BAC may be adjusted.

    Correct Answer
    B. The cost management plan controls how cost variances will be managed.
    Explanation
    The cost management plan controls how cost variances will be managed.

    Rate this question:

  • 35. 

    You have just started a project for a manufacturer. Project team members report they are 30 percent complete with the project. You have spent $25,000 out of the project's $250,000 budget. What is the earned value for this project?

    • A.

      10 percent

    • B.

      $75,000

    • C.

      $25,000

    • D.

      Not enough information to know

    Correct Answer
    B. $75,000
    Explanation
    The earned value is 30 percent of the project's budget.

    Rate this question:

  • 36. 

    You and your project team are about to enter a meeting to determine project costs. You have elected to use bottom-up estimating and will base your estimates on the WBS. Which one of the following is not an attribute of bottom-up estimating?

    • A.

      People doing the work create the estimates.

    • B.

      It creates a more accurate estimate.

    • C.

      It's more expensive to do than other methods.

    • D.

      It's less expensive to do than other methods.

    Correct Answer
    D. It's less expensive to do than other methods.
    Explanation
    Using bottom-up estimating is not less expensive to do.

    Rate this question:

  • 37. 

    What is the present value if an organization expects to make $100,000 four years from now and the annual interest rate is 6 percent?

    • A.

      $100,000

    • B.

      $79,000

    • C.

      $25,000

    • D.

      Zero

    Correct Answer
    B. $79,000
    Explanation
    The present value of $100,000 four years from now can be calculated by using this formula: present value = FV / (1 + i)n. FV is the future value, i is the interest rate, and n is the number of time periods.

    Rate this question:

  • 38. 

    You are the project manager for the construction of a new hotel. Before you begin the cost budgeting process, what is needed?

    • A.

      Cost estimates and project schedule

    • B.

      Cost estimates and supporting detail

    • C.

      EAC and BAC

    • D.

      A parametric model to arrive at the costs submitted

    Correct Answer
    A. Cost estimates and project schedule
    Explanation
    Cost estimates and the project schedule are inputs to the cost budgeting process.

    Rate this question:

  • 39. 

    You are the project manager of the MNJ Project. Your project is falling behind schedule, and you have already spent $130,000 of your $150,000 budget. What do you call the $130,000?

    • A.

      Planned value

    • B.

      Present value

    • C.

      Sunk costs

    • D.

      Capital expenditure

    Correct Answer
    C. Sunk costs
    Explanation
    Sunk costs are monies that have been spent.

    Rate this question:

  • 40. 

    You are the project manager of the JHD Project. Your project will cost your organization $250,000 to complete over the next eight months. Once the project is completed, the deliverables will begin earning the company $3,500 per month. Which of the following represents the time to recover the costs of the project?

    • A.

      Not enough information to know

    • B.

      8 months

    • C.

      72 months

    • D.

      5 years

    Correct Answer
    C. 72 months
    Explanation
    The time to recoup the monies from the project is 72 months. This is calculated by dividing the ROI of $3,500 per month into the project cost.

    Rate this question:

  • 41. 

    You are the project manager for a consulting company. Your company has two possible projects to manage, but they can only choose one. Project KJH is worth $17,000, while Project ADS is worth $22,000. Management elects to choose Project ADS. The opportunity cost of this choice is which one of the following?

    • A.

      $5,000

    • B.

      $17,000

    • C.

      $22,000

    • D.

      Zero, as project ADS is worth more than Project KJH

    Correct Answer
    B. $17,000
    Explanation
    The opportunity cost is the amount of the project that was not chosen.

    Rate this question:

  • 42. 

    You are the project manager for the CSR Training Project, and 21,000 customer service reps are invited to attend the training session. Attendance is optional. You have calculated the costs of the training facility, but the workbook expense depends on how many students register for the class. For every 5,000 workbooks created, the cost is reduced by a percentage of the original printing cost. The workbook expense is an example of which one of the following?

    • A.

      Fixed costs

    • B.

      Parametric costs

    • C.

      Variable costs

    • D.

      Indirect costs

    Correct Answer
    C. Variable costs
    Explanation
    This is an example of variable costs. The more students that register to take the class, the more the cost of the books will be.

    Rate this question:

  • 43. 

    You are the project manager of a construction project scheduled to last 24 months. You have elected to rent a piece of equipment for the duration of a project, even though you will need the equipment only periodically throughout the project. The costs of the equipment rental per month are $890. This is an example of which of the following?

    • A.

      Fixed costs

    • B.

      Parametric costs

    • C.

      Variable costs

    • D.

      Indirect costs

    Correct Answer
    A. Fixed costs
    Explanation
    This is a fixed-cost expense of $890 per month—regardless of how often the piece of equipment is used.

    Rate this question:

  • 44. 

    You are the project manager for the Hardware Inventory Project. You have a piece of equipment that was purchased recently for $10,000 and is expected to last five years in production. At the end of the five years, the expected worth of the equipment will be $1,000. Using straight-line depreciation, what is the amount that can be written off each year?

    • A.

      Zero

    • B.

      $1,000

    • C.

      $1,800

    • D.

      $2,000

    Correct Answer
    C. $1,800
    Explanation
    The straight-line depreciation takes the purchase value of the item, minus the salvage price of the item, divided by the number of time periods. In this instance, it would be $10,000 minus $1,000, or $9,000. The $9,000 is divided by five years and equates to $1,800 per year.

    Rate this question:

  • 45. 

    You are the project manager of the LKG Project. The project has a budget of $290,000 and is expected to last three years. The project is now 10 percent complete and is on schedule. What is the BAC?

    • A.

      $29,000

    • B.

      $290,000

    • C.

      $96,666

    • D.

      $9,666

    Correct Answer
    B. $290,000
    Explanation
    The BAC is the budget at completion, which is $290,000.

    Rate this question:

  • 46. 

    Your project has a budget of $130,000 and is expected to last ten months, with the work and budget spread evenly across all months. The project is now in month three, the work is on schedule, but you have spent $65,000 of the project budget. What is your variance?

    • A.

      $65,000

    • B.

      $39,000

    • C.

      $26,000

    • D.

      $64,999

    Correct Answer
    C. $26,000
    Explanation
    $26,000 is the variance. This is calculated by subtracting the actual costs of $65,000 from the earned value of $39,000. EV is calculated by taking the 30 percent completion of the project against the BAC. The project is considered to be 30 percent complete because it's slated for 10 months, is currently in month three, and is on schedule.

    Rate this question:

  • 47. 

    You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You are now 40 percent complete with the project, though your plan called for you to be 45 percent complete with the work by this time. What is your earned value?

    • A.

      $240,000

    • B.

      $270,000

    • C.

      $30,000

    • D.

      -$30,000

    Correct Answer
    A. $240,000
    Explanation
    The earned value is calculated by multiplying the percentage of completion, 40 percent, by the BAC, which is $600,000, for a value of $240,000.

    Rate this question:

  • 48. 

    You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You have spent $270,000 of your budget. You are now 40 percent done with the project, though your plan called for you to be 45 percent done with the work by this time. What is your CPI?

    • A.

      100

    • B.

      89

    • C.

      0.89

    • D.

      0.79

    Correct Answer
    C. 0.89
    Explanation
    The EV of $240,000 is divided by the AC of $270,000 for a value of 0.89.

    Rate this question:

  • 49. 

    You are the project manager for the Facility Installation Project. The project calls for 1,500 units to be installed in a new baseball stadium. Your team wants to know why you have not assigned the same amount of time for the last 800 units as you had for the first 500 units. You tell them it is because of the learning curve. Which one of the following best describes this theory?

    • A.

      Production increases as workers become more efficient with the installation procedure.

    • B.

      Efficiency increases as workers become more familiar with the installation procedure.

    • C.

      Costs decrease as workers complete more of the installation procedure.

    • D.

      Time decreases as workers complete more of the installation procedure in the final phases of a project.

    Correct Answer
    B. Efficiency increases as workers become more familiar with the installation procedure.
    Explanation
    The learning curve allows the cost to decrease as a result of decreased installation time because workers will complete more of the installation procedure.

    Rate this question:

  • 50. 

    Of the following, which one is the most reliable source of information for estimating project costs?

    • A.

      Historical information from a recently completed project

    • B.

      An SME's opinion

    • C.

      Recollections of team members that have worked on similar projects

    • D.

      Vendors' whitepapers

    Correct Answer
    A. Historical information from a recently completed project
    Explanation
    Of the choices presented, historical information from a recently completed project is the most reliable source of information.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Dec 20, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 15, 2016
    Quiz Created by
    Jzc0811
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.